Create classification of a Master Recipe

Hi Expert,
I need to create classification of a Master Recipe in C201 transaction. Can any one provide me the FM/ BAPI name which does the same.
Pls let me know if you want any further details.
Thanks

Hi Nabanita,
Is there any BAPI to upload Master recipe ( C201 transaction ) to SAP.
Please let me know.
Thanks,
Varma

Similar Messages

  • Creating Process Orders Without a Material and Without a Master Recipe

    Hi PP experts, anyone knows if it is possible and how to do create Process Orders Without a Material and Without a Master Recipe?
    Thanks!!

    Dear,
    If you want to use a cleanout recipe
    T code CORO
    create a order w/o material for rework qty
    Make the same entries as described under Creating a Process Order With a Material. Use OPJG config to have a default operation defined for the plant and order type combination.
    Please find the required details and conditions for creating process orders without master recipe.
    http://help.sap.com/saphelp_47x200/helpdata/en/89/a42cb3461e11d182b50000e829fbfe/frameset.htm
    Regards,
    R.Brahmankar
    Edited by: R Brahmankar on Oct 13, 2008 5:12 PM

  • Do you know the idoc for master recipe?

    Hi all.
    Do you know the idoc for maintain master recipe?
    I am looking for the idoc.
    I would like to create, update and delete master recipe with idoc.
    I have investigated about idoc,but can't find suitable idoc.
    (I did find it for BOM, but for recipe is nothing.)
    Thank you in advance..
    Satoru

    Hello,
    As far as I can see there are no BAPI's or IDOC's available to upload Master Recipe data.
    A suggestion would be to use the batch input technique to upload the master recipe master data. You find the documentation of the batch input recorder etc. via the menu path System -> Services -> Batch input -> Recorder
    I hope it helps,
    Regards,
    Marcelo

  • Creation of Process Order without assigning master recipe

    Hi,
    I want to create a process order without having default master recipe for the given material or default operation for the given order type. I want the user to select the master recipe manually in process order. We do not want to use production version also.
    We can define the default operation for the order type (OPJG) so that we can create a process order. I do not want a default operation in the process order but the user should select a valid master recipe. If we have default operation in the process order, it serves no purpose as it is never used anywhere.
    Is there any way we can achieve this?
    Regards,

    Hi,
    Please find the required details and conditions for creating process orders without master recipe.
    http://help.sap.com/saphelp_47x200/helpdata/en/89/a42cb3461e11d182b50000e829fbfe/frameset.htm
    Regards
    Kannan

  • Master recipe not pickedup automatically

    Hi all,
           While creating process order the Master Recipe is not picked up in the master data tab....BOM and PV no are shown but not the Master Recipe...Is there any customization for picking up Mater Recipe automatically in process order....????
    Regards,
    Joseph.

    Dear
    Goto COR4-Select Order Type and plant-Double Click -Look at Master Recipe Selection set up -It should be set to Master Reciepe Selection ( Autmocatically ) not manually .
    Re-set this and check with a process order creation in COR1
    Regards
    JH

  • Process order creation without master recipe creation

    Hi, i have created a finished product and i dont want to create the bom and master recipe for this finished product. when i create the process order for this material, i want system to copy the master recipe of the similar products either manually or automatically. please advise how to achieve the same.

    Dear Raju,
    Check these threads,
    Re: Create Process order without Production Version
    Production Order for a material without BOM and Routing
    Regards
    Mangalraj.S

  • CREATING MASTER RECIPE

    Can u tell me the procedure to create master recipe of a SFG material by copying existing master recipe.Please guide me on that .It is urgent.

    The creation of Master Recipe by Copying from another is as follows,
    Steps:-
    1) Enter material Number,Plant and Profile
    2)Click on Recipe in Menu Bar and choose Template
    3) Select Master Recipe
    4) Give the Group and Group Counter number from where u want to copy
    5) enter,give status
    6) now proceed as normal
    Regards
    Chitradeep Dutta

  • Is it Necessary to create production version if  using master recipe

    our industry Process industry
    we are using Master recipe for Production
    is it necessary to create production version

    Hi Krishna,
    Production version is essential to mantain if you have a PP-PI industry scenario.
    However, if you have not mantained it, you can still create a process order. Process order first searches for the production version (automatically/ manually) depending on the configuration settings.
    If you have not mantained it, system would throw a SAP standard information message, "Material XXXXX: Production Version not mantained".
    If system is not able to select valid master recipe / version.  it would look for default values for operation in the master recipe settings and would try to create a operation.
    Please see the following link:
    http://help.sap.com/saphelp_470/helpdata/en/ee/641c181bed11d29bfe080009b31c68/content.htm
    Method for Selecting Alternative Bills of Material
    Indicator determining the selection of the alternative BOM when requirements are exploded in material requirements planning.
    Use
    With Selection by order quantity, the system chooses the alternative BOM into whose lot size range the order quantity falls. The lot size range and area of validity of the BOM apply.
    With Selection by explosion date, the system chooses the alternative BOM into whose area of validity the date falls according to the setting BOM via dates.
    With Selection by production version, the system chooses the alternative BOM defined in the valid production version. The lot size range and area of validity of the production version apply.
    With Selection only by production version, the system chooses the alternative BOM defined in the valid production version. The lot size range and area of validity of the production version apply.
    If no production version is found, no production orders or process orders can be created.
    BR
    Rahul

  • BDC for C201(Master Recipe Create)

    Dear,
    Please help me in the following situation:
    I have written a BDC for transaction code C201 for Master Recipe Creation. Its running ok.
    But I have doubts like
    for the 1st table control:
    1) if for one operartion there are more than 1 phases
        then what precautions are needed for page down.
    for the 2nd level inner table control:
    1) I am in the process of coding pagedown for this 2nd table control. If I have to code for it what all precautions will I have to take?
    And in total what all precautions will I have to take?
    How feasible is this BDC?
    I have searched for BAPI, but did not find one.
    Kindly help me. I am under client pressure.
    Thanks.
    Regards,
    Shambhavi.
    Edited by: Shambhavi Salunkhe on Jun 23, 2008 9:40 PM

    Hi,
    In C201 transaction we have a table control in the operations screen. below the table control we have some push buttons and a input text field, we can make use this field to handle the table control. If you are insertinga first operation, enter the value in first row of the table control. for the second operation onwards enter max valye like 99999 in the input text box and click on enter. all the previous rows will scroll up and always second row of the table control will be free, so you can put the data in the second row. in the same way you will have some button to handle the other table control too .I hope this will help You
    Thanks,
    rajinikanth
    Edited by: Rajinikanth G on Jun 23, 2008 6:53 PM

  • Master recipes operations not getting transfered in SNP PDS to APO from R3

    Hello APO Gurus,
    I am trying to transfer SNP PDS for master receipes from R3 to APO.
    Issue description::
    The operation is not getting transfered correctly , some system default operation "010 generated Operation (from Planned Delive)" is getting generated in APO, also activity and resource capacity is not getting transfered. This situation exist for one plant 1000, for other plant 1100 the SNP PDS created correctly.
    i have following points:
    1. Is there some customizing setting missing on R3 or APO side  for plant 1000 tbefore SNP PDS transfer
    2. What need to be checked on master recipes data in R3,
    i have checked on below points
    1. FG Materials and all the Component Material to be in APO in a Active Integration Model.
    2. BOM & Routing and Production Version setup correctly.
    3. The Routing Operations have to Relevant to 'SCHEDULING'.
    4. Try deleting the existing Integration model for materials & re-create new IM & activate.
    Please help me to send SNP PDS correctly to APO to take heuristic run.
    Regards
    Gajendra
    Edited by: Gajendra_APO on Aug 23, 2011 1:14 PM

    Hi,
    It is good that you have given your already checked points.
    Please check the following things also and try to retransfer the PDS.
    1. Check your resource in ECC, whether you have maintained the Process formula.
    2. Check you have maintained some values in Master Recipe for processing time
    3. Check whether the resource has been transferred for your plant 1000 to APO and an active IM exists.
    4. Also check the type of the resource transferred to APO. It should be a single-mixed/ multi-mixed or bucket resource.
    Hope this will help you to solve the issue.
    Regards,
    Manimaran M.

  • Master Recipe without material

    Dear PP Gurus,
    I have one query.
    I want to create master recipe without material, i have created the same.
    Now while creating process order it is giving error,
    BOM for material 500000010 does not contain any valid items
    Message no. CO636
    please guide
    thanks in advance
    kailash thakkar

    Hi Kailash,
    What is mean by
    I want to create master recipe without material, i have created the same.
    What's the reason behind it.
    Regarding error CO636,
    - Check your BOM of that 500000010 might be components are missing over here.
    or
    - might be From to To lot size of BOM is not match with your Process order qty.
    or
    - Also check Valid From to To Date of your BOM.
    Regards,
    Dhaval

  • Material Assignment in Master recipe

    Hi,
    Is there any FM/BAPI to assign material into a master recipe? Currently, we are using BDC to call C202 transaction for this purpose. This process takes long time for material assignment which leads to performance issue.
    Thanks in advance
    Senthil Kumar A

    In LSMW , object BUS1012 is offered for routing creation and change .
    Unfortunately there is no object for master recipe creation & change and there is no standard batch input, nor BAPI/IDOC, nor   direct input. You should create your own batch input or CATT.
    Here is a possible procedure:
    Please record a Batch-Input with transaction SHDB and try if this work. If not please try with TOFF as described in the notes.
    Read carefully SAP note 142022.

  • Master Recipe details\ Inspection details based on the ECR number

    HI All,
    Could you please help me in finding one FM which gives Master Recipe details\ Inspection details based on the ECR number which is created in CC31.
    In the Transaction CC31 for a given Change Number,  there is a Master Recipe and Inspection in the Objects button -> Task list . We need Master Recipe and Inspection details associated with that particular change number.
    Awaiting your response
    Thanks,
    Chetan

    HI,
    Check this FM MRTRS300_MASTER_RECIPE_READ

  • PI characteristics in Master Recipe

    Hi,
    I would like to update the Process Instruction characteristics in a Master Recipe using Change Master (CC01) via BDC.Now when there is a change in one of the PI characteristics, my program updates the PI characteristics in the Master Recipe via BDC by creating a new Change Master, but in case the user again runs the same program after updating the PI characterestics using a different Change Master, all the the relevant rows are getting disabled, thereby not making it possible to either enter or modify any values in future.
    Could you please let me know why this happens and how to over ride this problem ??
    Thanks in Advance.
    Lakshmi.

    Raju Garu,
    In C201 or C202 select the Phase for which you wanted to have QM, then press CtrlShiftF2 or from Menu Goto->Quality Planning->Inspection Characteristics, here you need to assign the MIC. You a control key relavant for QM in this phase.
    Regards,
    Prasobh

  • PI charactersitics in Master Recipe gets disabled.

    Hi,
    I would like to update the Process Instruction characteristics in a Master Recipe using Change Master (CC01) via  BDC.Now when there is a change in one of the PI characteristics, my program updates the PI characteristics in the Master Recipe via BDC by creating a new Change Master, but in case the user again runs the same program after updating the PI characterestics using  a different Change Master, all the the relevant rows are getting disabled, thereby not making it possible to either enter or modify any values in future.
    Could you please let me know why this happens and how to over ride this problem ??
    Thanks in Advance.
    Lakshmi.

    Hi
    To activate ECN for Master recipe u need to set the Following
    1) In OPN0 - Default values for Master recipe choose the Profile with which u want to create the Master recipe and Click on details > In the Change Parameters at bottom select "with Change Number" for Change Rule and SAVE
    2) In OP5A - Select the Screen Group PP/PI/QM task lists: header screens and tick *Req * for the field Change Number (PLKOD-AENNR) and SAVE
    Now when u Creating New Master recipe system will give Error if no change no assigned
    Pl refer the link for more details
    [http://help.sap.com/saphelp_dimp50/helpdata/en/89/a4200b461e11d182b50000e829fbfe/content.htm]
    Regards
    Brahmaji

Maybe you are looking for

  • New Hardrive and now blank screen with sleep light on

    My warranty ran out on one of my mbp's, so I decided to install a new hardrive in one. I went through all the steps, and was very cautious. Now when I turn on the laptop the screen is blank and the sleep light stays on the entire time. I hear the cd-

  • How to not run a gateway instance if the target server is down

    I have a DirectoryWatcher gateway instance that runs every 10 min looking to do a series of actions when a file is added to a directory on another server. This other server is down periodically and my gateway instance fails. Then when the server come

  • Is there a problem using Acrobat Reader plugin Find with Mac OS X v10.7 Lion?

    I've recently noticed that the Find function is not working when I am viewing a pdf with Safari 6.1.1 and OS 10.7.5. I get a "Not Found" result no matter what I enter, even when I'm sure the search phrase is in the pdf. Is there a preference in Safar

  • InDesign won't Startup Mac 10.8.2

    I saw other discussions regarding this but couldn't find an answer that worked for me. I already tried creating a new user and renaming my preferences - neither worked. Here's the error message I get: http://pastebin.com/YmkR7czk I have CS5 InDesign

  • PUBLISHING OC4J JSP as web portlet

    I have developed a JSP page in OC4j and want to publish this page on portal 3.0.9 as web portlet. I have created web provider and registered this page as portlet. When I view the portlet it comes as a Blank Page. Can anyone tell me how to publish a J