I have created an integration model using CFM1 & activated in CFM2.
now  dont know how to proceed.
is there any document or link to transfer data from R/3 to APO system.
i m new to this field & trying by own.
Thanks in advance.

Best way of creating CIF integration Model
Hai,
Please go through the above thread which can help you for understanding more about the integration models creation.
You have mentioned that you have done CFM1 and CFM2. Can you please inform for which object you have done and what you would like to see in APO?
Giving more details would enable helping you better.
Regards,
Murali.J

Similar Messages

  • Unable to delete/create integration models.

    Hi All,
    I need to correct some int.models wrt the logical system.
    1)     CFM1 u2013 choose variant pops up a msg- logical system not maintained in NDV2. This is not  supposed to be maintained. I need to change the variant models for a different logical system that is maintained in NDV2.
    2)     CFM7- delete all models.- I am unable to delete the models even after making them inactive.
    Final objective is to delete all the models- active and inactive and recreate new ones as nomenclature needs to be same. I canu2019t maintain the wrong (present) logical system in img, that's seen in the IM variants that do not lend themselves to change. The moment i do CFM1 it pops up a an error screen referring a wrong logical system..
    Pls., guide step by step.
    Regards,
    Lok

    Thanks Lakshmi,
    I began on the same note as wass evident but i did not have the wb request auth required. so was thinking if there is another was out fiddling with user transactions of IMs
    Thanks for prompt reply. Awarded full 10 points.
    Regards.
    Lok

  • Transfer of material from R/3 to APO, Problem in Integration model

    Hi
    I have created Integration model for Transferring material from R/3 to APO.
    While  activating the model, it is giving error  with status as i..e. SYSFAIL
    On clicking the status, I am getting the following message
    "Logical system R3CON does not assigned to Business System Group"
    ?Where to locate the BSG in  R/3 and assign before transferring  matl to APO
    i require the steps&help  to solve the problem.
    Thanks in advance to all members for the help.
    Srikanth

    Dear Srikant ,
    Pls check you have followed the below steps in the same sequence for R3 and APO
    <u>CIF Settings in R/3</u>
    Check ALE settings or activate ALE settings          
    •Define the logical system               <b>BD54</b>
    •Assign logical system to a client               <b>SCC4</b>
    Set the RFC destination               <b>SM59</b>
    <i>Assign target system and queue type          <b>CFC1</b></i>
    Maintain the SAP APO release               <b>NDV2</b>
    Activate BTEs for SAP APO integration          <b>BF11</b>
    User parameters for CIF               <b>CFC2</b>
    <u>CIF Settings in APO</u>
    Check ALE settings or activate ALE settings          
    • Define the logical system               <b>BD54</b>
    • Assign logical system to a client          <b>SCC4</b>
    Set the RFC destination                <b>SM59</b>
    Set up business system group     
    –Create BSG                <b>/SAPAPO/C1</b>
    –Assign logical systems to BSG          <b>/SAPAPO/C2</b>
    Maintain distribution definitions               <b>/SAPAPO/CP1</b>
    User parameters for CIF               <b>/SAPAPO/C4</b>
    You have got stuck up somewhere in R3 setting , which I have marked in italic font i.e.<i>Assign target system and queue type          CFC1</i>
    I hope this will solve your problem .
    Thanks ,
    Digambar

  • Requirement Reduction integration model

    Hi,
    Can someone explain in layman terms with an example what happens when "requirment reduction" object is CIF'd alongwith Planned independent Requirements (to APO). Why should/would someone create an integration model for requirement reduction when integration models exist for PIRs and Sales Orders consumption settings are taking care of netting (as applicable/set). we have funtionalities for consumption and reduction of sales orders from PIR's e.g in APO and ECC.
    Thanks
    Lok

    Hello,
    I would like to see a clear explanation to that as well.
    From what I understand reading about this topic it is to have additional control over this by applying own logic in CIF.
    Quoting the SAP documents:
    <<If you set this indicator, you can create integration models specifically for
    the Requirements Reduction filter object type (type T_FCC).
    The filtering takes place on the basis of active integration models for
    requirements reduction. In this case, you can control in greater detail for
    which material-plant combinations a requirements reduction should be transferred
    to SAP APO.>>
    For normal cases this is not needed. Perhaps it is needed if you want certain shipments to other plants to reduce forecast. E.g. mixed MRP.
    Regards,
    Tor

  • BOM and PDS in integration model

    Hi, All!!
    Could you help me colleagues?
    I try to create integration model in ECC (transacion CFM1), but at choice PDS or BOM the system gives out the message: "Integration model contains object types not valid for this APO release"
    How to transfer in APO this data?

    Thanks, I have understood

  • EWM-ECC  CIF Integration model

    Hello All,
    I want to tansfer data for plant,shipping point,customer and vendor from ERP to EWM.For this I have created Integration model.When I am trying to activate this I could not as I am getting message like'Queue for current initial data transfer is deregistered-Tgt System: APOCLNT800-Deregistered Queue' and hence Inbound queue blocked.
    What could be the reason for this message. How to unblock this Inbound queqe?
    Thanks,
    Shailesh

    Hi  James,
    Thanks. But this error is due to queue 'CFLD*  System is not activating integration model and showing error like this'Operation terminated due to error (queue CFLD*, target system APOCLNT800)'
    In SMQR I could not find this queue to acivate ,I tried in SMQ1/SMQ2, but I could not find this queue.
    Do I need to create this queue? I yes I am unkown T.code for this. Do you have any idea?
    Thanks,
    Shailesh

  • Transaction for activate the integration model

    hi,
       i created integration model using cfm1 transaction , how to activate the model ? in which transaction.
    regards
    muthuraman.d

    Hi Mathuraman,
    you can use the transaction CFM2 to activate your generated Integration Model. This transaction is used both for activation and deactivation of the Integration model.
    For Initial transfers you can  use the program RIMODINI also.
    Let me know if it helps.
    Regards
    Gaurav

  • Restrciting Deliveries in Integration model

    Hi,
            How can we restrict deliveries in integration model by dates? I see the option to select sales orders but not deliveries. Is it with any other name? How do I restrict it by dates?
    Thanks.

    Hi Raj,
    While creating Integration model if select sales order option by default it'll activate deleveries , Quotations and
    Customer independent requirements,As far as I,m concerned there is no restriction for date selection,You can restrict only by location product....
    Regards,
    Prabhu

  • Integration Models and CCR simultaneously . .

    Dear All,
    i have 2 questions :
    1) Why cant we run two Integration model simultaneously ???
    and
    2) Why cant we run CCR jobs in parallel with planning run ???
    Please let me know your observations and opnions.
    Regards,
    Prasad

    Hi Prasad,
    Below are the answers for your queries.
    1) Why cant we run two Integration model simultaneously ???
    Integration models are the building blocks of both master data and transactional data for APO.  It has to be contructed in APO in a sequence or in a order so that the updation of data can be performed sequentially.  Each data will look into the update of other data.  For example, we need to run integration model for location first and then location-product.  The first run of location will create integration model for location in APO and then when we run subsequently the location-product, the combination will be referred in APO.  If we run both location and location-product together, if location-product tries to update the APO system first(tables) before location data, then it will throw out error and cancel the model run.  Hence, it is advisable to run the models one by one in a sequence.
    2) Why can't we run CCR jobs in parallel with planning run?
    CCR runs will compare the transactional data between both R/3 and APO and display the results.  Planning run will perform the planning based on the selection conditions and it takes data from both R/3 and APO.  The planning results will be transferred from APO to R/3 based on our customisation settings.  During the time, when transfer of results happening, if paralley, comparison of both system data happens via CCR job, it will not give correct data or end up with errors or tries to cancel the job.
    Hope this clarifies your question.
    Please confirm whether you are clarified?
    Regards
    R. Senthil Mareeswaran.

  • Program for creating a model is locked by User

    Hi Guys,
    We have created a process chain to create the Integration Model and to activate the Integration Model using this prg RIMODGEN. So, This prg we have created variants for different location wise. This process chain contains 13 processes For each location, which is running in parallel. Some time we are getting the error message " Program for creating a model is locked by User
    Regards

    Dear  Pullaiah,
    Locking happens if there is any overlap of models or duplicate  scheduling of jobs with same variant.                                                                               
    See include LCIFIF01                                                                               
    CALL FUNCTION 'ENQUEUE_ECIF_IMOD'                                    
      EXPORTING                                                          
        mode_cif_imod  = 'E'                                             
        modelname      = i_modid                                         
        logsys         = i_logsys                                        
        apoapp         = i_appl                                          
      EXCEPTIONS                                                         
        foreign_lock   = 1                                               
        system_failure = 2                                               
        OTHERS         = 3.                                                                               
    So this means for you, you get the lockentry if the modelname, logsys and apoapp is the same. So please check again your variants if there is one with the same integrationmodels.            
    This can be the only reason we you get here this entry in your joblog.
    Regards,
    Tibor

  • CIF - Integration model name and APO application

    Hi Experts,
    In the CFM1 Transaction, there are 3 mandatory inputs are Model name, Logical system and APO application.
    Logical systems are customized in CFC1 transaction. I couldn't trace the model name and application creation.
    What is the transaction to customize/Create the new Model name and APO application.
    Hope this is very simple question to you and expect your soon.
    Thanks,
    Saravanan V

    Hi Somnath,
    Thanks for ur reply.
    First I saved the selection as variant. But it was not updated in the IM table.
    Then I tried to generate the model and now I can see the details when I use the F4 help.
    So, to create a integration model need to generate the variant once.
    Thanks for the confirmation.
    Thanks,
    Saravanan V

  • Cannot Create the Model in PI 7.1

    Hi All,
    when i try to create the Model in PI 7.1, there is no value from the Model Type drop down list. So the Create button is disable.
    what's more, when i double click the Sell From Stock (ESM) under SAP BASIS 7.10 -> Modeling -> Models -> ESA Sales Model -> 01 Integration Scenario Models
    it said:
    Error when initializing business modeling
    Initialization of business modeling could not be started. You cannot work with business modeling. Check that all required configuration objects are available
    Is there any post installation step i missed or any configuration i need to set up?
    Please help thanks a lot
    Regards
    Lawrence

    Hi,
    It is recommended to use IE 6.
    For IE8.0 use compatible mode option. (Menu>tools->compatible view)
    Thanks,

  • Not able to include PM order type PM03 in integration model

    Hi Experts,
    I am creating PM order in R/3 with order type PM03. But while creating the integration model for maintaince order, PM03 is not populating. and others I am getting like PM01, PM02 etc...
    Please advise if I need to do some setting for the same.
    Thanks
    Hitesh

    Hi,
    Request you to cross check whether the PM03 order type has the below two check box active  in IMG. 9 Tcode = OIOA
    Open Item Management and Release Immediately.
    PM03 order type with the above settings are getting reflected for me in my integration model.

  • Manual Reservations Integration Model

    Hello All,
    In our project, during Go-live we dint had manual reservation Integration Model Activated due to some business reason. 
    whenver a process order is created in R/3, Reservations for Components appear in R/3 and APO.
    Now when the components are good Issued in R/3 during Finished Product Process Order, these dependent reservations are not deleted in APO though the stock is reduced. Upon analysis we found that by activating the Manual Reservation Integration Model , these reservation will be deleted and hence both the R/3 and APO System will be in sync.
    Now the Problem is when we are trying to do this manual reservation Integration Model activation through Batch Job , activation is taking a very long time. Upon further analysis we found that for the material-Plant combinations, program tries to search records in table RESB and approximately it takes around 5 minutes for each material -plant combinations. In our integration model we have around 2400 Material-Plant Combinations. CFC3 settings for Reservations are select block size of 1000 and filter block size of 512. R/3 version is 4.7.
    Table entries in RESB are close to 3.5 Million with 141 Extends.
    So just wanted to check with you guys if anybody has experienced this problem before and what resolutions were put in place to addres this ? Are there any SAP Notes available ? I searched but could not found any.
    also what would be the best way to go forward? Some of the options i could think are
    1) Run the I.M for selected material-Plant Combinations
    2) Run the I.M for generic selection Criteria ( i.e AS IS) during Weekend.
    Pls share your opinions.
    Regards,
    Pawan.

    Hello Kenneth,
    As i understand from your message that if a final Issue Indicator is unchecked, then those reservations should be present in APO. However i got confused with your below statement
    Therefore it is neccessary that reservations with final issue indicator set are available in APO.
    I think you might be trying to tell  reservations with final issue indicator unchecked ( and not SET) are available in APO.
    Regarding Transaction Code MBVR, I have few queries
    1) Does this T-CODE MBVR sets the deletion Indicator in Table RESB or does it delete the Reservation permanently from Table.
    2) I am not able to locate Completed Items field, which will enable me to delete Reservations. Can you pls let me know the field name.
    Pls note that whenever i am trying to delete reservations thorugh t-code MBVR, it gives a message " No Document exists for the Speficied data".
    thanks for your assistance,
    Pawan.

  • Purchase Order Integration Model Activation Error "Source Invalid"

    Hi Experts,
    When I try to activate Purchase Order CIF integration model for a specific plant, I am getting an error
    "SOURCE_INVALID" r                                    XC           014
    When I checked failed LUW, found one product which is Subcontracted.
    These a Subcon PO exist at this plant and Vendor is Subcon Vendor.
    Before IM activation, I have CIFed Subcon vendor and T-lane between Vendor to plant exists in APO.
    Any idea how can I resolve this issue?
    Thanks,
    Vipul

    Hi Vipul,
    I hope you have created subcontracting purchasing info record and connected with the productuon version.
    Secondly whether it is valid.
    A purchasing info record of the category subcontracting which documents the subcontractor as the source of supply of the end product.
    Regards
    Datta

Maybe you are looking for

  • Logic Pro 7 Mix Bus -- Mixing in Logic Pro 7.0 -- Something is wrong

    Ok, Maybe its just me, or my crappy audio interface, or both. anyways, heres my issue. Heres the scenario, I have approx 30 tracks, a handful of exs's, eq's on most channels, everything is fine, the track is sounding great and i cant complain. I have

  • Spry problem in IE

    Exception caught while loading example.xml: [object Error] This message shows in IE when i using spry table (when I using FF it works normally) This is my xml <?xml version="1.0" encoding="utf-8"?><school> <classroom> <a>table</a> <b>abc</b> </classr

  • Using music from a pc

    I sort of wrote about this earlier today but not sure I framed the question correctly. My 16 y.o. daughter has a PC and she down loads tons of junk. After running Norton Anti Virus on her computer today I see she has a number of trojans on her PC. Sh

  • The messages not dequeue

    I have a separate installation of Sun Java Communications Suite 6u2 frontend: WebServer,Communication Express, messaging (front) and Calendar (front) midleTier: Delegated Administrator, webserverand Access Manager backend: Directori Server, Messaging

  • 'There is a problem with this Windows installer package'

    iTunes won't install. I keep getting the following message midway through installation; 'There is a problem with this Windows installer package. A program required for this install to complete could not be run. Contact your support personnel or packa