Dear Eagle,
When Blocked for Purchasing, system wont allow to create Source List also below error message is throwing,i tried practically.
Not possible to generate any source list records
    Message no. 06717
Diagnosis
    The system was not able to determine any procurement information (i.e.
    purchasing info records or outline purchase agreements) for the
    material(s).
System Response
    No source list records have been generated.
Procedure
    If procurement information does exist for the material, check the
    selection criteria you entered (e.g. material or plant number).
I know system wont allow to create source list also but you saying system allow,thats the reason i tried practically.
we canot do any funtions realted of procuring i mean combination of Purchasing organization.
may be your dout is this only
Prem

Similar Messages

  • Is it possible to creat Shoppping cart for Blocked vendor in R/3

    Hello all,
    is it possible to create shopping cart for blocked vendor in R/3. we are using extended classic scenario with SRM 5.0. when i am trying to do this vendor is not visible in vendor list. Am i missing somthing???
    if it is not possible in standard set up...what exactly i need to do.
    my requirement is that i should create shopping cart and then PO for posting block vendor in R/3 ( i know that we can do it in R/3)
    how to achieve this in SRM 5.0 please guide.
    Thanks
    Rupesh Mundhada

    There are possibly three types of blocks for a vendor in R3
    1. All company code are blocked for vendor
    2. Selected company code is blocked for vendor
    3. Vendor if blocked for the purchasing organization
    But SRM allows only Central Locking and Purchasing Organizations level locking to be replicated from R3 - MM. So If the vendor is only blocked for a selected company code it will be still possible to create the shopping cart successfully, followed by purchase order; and PO will be issued to Vendor also; but it will not be replicated until and unless the block at the selected company code level is removed.
    This is not wrong; though you will be able to change them as per your business need. The reason is Selected Company Code level block is only used by finance people to stop payment to vendors because of some reasons like exceeding the limit or anything else.
    Please reward points if you find it useful.

  • Source list for service vendors

    Dear friends,
    How to maintain the source list for service wise for service vendors.
    And for what purpose standard service catalog is maintained.Please suggest
    Regards,
    Canand

    U CAN NOT MAINTIN THE SOURCE LIST FOR SERVICE AS IN THE INTIAL SCREEN OF SOURCELIST SYTEM ASK FOR THE MATERIAL CODE

  • Source List for Material Group

    Hi All,
    How do I maintain a source list for a material group.? Since ME01 requires a material, I cannot create source list in this tranasction.
    The client want a the Source (for material Group) to be assigned automatically in PR assignment step.
    Again, within a material group there can be several infor records, For example:
    Mater Group: Office Supp.....I can have two infor rec for the same vendor....one with "Short Text" Notepad and another info rec with "Short Text": Paperclips. Or the second info record could be a different vendor also.
    How could the system know which one to assign as a source since it's the same material group (one for Notepads and the other for paperclips)??
    Thanks in advance

    Hi duke,
    In SAP we have a choice of creating source list for a "Material Group ". Following is the method.
    You may have the outline agreements related to material group rather than a single specific material - For ex. outline agreement with a item category M( Material unknown) or      W ( material group).In doing so you can decide whether to exclude or include certain materials of the relevant material group by means of the source list.
    To create the source list for a material group proceed as follows.
    1) On the outline agreement overview screen, select the items for which you wish to enter the source list record & choose Item --> Maintain source list
    2) To exclude the particular material keep the "Exclusion" indicator set against a material with a validity period.
    I hope this will be useful to you.
    Vivek

  • Create Vendor Inforecords and source list for material

    Hi All,
    senario:I have to create vendor Inforecords and source list for new material as copy of reference material.
    There are various FM's available to read inforecord, source list but as reuirement is to copy these things from reference materil and create same for new material.
    Can you people suggest any way to achive these functionalies through any FM, BADI or any other way...
    Looking forword for your reply..
    Regards,
    Rahul

    Hi All,
    Can we use FM MGW_COPY_INFORECORDS to create inforecords for new material.
    Just to cross check, as i m not sure about use of this FM.
    Regards,
    Rahul

  • Problem creating source list

    Hi
       We are on ECC 5.0 and in one of our ABAP programs create a PIR as a first step using ME11 BDC call and then go ahead to create a sourcelist for the material + plant and the vendor ( for which PIR was created in the first step ) .
    To create source list we use the following function modules ( fms )  in sequence
    ME_INITIALIZE_SOURCE_LIST
    ME_DIRECT_INPUT_SOURCE_LIST
    ME_POST_SOURCE_LIST_NEW
    What we observe is that - the ME_DIRECT_INPUT_SOURCE_LIST fm always raises an abort message - ' No PIR exists for the material and vendor ' even though PIR is created in the first step and we check for its existence before we call the fms for the source list. However if we introduce a wait for upto 15 seconds after the PIR has been created the sourcelist creation goes through.
    Any idea why the above is happening. Similar situations faced with source list creation - shared is appreciated. Correct answers helping me solve this problem will be promptly rewarded

    Hi Karthik,
    System takes some time to COMMIT all the work thats why it's happening.
    Keep the WAIT FOR UP TO <reasonale seconds value> SECONDS in your code.
    Regards,
    Atish

  • Source List for Standard and Subcontracting Info Record

    Dear Sir and Madam,
    We have scenario where nart A could purchase with Standard PO or Subcontract PO.
    We  have following 2 Standard Info Record and 2 Subcontract Info Record.
    Standard InfoRec 1 for Nart A to Vendor 001 --Fixed Vendor
    Standard InfoRec 2 for Nart A to Vendor 002
    Subcontract InfoRec 1 for nart A to Vendor 003 - Fixed Vendor
    Subcontract InfoRec 2 for nart A to Vendor 004
    We have the problem here, how can we set the fixed vendor in Source List, for Standard PO using vendor 001 and Subcon using Vendor 003?
    Thank you very much,
    Regards,
    CW

    In source list only one vendor can be assigned.
    If u want to assign 2 or more vendor, try using Quota Arragement.
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/f4/7d267944af11d182b40000e829fbfe/frameset.htm
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/75/ee115f55c811d189900000e8322d00/frameset.htm

  • Source List for MRP Area

    Is there a possibility to maintain source list for MRP purposes
    at storage Location level? We receive requirements from a couple
    of our subsidaries and we were consolidating this to be a single
    requirement for our suppliers, however this has changed we have
    to now show each subsidary's requirements individually. We
    currently only use a single plant, previously we created
    additional plants for this and maintained a separate source list
    for each. Is this the best way to represent and run MRP for each
    subsidary? Thanks.

    Dear Kennedy,
    Source list for Storage Location level not possible!!
    An MRP area represents an organizational unit for which you can perform material requirements planning separately.
    An MRP area can include one or several storage locations of a plant or a subcontractor. You can define MRP areas in a plant.
    By defining MRP areas, you can perform MRP for each area. This means the right quantity of materials can be provided on time for each area, such as a production line, a storage location for spare parts, or subcontractor stock.
    Bye,
    Muralidhara

  • Source List for Services

    Hi experts,
    I have two queries-
    a. Can we maintain source list for services created through AC01 transaction? If yes how?
    b. We are currently using auto PO functionality for Material PR using ME59. Can we do auto PO for service PR also? How
    Your explanatory reply will be rewarded with full pointsw.
    Regards,
    santosh

    Dear Dheeraj,
    Thanks for your reply for my first question. But can you through some light on the second question? Source list is a madatory element to set up an auto PO (ME59). If we cannot maintain source list how to use auto PO functionality for Service.
    Regards
    Santosh

  • List of blocked vendors

    Hi,
    Any report to see the list of blocked vendors.(at company code level & pur org level)
    Regards
    sunil

    Hai;
    You Can get this Report Using t.code MKVZ.
    just execute by giving the Purchase organisation.
    It will list out all the vendors in that Purchase organisation,with all the details.
    there one field (B) is there indicating the Blocked vendor.
    You can also sort the list based on that Block Indicator.
    ok
    Hope You are clear and this will help you better.

  • How we create Schema group for every vendor?

    If we have multiple vendors/transporters, how you configure pricing procedure for each vendor what is the process of creating Schema group for every vendor?
    Thanks in advance
    Suresh

    hi suresh,
    you create Pricing procedure, and then you create Vendor schema group; and purchasing schea group.
    for your scenario you will create N number of vendor schema groups.
    follow this menu path:
    spro --> materials management --> purchasing --> conditions --> define price determination process --> Define schema determination --> define caluculation schema for standard purchase orders -->
    in that screen:
    you maintain entries in the combination of
    purchasing org schema group  -- vendor schema group -- pricing procedure.
    for your scenario, you maintain N number of vendor schema groups and assign it to procing procedure.
    hope this may help you,
    Regards
    srinivas

  • Source list mass blocking of vendor

    dear all,
    ply give me transaction code for source list in which i can block vendors.
    i have created an LSMW tool also but it creates an double entry in the transaction ME01.
    we have even crated BDC but there also same error is occuring.
    so is there any other ways for doing mass changes
    regards
    amey

    One option is thru ME05 transaction, which is generate source list.
    You get a list, there you can filter (e.g. by vendor) and then set block indicator.
    Alternative, if you just want block the vendor, then use MK05 and block this vendor for procurement,
    And about your LSMW and BDC, you are just not hitting the existing source list records, hence you create new ones. You probably have to enhance the key. Lookup table EORD to see what you may need to hit an existing record.

  • Purchase order is creating even for blocked vendors

    Dear Friends,
    FI guys have blocked the vendor for some reason.
    But when we select the blocked vendor in PO creation screen (ME21n), it allows us to create the PO without showing any error message. Based on that, even it is allowing to create service entry sheet/GRN document number. Only during MIR7/MIRO invoice entering stage, it is showing the error message.
    Could you please let me know how to resolve this issue at the PO creation stage itself - any sap note number/workaround procedure/providing any error message etc.,
    Regards,
    Dwarak.

    FI team might have blocked at company code level.
    However it will allow you to make PO's but you cant make the payment against that vendor.
    If you block it at PORG level you ll not be able to do the Po's anymore.

  • PO is creating for blocked vendor.

    Hi Xperts,
    I found a case where, we have a blocked vendor at pruchase organization, however the po is still creating for same vendor through automatic PO by ME59N. and not allowing to create PO manually through ME21N.
    Please help....
    Thanks in advance

    Hi,
    please check once again from XK06
    You need to select company code & purchasing Org and then under deletion flags select options as "all areas", Selected company code","selected Purchase Org".
    Vendor should block for all company codes and for all purchase org.
    Regards,
    Sandesh Sawant

  • Mail to be trigger for blocked vendors during F110 execution

    Hi Experts,
    We have blocked the vendors as per our requirement and while executing F110(4.6C version),it is ensuring that no payment is made to the respective vendors.Even we are able to see the blocked vendors in Exception log.
    But as per my requirement there should be email to be trigerred picking up all the blocked vendors while executing the payment run F110.
    We have created one variant to the program called "ZRFFOUS_C" by copying the "RFFOUS_C",and configured to one payment method called "I" at FBZP(country code level).
    Details for variant are Company Code,Payment Method(A to Z),House Bank,Account ID,Check lot.
    In that program at GET REGUH i am collecting all the vendor which comes for payment and seperating the blocked vendor in one table and trying to send mail
    Now the mail is not triggered properly..
    is it becoz we have done it a wrong way or some configurations needs to be done
    we have tried sending email from SAP directly it is working fine
    and more over we need to send the mail irrespective of bank account,lot number , account id considering we are about to create each and each variant for it. we have about 12 to 13 bank account so creating 12 programs will occupy lots of bytes is there any way to avoid this
    please throw  light on this
    with regards
    s.janagar

    it is due to some configuration and not becoz of coding

Maybe you are looking for