Creating a planned order with error "Material requires configuration"

Dear All,
I am facing a problem for creation of a planned order with error "Material requires configuration".
To follow the note 180317, I change Account Assignment Category to "U" (Unknown).
However, the system still does display the same error.
Could you please help provide possible solution for this?
Regards,
Phong

See also the following blog post:
Configurable planned order for material variants: Exception "53: No BOM explosion due to missing configuration"
BR
Caetano

Similar Messages

  • PPDS Planned orders with setup driving requirements in R/3

    Hi Gurus -
    We plan Finished Goods and Semi-FG in APO and send the planned and process orders over to R/3. We use the change-over matrix(set-up)matrix to create the set-up times for the finished good planned orders.
    For a material I have 24 hours change-over time. Lets say material runs on tuesday 3 PM, the setup time is 24 hours before that.
    Setup time: Monday 3 PM to Tuesday 3 PM
    Run Time: Tuesday 3PM onwards.
    Unfortunately the Packaging requirements are being shown on Monday itself. While I have setup or change-over time, I don't really need the packaging materials on monday. So what can we do to avoid this?
    Basically as soon as the APO planned order hits R/3, the BOM in R/3 is being exploded based on the order start date/time and not based of actual runtime of the order.
    For MRP folks, its misleading since the packaging items are not really needed on monday.
    Any help on this will be greatly appreciated.
    Regards
    Rajesh

    Hi Varun,
    Have you mapped setup and run as two activities in same resource or seperate operations all together.
    If compoenents are assigned to run then are dates getting calculated correct ly in APO and only getting chaged in ECC?
    In ECC there is configuration for production/process order   under scheduling parameters for production order where you can decide whether component should be assigned to run activity or set up activity but unfortunately this config is not available planned order.
    If you have defined set up and run as seperate operation then there shold not be problem check config in ECC
    Define scheduling parameters for planned order- adjust dates- adjust schduling should be adjust basic date and dependent requirement to operation date.
    Regards,
    Santosh

  • Creating planned orders with BAPI_MOSRVAPS_SAVEMULTI3

    Dear all,
    I have to create planned orders in our APO-system ... This works fine with function BAPI_MOSRVAPS_SAVEMULTI3, until I try to create a planned order with a configurable material ... I added values to the following tables: cfg_headers, cfg_instances and cfg_values but still I am not able to create a planned order ... Maybe I don't fill the correct fields in the mentioned tables ? Can anyone tell me which fields they fill to create planned orders with configurable materials ? I used the fields that are required according to the SAP-help, but it seems that my values are possibly wrong ... Maybe an example can help me too ?
    Thanks in advance !!!
    Greetz,
    Kurt.

    Hello Babu,
    I am facing the same error in BAPI_PIRSRVAPS_DELMULTI. Could you revert with the solution if you have got one.
    Thanks,
    Ankit

  • How to cummulate sales orders for creating one planned order.

    Hello friends,
    My scenario is make to stock. I use sales orders for creating plan only. I want to cummulate all sales orders of one finish material and create one planned order  for that material when i run mrp. How can i do this?
    Thanks

    Kiran,
    What is the planning strategy you are using?
    Does all the sales order requirment same? If it is same then it is possible. Please explain more in details. If not you need to look at using some perodic lotsize procedure to combine requirments. Like "Daily", Weekly" "Month" etc..
    Regards,
    Prasobh

  • Creating SNP planned order using ''BAPI_MOSRVAPS_SAVEMULTI3'

    Hi Experts,
                      I am new to SAP-APO, kindly clarify my question. I am using 'BAPI_MOSRVAPS_SAVEMULTI3' with source of supply PDS for creating SNP planned order by passing 'EE' in the  table parameters 'ORDER_HEAD-MASTER_ATPCAT'. It is creating a planned order which is PPDS planned order with number range starting from '1000...' rather than creating SNP planned order with number range starting from '8000..'. Please let me know what might be the reason for the BAPI misbehaving incorrectly. Also kindly let meknow what are specific parameters to pass to above bapi to create SNP planned order.

    Hi,
    The BAPI BAPI_MOSRVAPS_SAVEMULTI3 is used for creating PPDS inhouse orders.
    You will have to use BAPI_MOSRVAPS_CREATESNPORDER for SNP inhouse orders creation from SNP PPMs( there is no explict mention of SNP PDS- you may please check).
    Regards
    Datta

  • Error message while creating production order with KMAT material strategy25

    Hi PP Gurus I am running variant configuration cycle...Strategy 25, Custermer Req KEK (KMAT Matrl)
    Sales order & MRP Picked the components correctly as per the dependencies
    written. So Planned order generated against sale order.
    When I tried to convert planned order to Production order...I am getting the
    below error message..
    Error Message:
    You cannot make an assignment to make-to-order stock Message no. CO684
    Diagnosis The component cannot be allocated to an individual stock because
    make-to-order production and engineer-to-order production cannot be executed
    with this order.
    A possible cause is that you are trying to create an order with reference to a
    sales-order/project, where an account assignment to a sales order/project is not
    allowed in the settlement profile that is assigned to the chosen order type.
    This is inconsistant.
    System response The following responses are possible:
    Order processing is cancelled.
    The system resets the special stock indicator back to the original value.
    Procedure Choose another order type.
    I used order type with SD1 as settelement profile.
    OVZG: default 046, settlement profile = SD1
    OPJH: Settlement profile = SD1
    Plz through some light on this if u have worked on Variant Configuration/MTO
    settlements.
    Question:
    1) Is creation of production order with KMAT material supported by SAP?
    2) If yes, why the above error occurs?
    Waiting for Ur reply
    With Best Regards

    Dear R.Brahmankar,
    I have check on the note, but it is not relevant to ecc6. The current system default setting is :
    Standrad setting for reqt class 046
    Special Stock E
    Acct Assgt Cat. M
    Valuation M
    Settlmt Profile SD1
    However if I change the Acct Assgt Cat. from M to E. It resolve the problem. I would like to know is this the right solution?
    Config in Acct Assgt M
    Consumption Posting = E
    Config in Acct Assgt E
    Consumption Posting = '  '
    In F1 key of Consumption Posting field it shown following:
    To flag the sales order item as cost- and revenue-carrying, enter an "E" (settlement via sales order).
    If you do not wish to flag the sales order item as cost- and revenue-carrying, do not enter anything.
    Dependencies
    If you are working with nonvaluated sales order stock, always flag the sales order item as cost- and revenue-carrying.
    If you are working with valuated sales order stock:
      In the case of complex make-to-order production, flag the sales order item as cost- and revenue-carrying
      In the case of sales-order-related mass production, do not flag the sales order item as cost- and revenue-carrying
    Should we change to E?
    Regards,
    Ong

  • Problem when creating planned order with MRP run

    Hello,
    I create a material with a fix reorder point, MRP type VB. When I run MRP with MD03 on this material I have several problems :
    - planned order is created with an opening date in the past, so I have error 'Opening date in the past' in MD04. How can I generate a planned order with opening date not in the past
    - when changing manually opening date, after running again MD03, I have error 'No BOM selected'. Material is configurable, has a text BOM, a routing and a configuration profile. What is the problem? When modifying planned order, I have message :
    Material requires configuration
    Message no. 61259
    Diagnosis
    Orders and requirements for a configurable material must have characteristic values.
    Usually, you should create a variation for configurable materials managed in inventory management which has the default variant configuration.
    System Response
    MRP: Requirements without characteristic values for a material cannot be planned in MRP.
    Procedure
    Check requirements or orders.
    Create a configuration evaluation for the material in the material master record if necessary.
    Thanks in advance.

    Hi
    I am facing the problem. Could you please tell me if you have resolved the above problem? If yes, Could you please provide me as how you resolved? Thanks in advance.
    Thanks
    Nagesh.

  • Error while creating a Planned Order

    Hi SAP Experts,
    I have an error encountered while creating a Planned Order which is "Mode linkage problem with mode number".
    Diagnosis:
        An application program called an LCA routine and the following error occurred:
        An order has at least one condition with mode linkage with the same mode number. The activities of this condition must have compatible modes. The modes are compatible when each mode of one activity has a mode for the other activity with the same mode number. The first activity that violates the condition is given in the return code table in ABAP.
    Please enlighthen me what is this error and what should be done to this error.
    Thanks in advance,
    Raymond

    Check the PPM or PDS being used in the Planned Order.
    Most likely you have a Setup Activity followed by Produce Activity. However the Mode (i.e. Resource) used in the two activities are different. The same Mode needs to be used both in Setup and corresponding Produce activity.
    Hope this helps,
    somnath

  • Error while creating manual planned order in apo

    Dear expert
    While I am creating manual planned order i am getting error as message /sapapo/rrp251
    Every thing is correct BOM and PV's no error after consistency check and it getting succesfully transffered to APO and it is also visible in APO
    But while creating manual planned orders planned order are not getting generated  I am using BLock planning with PPDS
    Please help How to resolve it
    Regards
    Virender

    Hi
    The error message /SAPAPO/RRP251 - Error occurred while creating order means While creating an order, the system encountered problems, such as, for example, no available components or components that are available late, orders that could not be scheduled, and so on.
    I think system attempted to solve the availability problems by using alternative procurement options. This was not successful. The order could not be created. Check the exceptional situations in the planning protocol, under Goto -> Planning log, and deal with the causes of the exceptional situations if this is possible or necessary.
    Thanks
    Amol

  • Where/ how do I set SNP to create Planned orders with multiple line items?

    Hi
    Currently our SNP is generating planned orders on a daily basis, it creates a single order with a single line item per location.
    Where/ how do set SNP to create planned orders on a daily basis to generate a single order with multiple line items per location, so therefore one planned order with multiple line items for a single location.
    Thanx
    Keegan

    Hi Keegan,
                   In SNP (APO) it is not possible to create order with multiple line items.
    But you can do some settings so that while planning system can do aggregation and disaggregation.
    But your requirment should be set on Aggregation/Dis-aggregation logic.
    Please follow the follwing links:
    http://help.sap.com/saphelp_scm2007/helpdata/en/2c/c557e9e330cc46b8e440fb3999ca51/content.htm
    Aggregation:
    http://help.sap.com/saphelp_scm2007/helpdata/en/42/f731d078e73ee4e10000000a1553f6/content.htm
    Disaggregation:
    http://help.sap.com/saphelp_scm2007/helpdata/en/a6/ebefaf32e22e468355da304cc59387/content.htm
    Please be sure that the setting of this logic will be at planning area level.
    You can't change aggregation/disaggregation logic further.
    Regards,
    Santosh

  • Error while creating the sales order with billing reference

    hi alll
    i am getting error while creating the sales order with billing reference.The line items are coming in grey.I am not able to change the items as well as the quantity field.Can u guide me
    cheers
    shalsa007........

    Dear SAP SD 007
    I can confidently tell that an enhancement or an user exit has been applied in your scenario
    You have to check that
    Normally when creating a sales order with respect or referring billing documents the qty will be in editable mode and it is standard problem
    Your people has solved the standard problem by enhancement
    Usually OR--LF-PGI----F2 (SAY THE QTY IS 25 UNITS)
    Now you are creating returns order with reference to F2 in the return order type Re there is a standard issue that user can edit the qty to 30 from the original 25
    To solve this only your people have used userexit
    Line items and qty greyed out means definately there is some enhancement or user exit applied
    You have to check that
    Regards
    Raja

  • BAPI/FM in ECC to create a sales order with variant configurable material

    Hi all,
    I need to create a function module that creates a sales order in ECC with a variant configurable material.
    can some one tell me if there is a in built function module or BAPI that i can make use of to create a sales order with variant configurable material in ECC.
    Regards,
    Jessica Sam

    Thanks MxG,
    I dont know how to use this BAPI. .Can you suggest me a sample code.
    My reqmnt is, i have
    Sold to party, ship to party, bill to party , VC config material and all char values that should be populated while creating a sales order.
    please help me with what values should i populate in i/p paramters and and how to use this BAPI with some sample code if posible.
    Regards,
    Jessica.

  • BAPI/ FM in CRM to create a sales order with variant configurble material

    Hi All,
    I need to create a sales order using variant configurable material in CRM not manually through GUI. I need to develop a function module that will create sales order using variant configurable material in CRM .
    Can some one tell me if there is an in-built BAPI/Function Module availabe in CRM to create sales order using variant configurable material in CRM .
    When i researched i found that there is a BAPI 
    BAPI_BUSPROCESSND_CREATEMULTI which can create a sales order in CRM.
    I dont know if this can create a sales order with varinat configurable material in CRM
    can some one guide be how i can build a function module in CRM which generates a sales order with variant configurable material.
    Regards,
    Jessica Sam

    Jessica
    I am not a CRM expert and am still learning. But you can try the BAPI CRMXIF_ORDER_SAVE and see if that helps.
    Good Luck
    Ram

  • Planned orders with excesseption messages

    Hello All,
    I want to creates a customised report for the planned orders with exception messages. In which table I get the required information?  User want the selection criteria as WBS, meterial codes  and material groups. Thats why I can not use the MD04,MD05 etc.
    Please suggest the tables.
    Regards,
    Mayur

    Hello Ramagiri,
    Thanks for the quick reply.
    Table MDKP shows X tick in exception group but does not show the message number. In which table I will get these message number?
    Mayur

  • No sales orders with MRP-relevant requirements were found MD04

    Hello MM Enthusiast,
    We are in process of EHP upgradation and I need to replicate the following error message,
    No sales orders with MRP-relevant requirements were found
    Error message MF 336
    Please let me know how to get the above message in S environment.
    I have gone through the already discussed thread (http://scn.sap.com/thread/3460655) but couldn't able to get the message MF 336.
    Based on your response I can replicate and apply the causing / resolving note given by SAP AG.
    Looking forward to your valuable input to proceed further on this issue
    Cheers,
    Kumar S

    This issue was solved using a different availability checking rule in MRP3 of the material master.
    the old checking rule  had a requirements summary, while the new was for individual requirements, this setting is defined in OVZ2 customizing transaction.
    Hence you need to enter a checking rule in your material master which has a A as sales requirement in OVZ2.
    then create 2 or more new sales orders for this item for the same delivery date.
    After that you should get the error in MD04

Maybe you are looking for

  • Changing panels in frame at runtime using NetBeans

    Hi there, I'm having trouble changing JPanels in a JFrame at runtime when they were both generated in NetBeans. I find that I can do this easily in a manually coded GUI with the code below. However with NetBeans generated frames and panels it doesn't

  • [SOLVED] Netbeans won't start unless I am root

    Hi problem as topic. I have this issue since I upgraded to 7.3 (I didn't do this earlier, for I have to reconfigure the android plugin each time a new version comes) The symptoms are exactly as discribed in this thread: https://bbs.archlinux.org/view

  • Attribute Asset (AN1) - Need real time business Scenario.

    Hello Gurus, I haven't worked on a scenario in which there's a need to use the attribute AN1-Asset. I want to know any of you have can share your experience in working with any client & using this attribute to connect to ECC FICO. 3rd attribute in th

  • What is MSVCR80.dll

    What is MSVCR80.dll? Computer tells me it is missing and to re-install program

  • Setting time limit on running report