Creating process chains

Hi guys,
I need a step-by-step guide on how to create process chains urgently, could you please walk me through the process of what to click on to begin with e.t.c.
Thanks in advance

Hi Gurbinder,
First of all you need to Identify the InfoObjects if you want to take up Master Data Loads, and if you want take up transaction loads then select the Data Targets to which the data has to be updated. Then plan the dataflow accordingly.
You want to create a Process Chain, Go to RSPC, and then select the create option and from the Process categories available on the left handside drag and drop the Start process, then define the Variant for the same. In the same way you need to identify the other Process Types available on the lefthand side. For Eg: Start Process>Load to ODS>Activation of ODS Data>Delete Indexes for the InfoCube>Load to InfoCube>Create Indexes>Delete Overlapping Req-->Agg. Rollup.
This is how you need to specify the dataflow, several other Process Types also included based on the requirement For Eg: Sending Mail Alerts when the Job is Success or Terminated.
Hope this will Help you..
Regards,
Madhu

Similar Messages

  • Steps to create Process Chain in  Version 2004S SAP NetWeaver

    Hi,
    I have created a process chain in 3.5 version.Now i want to create a process chain in 2004s version.so what should be the steps to create this process chain.

    Hi
    1. Goto RSPC
    2.By using create icon create process chain.
    3.Now it will ask for process variant. Either assign already made or create new on.
    4. Now save it.
    5.Refresh the tree and u will find ur Procees chain in the list.
    Hope it helps, if so then assign points.
    Vinod.

  • Problem in creating process chains for CO

    Hi Friends,
                     I have a CO cube "0OPA_C11" getting data from Three datasources,
    those are 0CO_OM_OPA_6(supports delta), 0CO_OM_OPA_1(full only), 0CO_OM_OPA_2(full only), i have already created process chain to this cube using these three datasources, the chain is like this,
    1. delete indexes
    2.0CO_OM_OPA_6(supports delta
    3.0CO_OM_OPA_1(full only),
    4.0CO_OM_OPA_1(request overlapping)
    5.0CO_OM_OPA_2(full only),
    6.0CO_OM_OPA_2(request overlapping)
    7.create indexes
            Is it right? here the chain is running, after completion of that, in manage of cube, it is showing only the request for 0CO_OM_OPA_2(full only), the request which were there earlier like Init request and new delta request for .0CO_OM_OPA_6, full request for 0CO_OM_OPA_1 are getting deleted, it is showing the request only for 0CO_OM_OPA_2,
      the way how i created the process chain is right or wrong? can anybody give me the solution?
    Thanx in Advance
    BalajiReddy

    Hi Nick,
              Thanx for your reply, everthing is ok what you've asked me to check, i think there is certain scenario to create the process chains for the data targets, which are getting data from multiple datasources, which support delta's as well as full.
              I want that scenario, can you tell me? or can anybody tell me?
    The right points are assigned to the right answers.
    Thanx in advance
    balajireddy

  • How to create process chain with dso and infocube at a time

    hi friends,
      i have a FLATFILE in application server and i need to upload it to STANDARD DSO and i created a INFO PACKAGE and DTP for DSO.
    i have a STANDARD INFOCUBE to upload data from above DSO. here DSO is the source.  i want to schedule  this process in process chain. how could i do this. any one please give me solution.
         can any one explain me the options in RSPC and how they work and where we exactly use. this is very helpful to me. please give me guidance. thank you.
    thanks,
    sree

    First make sure you have already created the infopackage to load the data from server to the DSO and the DTP to load data from DSO to the Cube.
    Now goto Tcode RSPC.
    Choose Create process Chain option. provide appropriate technical name and description.
    Drag "Execute infopackage" process type from left hand side pane in RSPC.  Choose the infopackage to load the data from Server to DSO. you can find this infopackage using the F4 help in the above selected process type.
    Drag the "data transfer process" process type to load data from the Flat file data source above to the DSO.
    Then Drag the "Activate DataStore Request"  process type and select the DSO in which you would load the data  using the above DTP.
    Drag the "data transfer process" process type to load data from DSO to the Cube.
    Save, activate  and schedule the process chain according to appropriate time.

  • How to create Process chain in BI 7.0

    hi,
        I dont know how to create process chain in BI 7. If any one have document step by step process to create process chain. help me. thank u.

    check these links..
    http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/00a1f389-ec7c-2c10-04bc-9d81b3084171
    http://wiki.sdn.sap.com/wiki/display/BI/Processchainscreationandmonitoring
    http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/900be605-7b59-2b10-c6a8-c4f7b2d98bae
    http://wiki.sdn.sap.com/wiki/display/BI/FiveWaystoEnhanceBIFunctionalityUsingABAP--PartV--ABAPinProcess+Chain

  • Do we need to create process chain explicitly nor system generates process

    Hi all,
    Do we need to create process chain explicity in bpc netweaver nor the system generates it internally when we run data managment packages
    thanks
    Pooja

    When you install BPC, there is a set of delivered process chains which are installed as well.  You create the data manager packages from the BPC Excel clicent based on these process chains.  You can of create custom BPC process chains in NetWeaver and create packages from those as well(for example via a How-To guide).   So to answer your question, no, you do not have to create the "standard" process chains, and they are not generated by the system either, they are delivered as part of the BPC installation.
    Regards,
    Rich Heilman

  • How to create process chain for 0EMPLOYEE

    I want to create process chain for 0EMPLOYEE attribution and text, how to create it and make a schedule for daily loading? Could anyone write steps in my case? Thanks!

    Hi,
    Follow the following steps:
    1. Go to RSPC->create->give name and disc of your chain.
    Start Variant Creation
    2.  Now you will be prompted to give a start variant,create a  new variant(click on page icon )
    3.Change Selections->date/ time.
    4.give date and time for start of the chain.
    5.click the check box for periodic job->period values->daily->save->save
    Addition of process types
    6.Select the process type "Execute Infopackage"
    7.select the name of the infopackage which loads attr data to 0EMPLOYEE.
    8.Attribute Change run will come automatically( if not then drag it as well and create variant )
    9.select the name of the infopackage which loads text data to 0EMPLOYEE.
    10.Attribute change run wil again follow.
    (connect the process types which are not connected,by right clicking the process types )
                                 start
                           IP A     IP  T
                          attr          attr
    A = attribute
    T = Text
    Please Reward points if useful
    Manish

  • How to create process chains

    Hi Friends,
       I got one task on regarding creation of process chains, I am new to creation of process chains, can any one help me out immediately, pls send some documents and some sample process chains to my mail " [email protected]"

    Hi Kuna,
       Use TCode RSPC to create process chains.
       Pls. refer to this link for further development.
    http://help.sap.com/saphelp_nw04/helpdata/en/8f/c08b3baaa59649e10000000a11402f/content.htm
    http://help.sap.com/saphelp_nw04/helpdata/en/7b/d4313b38bea774e10000000a114084/content.htm
    http://help.sap.com/saphelp_nw04/helpdata/en/d5/e80d3dbd82f72ce10000000a114084/content.htm
    Also check..
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/36693695-0501-0010-698a-a015c6aac9e1
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/9936e790-0201-0010-f185-89d0377639db
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/3507aa90-0201-0010-6891-d7df8c4722f7
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/263de690-0201-0010-bc9f-b65b3e7ba11c
    assign points if useful ***
    Thanks,
    Raj

  • How to create process chains for Master Data?

    I need information on " how we can create process Chains for Master Data"

    Hi Sachin,
      http://help.sap.com/saphelp_bw33/helpdata/en/ad/6b023b6069d22ee10000000a11402f/frameset.htm
    and also Modelling aspects in process chains (ppt)
    https://websmp109.sap-ag.de/~sapidb/011000358700002337702003
    Hope this helps.
    Srini

  • How to Create Process Chain for Remote Cube.

    Hi,
              I created Remote info cube, data from ECC, loaded Successfully, I want to create Process Chain for Reomte Cube, Please Help me.
    Thanks,
    Nandish Gowda

    Hi Nandish,
    After initialization, th next delta will come as per your delta nature, if it is 0calday: Then your next delta will come tomorrow only.
    If you are able to 7 records in RSA3, why not in PSA( Why it's only 5 records). Analyze this closely.
    Sometimes, RSA3 exactly doesn't match with PSA because, RSA3 works on update mode F.
    Regards,
    Suman

  • HOW TO CREATE PROCESS CHAIN FOR PSA ARCHIVING

    SDN EXPERTS,
    i like to create process chain for archiving. but i dont see any event for archiving when i go to create a process chain for PSA archiving. please let me know.
    thanks

    Hi,
    In the below document on the 14th page it says it is not possible to archive the master data & PSA.
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/f47fec9f-0501-0010-ce84-8a7231715ae6
    As per my understanding..
    But one thing you can do is use another ODS and load the same data that you're loading to something else and try to archive that data(Only if you have transformations in the current CUBE/ODS).
    Correct me if i was wrong and eloborate your requirement.
    Regards, Siva

  • How to create Process chain for Aggregate for Master data

    Hello friends,
    I created Aggregates on Navigational Attributes.
    Now they are working fine, but i need to know that how shall i create the Roll up for Aggregates on Navigational Attributes.
    The point is the master data changes frequently a lot of time for e.g. for 0customer etc.....
    So if any one can send me the step by step documents so as to know how to roll up the Aggregates for Navigation attributes or for aggregates created on Master data....
    How to create process chains for the same ?????????
    Because if master data changes, then rolling up the aggregates straight forward will not help.
    So we need to write a process chain so that it deactivates the aggregate and reactivate again and fill up again..........
    If i mis interpreted something please rectify it.......
    Please advise

    Hello,
    the changerun that you have to schedule in order to activate the master data will adjust the aggregates automatically.  There is no need to deactivate them after master data loads.
    Best regards,
    Ralf

  • How to create process chain ?

    hi all,
    will you please simlify how to create process chain if anybody has a screen shot or slide show about pc creation it will definatly help me a lot.
    rewrd point for sure,

    This may help:
    [http://help.sap.com/saphelp_nw04s/helpdata/en/67/13843b74f7be0fe10000000a114084/content.htm]
    [https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/8da0cd90-0201-0010-2d9a-abab69f10045]
    Regards,
    Jordi

  • How to create process chains,and how to use process like and or xor

    Hi,
    How to create process chains,and how to use process like and or xor.
    can any one please give me a example in each.
    Thanks,
    cheta.

    Hi Cheta,
    Here is step by step procedure to create process chains
    Process chain is nothing but executing a process ..(or) loading the data any process we can do in background.. that means.. automatically we can execute our process based on Time or any event..
    Creating Process Chains
    Prerequisites
    If you want to include a load process in the process chain, you need to have already created an InfoPackage.
    You cannot load flat file data from a client workstation in the background. For this reason, you have stored your data on an application server.
    Creating Process Chains
    You have the option of creating a process chain in the process chain maintenance screen directly or by using a maintenance dialog for a process:
    Creating a Process Chain Directly in the Process Chain Maintenance Screen
    You are in the BW Administrator Workbench.
    1. Click on the Process Chain Maintenance icon in the AWB toolbar.
    The Process Chain Selection dialog window appears.
    2. Choose Create.
    3. Enter the technical name and a description of the chain, and confirm your entry.
    The Add Start Process dialog window appears.
    4. Create a variant for a start process.
    1. a. On the Maintain Start Process screen, choose whether you want to schedule the chain directly or whether you want to start it using a metachain.
    2. b. If you choose to schedule the chain directly, enter the start date value for the chain under Change Selections and save your entries.
    The Maintain Start Process screen appears again.
    3. c. Save your entries, return to the previous screen and confirm your entries in the Add Start Process dialog window.
    You are taken to the Plan View of the process chain maintenance screen.
    In the left-hand area of the screen, a navigation area is displayed. In the right-hand area of the screen, the process chain is displayed.
    5. Use the drag-and-drop function to add the relevant processes into your process chain.
    You use the Process Types function to select the processes. This sorts the process types according to different categories. You can also call up InfoPackages and processes for the data target from the separate InfoSources and Data Targets navigation trees.
    Hope this helps
    Regards
    Karthik

  • Creating process chains in ECC

    Dear APO/SCM experts,
    I am a Basis consultant and have been requested by our SCM funtional expert to configure the ECC system so that he can maintain process chains directly in ECC (via transaction RSPC and RSA1).
    He receives the following message in ECC when attempting to maintain the process chains: "You can only work in client 000".
    I am no SCM expert, but are you not suppose to maintain these chains from SCM? We are using BW as well and the BW consultants have never requested me to perform this action in ECC (as I understand SCM and BW source systems, datasources, process chains etc. are very similar).
    So, can you actually create and maintain process chains directly in ECC?
    Regards,
    CJ

    you should be able to create Process chains in ECC or SCM or BW. the process and concept is the same
    am not sure why ur SCM functional consultant asked u to create process chains in ECC and what he needs exactly. Maybe u should get more details. Maybe its a ECC process he wants to be done like say the integration models - not sure if you would want to do SCM processes from process chains in ECC
    not sure of the msg about the client 000 though
    yes you can create Process chains in ECC with the same RSPC transaction
    maybe he thinks you can maintain it all from solution manager or a central admin system in ECC

  • Creating process chains in production environment..

    Hi,
    We are planning to create process chains in our project , can we directly create process chains in the production environment? the data and the set up is very very small here  so the number of chains and processess are very less , is it ok if we create the process chains in Production environemnt directly, or we need to create in development and transport it to production (note: there is no quality instance for BW in our project).
    Solicit your help!!
    Regards
    Srinivas

    Hi ,
    Best practice would be to create PC in DEV and move it to PRD .
    Actually what happens in real time is sometimes your data mismatch happens or some other data loading activity you are doing in PRD system . So you need the freedom of creating DTP or Infopackage directly in PRD system . otherwise it would be a time consuming process to make it from DEV to PRD .
    Similarly when you are Infopackages & DTPs in PRD environment, there is a chance that your process chain might also be changed . So yes we can create it in PRD system .
    Kind Regards,
    Ashutosh Singh

Maybe you are looking for

  • Doubt in GUI Upload

    Hi All, I am using function module as follows to upload orders to database.File is created in required format on given path with same name as c:\va01.txt. But when i run my program its showing exception as "CANNOT INTERPRETE DATA IN FILE" What can be

  • My LG G3 won't detect my bluetooth headsets

    I have two Sony Ericsson bluetooth headsets, MW600 and HBH-IS800. They both worked fine on my old Droid RAZR MAXX, but my LG G3 doesn't even detect them. All that it picks up is my neighbors Roku Player. I've made the phone visible, searched for devi

  • Change origin of canvas

    hey, i have a canvas that positions itself in the middle of the screen with two lines (x and y axis). the problem is that i want to be able to move the origin, which then draws the axis again. thanks Pedge // GCanvas.java import java.awt.*; import ja

  • Error Message When Updating Table of Contents

    I am working in FrameMaker 8. I am updating a generated table of contents that was created by another person. When I update the TOC, the updating is completed successfully in the TOC, but I am getting the following book error message: I believe that

  • Converting to OTF and emailing

    I am using the below code to convert a SAP output to OTF and then send in an email as an attachement.  The email, works and the attachement is added but when I try to open the pdf attachement I get an error saying the file can not open or must be dam