Creation indicator purchase requisition in md02

Hello SAP Gurus,
     This is regarding creation indicator purchase requisition in md02.In this creation indicator purchase requisition if we keep setting as 2 than it will create purchase requisition if the dates of PR are in the opening period and will create planned order  if dates of PR falls out of opening period.And it takes the opening period from schedule margin key.
     My question is , as system calculate the opening date by subtracting the number of days which we have given in opening period in schedule margin key from the order start date.suppose if order start date is 10.03.2008 and we have given the opening period of 5 days,than the opening date will be 05.03.2008 if there are no holidays between it.So how it comes that PR date will fall in opening period?I am confused that when system will create planned order and when system will create PR if we keep creation indicator purchase requisition as 2.
      Plz help me with this query.If you could explain with one example than it would be great.
                     Thanking all in advance.And obviously for suitable answer i will definately give good points.

Hi,
System calculates the opening date  by subtracting the number days given as opening period at SMK from order start date.
For creation ind =2 ,
MRP run date decides the PR / Planned order creation even if u set procurement F.
If MRP run date falls bettwen the opening date & order start date , it will create PR only,
If run MRP run date falls outside the opening preriod ie earlier than the order opening date, system will create planned order and it has to converted to PR
For  examble,  Order start date is  28.03.2008 and 2 day is defined as opening period SMK for ROH.
If u run MRP on today it will create planned order.  
Hope u understand , ifso reward and close.
Regards
Pradeep

Similar Messages

  • Sales order - automatic creation of purchase requisition - cost assignment

    Hi
    When the sales order is released, we have an automatic creation of Purchase requisation. We have given "internal order" as the cost obect in the sales order. But when the system has created automatic purchase requisition, it has not picked internal order. What could be the reason?
    Thank you for the help.
    Thanks
    Ram

    Hi
    I feel that it is abug in the development you have carried out for creation of Purchase requisition when a sales order is relased,
    Please check the enhancement, you need to pass the values to the correct table after derivation.
    Thanks & Regards
    Kishore

  • Sales order - automatic creation of purchase requisition - CO assignment

    Hi
    When the sales order is released, we have an automatic creation of Purchase requisation. We have given "internal order" as the cost obect in the sales order. But when the system has created automatic purchase requisition, it has not picked internal order. What could be the reason?
    Thank you for the help.
    Thanks
    Ram

    Hi
    I feel that it is abug in the development you have carried out for creation of Purchase requisition when a sales order is relased,
    Please check the enhancement, you need to pass the values to the correct table after derivation.
    Thanks & Regards
    Kishore

  • SNP Heuristic: Creation of purchase requisition

    Hi experts,
    we face following problem: heuristic creates purchase orders when there is no source of supply.
    Background:
    there is a forecast demand for a location product on a customer location without transport lane to the production plant due to false master data.
    The SNP heuristic generates purchase requisitions to fulfill the demand and there is no requirements shortage.
    So it is hard to recognize which forecast demands can't be fulfilled.
    Is there a parameter in material master or in a heuristic profie which disables the creation of purchase requisitions in snp heuristic when there is no source of supply.
    If no purchase requisition is created there will be a requirement shortage which can be recognised by an alert.
    Thanks for your help.
    Robert

    hi.
    As per heuristic process , the system will create a purchase requisition if there are no Tlane exists and the material's procurement type is F/X since it is a infinite planning.
    Now you can use a optimizer or CTM to restrict the system from creating purchase requisition.
    Also you can try with location heuristic.
    Hope this can help.
    regards,
    kaushik

  • Auto Creation of Purchase Requisition at Contract Level

    Hi All,
    I am having business requirement for creation of purchase requisition at contract level for third party Products.
    Brief Business requirement
    My client is in trading business of telecom product.  They are sourcing product from different-different vendors and some of the product is also supplied by him self. As a business practice the system will automatically create an Installed base as per structured by business owner once delivered the product to end customer and also assigned warranty norms.
    Once warranty is over then customer will called for contract since at the time sailing the product warranty will be liability of the company which in terns had some mutual contract with supplier (back to back replacement).
    But once the same will come under service agreement/contract on that time they want installed base selection of components should had a functionality to segregate component based on vendor because they want to calculate % margin based on net sale value of the product.(e.g 10% of net sale Value 10,0000)  not only that they also wants based on that system should automatically create Purchase requisition so that logistic department will take care of third party agreement part.
    If any body come across with such kind of business scenario. Please share the proposed solution.
    Regards
    Neeraj

    Hello,
    I noticed that this question had status answered.  We have the same requirement.... how did you resolve this?
    Best Regards
    Kristof

  • Auto PO  creation using purchase requisition

    Hi,
    I have tried the following steps for auto PO creation using purchase requisition.
    i. Maintain Auto PO in Material master Purchasing view
    ii. Select Automatic purchase order in Vendor master- Purchase data
    iii. Maintain info-record
    iv. Create PR through ME51
    v. enable source determination during creation of PR
    vi. Execute using ME59N
    But Auto PO is creating with the same document type (e.g NB) which is used while creating purchase requisition (e.g NB). Following steps have done in SPRO.
    1. SPRO - MM - Purchasing - purchase requisition - define  document type
    a. NB- PR document type LINK TO DI01- PO document type
    2. SPRO - MM - Purchasing - Purchase order - Define document type
    a. DI01- PO document type LINK TO NB- PR document type
    3. There is no linking from NB - NB & DI01 - DI01 but still it is creating auto PO with document type NB iif requisition has been created with document type NB.
    Please suggest on this . waiting for ur quick response.
    Thanks...
    ARATI.
    Thanks!
    Arati.
    Edited by: Rakesh Gupta on Aug 20, 2009 11:00 AM

    Hi
    Please check the below thread
    PR to PO  via  ME59 -Doc type issue
    Thanks/karthik

  • Creation of Purchase Requisition with MRP - MD02

    Hello,
    I have created a sales order using one material with MRP. When I run MRP-transaction MD02 for this material, a purchase requisition is created.
    What we want is to block the creation of the purchase requisition when the sales order has delivery block (code 02). I have been trying to use this enhancements; setting break-points in all function modules, but when running MD02 is does not stop there:
    MEREQ001      Customers' Own Data in Purchase Requisi
    LMDR2001      User exits restr. profiles of opt. pur.ord.-based load bldg
    LMDZU001      User exits in additional planning                         
    M61X0001      User exits PP-MRP materials planning                      
    M61X0002      User Exits PP-MRP Material Requirements Planning Evaluation
    Do you know a way to do this or also change data in the purchase requisition created with MD02?
    Thanks and regards.

    Dear ,
    Are you very particualr to process the Sales Order demand when there is a delivery block ?
    To restrict that  one you can do the following steps :
    1.Goto Sales Order -VA02-Select the line item -Double Click -Select the Schedule line  tab -Set Sechedule line item categoery as CN instead of CP.If it is CP then it will processed through MRP
    2.Change the pricining date and make credit block for sales Order and do not release though VKM3 so it will not be tearted through MRP run  to have PR geneartion
    Hope this is clear
    regards
    JH

  • Creation of Purchase requisition in Maintainance order

    Hi
    I have a external operation in maintenance order , i have set the indicator in control key
    I assign service order in the maintainance order
    When i save the order system creates a purchase requisition
    Please let me know where is the setting which controls the creation of this purchase requisition
    Thanks

    Hi
    Check for Path
    SPRO>Plant Maintenance and Customer Service>Maintenance and Service Processing>General Data>Define Account Assignment Cat. and Document Type for Purchase Requisitions
    You will get Document Type for PR.
    Details of this document type are maintained in MM
    SPRO>Materials Management>Purchasing>Purchase Requisition>Define Document Types
    Hope this helps
    Regards
    Manish

  • Avoid  automatic creation of purchase requisition for bom item N

    Dear.
    When I create a production order , for the components  with bom item N the system create a purchase requisition. I need to avoid this automatic creation , do you know a solution to obtain this ?
    Thanks.

    For the many people that have asked this question.
    N item category in the BOM is always going to propose direct procurement. Through configuration I have not found a way to make it go away from the planned order. You can make it go away from the production order.
    The IMG path: 
    Plant Maintenance and Customer Service 
    -> Maintenance and Service Processing 
    --> Maintenance and Service Orders 
    ---> Functions and Settings for Order Types 
    ----> Define Change Docs, Collective Purc. Req. Indicator, Operation No. Interval
    Under the Res/PurRq -> Specify Never
    In order make this setting effective, you must define the following
    system message to error or warning, as it is stated on note 569984
    Version Appl.A. No. Cat
    00000000 C2 280 W
    Please note that this setting is effective for reservations and
    requisitions.
    The best solution is to use BOM item category L with the bulk indicator set. You will not get any direct procurement proposals or planned orders and you can use long term planning to see the time phased MRP results.

  • PM (T-code IW32) - Creation of purchase requisition permitted price=0$

    Hi,
    In IW32, we are able to enter a price of 0,00$ and save the purchase requisition. In ME51N, this action is not possible, we have to enter a price > 0,00$. Why are we able to save a 0,00$ purchase requisition using IW32, and not ME51N? We should not be able to create a 0,00$ purchase requisition in IW32 !
    IW32 procedure of PO creation:
    1. Run IW32
    2. Enter order number
    3. Go to «components» table
    4. DO NOT enter component, enter description, reqmnt qty, UM, IC, Plnt, OpAc
    5. Select the line item
    6. Click on the Purchasing button at the bottom left of the screen
    7. Enter Price = 0,00$, G/L account number, and save
    8. Quit IW32 transaction
    9. Go back in IW32, select the line item, click on the purchasing button, and there will now be a purchasing requisition number in the Purchasing Data table.
    10. Go in ME54N. You will now be able to release a 0,00$ purchase requisition....
    The system SHOULD NOT allow me to create and release a 0,00$ purchase requisition. How can I fix this?
    Thanks,
    Julien

    Hi,
    Go to SPRO > MM > Purchasing > Purchase Requisition > Define Screen Layout at Document Level > Here for Field selection key "ESTF" i.e. Requisition from prodn. order, mark field "Price and price unit" as required under selection group 'Quantity and price'.
    It will start asking Valuation Price during Order Creation for PR.

  • Automatic creation of purchase requisition for semi-finished product HALB

    Hi Gurus,
    We want the MRP to generate automatically a purchase requisition, instead of a planned order, for a semi-finished product.  Of course, we still want to be able to convert it to a planned order.
    thanks
    Jean-Francois Millaire

    Hi Jean-Francois Millaire,
    You want a purchase requisition after MRP run & you should also able to convert that purchase requisition to planned order,If i understood correctly, hope this is your requirement
    First one is possible -in MD01/MD02 maintain create purchase requisition as "1"
    Second is not possible,its not possibel to conver a PR(purchase requisition to Planned order where as vice versa is possible
    confirm my understanding,pls revert if you differ
    Regards,
    SVP

  • Error in creation of purchase requisition

    Hello Sap Guru,
    When we are trying to create a purchase requisition under t.code ME51N, we are getting error message "enter valuation price"?
    If anyone can please explain the reason & solution of this error.
    Thanks In advance
    Deepak Garg

    {code)When we are trying to create a purchase requisition under t.code ME51N, we are getting error message "enter valuation price"?{code)
    Hi,
    it is sap standard process when you create PR and if material master record exist the price is automatically taken from the valuation price field. if record not exist enter lum sum price of requested material price.
    When purchase guy create po with reference to Pr they can change valuation price also.
    In custommization for Purchasing under Purchase Requisition -> Define Screen Layout at Document Level, you can set price and price unit. The Valuation price field can be set as a mandatory or optional input field.

  • Creation of Purchase Requisition from VA01

    Hi,
    I have a requirement to apply block Id in me52n from tranasaction VA01 while creating sales order.csan you tell me how purchase requisition is generated from VA01 as this information will help me impose block in me51n from VA01.(Prior to that i have tried various badis and user exit but none of them are really helpful).
    Thank you.

    First of all you need to define the schedule line categories and then assign them to item categories. The system will automatically creates the purchase requision based on the item category/ schedule line.
    I guess, you need to look at the copy control process between sales and purchase.
    also look at the sales order user exit (Save document prepare / Save document) in MV45AFZZ
    Good luck

  • Creation of Purchase Requisition from a BID

    Hi,
    I am trying to create a purchase requisition from a bid instead of a purchase order. Does anyone have any idea on this?
    Thanks
    Sunny

    Hello,
    are you trying to create a local SC or a backend PR ?
    If you are in classic mode (so PR and not SC), you could try to derive the PO flow to create a PR instead.
    But this is not really clean.
    The best way is to add a new button "Create PR" in quote screen (or rename the create PO if you don't use it), linked to your own fcode processing and finally call the META_REQUISITION_CREATE in SRM (instead of META_PO_CREATE).
    The last point would be to create a link BID_INV>BID>PR to be displayed in document flow. You have to check if it is possible, because sometimes the system is designed for limited possible flows and does not take into account the flow you want to add.
    In standard, you can create directly a backend PO only if the bid was created from a SC in the sourcing cockpit. Otherwise use local or extended PO (replicated in R/3).
    If this is the case, FM BBP_PD_SC_TRANS_MULTI_BE_PO will transfer the initial SC items to next document, which is a backend PO. You would need to operate some changes here to create PR.
    Rgds
    Christophe

  • Creation of Purchase Requisition with Sale order

    Hi,
    I have a scenario where I need to create a Purchase requisiton for the requirement from the sale order (like the Third party sale order).
    I have done the required configurations to create the Purchase requisition.
    My Sale order has three line items and each line item has different Item category and schedule line category.
    I have configured different Purchase requisition document types for every schedule line.
    When sales order is saved, I need seperate Purchase requisition since the PR document type are different for every schedule line.
    But system creates only 1 PR with multiple lines. It picks the PR doucment type assigned to the schedule line category of 1st line item in the sale order.
    How can I get different PR for different doucment type in a single Sale order?
    Regards

    This can is happening b'coz at your sale order only one I cat is determining by default.
    So, determine diff I cat with diff desired the sch lines cat in the doc.
    Say,
    maintain, I Cat determination(VOV4)
    Sales Order(VOV8) - I Cat Group(material- MM02) - I Cat(VOV7)
    ZTPS - ZTA1 - ZTA1
    ZTPS - ZTA2 - ZTA2
    ZTPS - ZTA3 - ZTA3
    and also check.
    I Cat (VOV7) - Sch Line Cat (VOV6)
    ZTA1 - Z1
    ZTA2 - Z2
    ZTA3 - Z3
    Hope this can assist you in understanding.
    Thanks & Regards
    JP

Maybe you are looking for

  • Displayin document in Smartform

    Hi everyone. I am using the following code to read an attachment . At the end of this code i'm using GUI_DOWNLOAD to download the data read from attachment into my system as a word document say filename C:\ XYZ.doc .This is working fine giving the ri

  • Two different 10g installations in the same box

    Hi, I installed oracle 10.2.0.2 and 10.2.0.4 in the same box, using different paths as ORACLE_HOME, but the same user... I am gettin this errors when trying to create an instance: hu Feb 12 10:31:29 2009 Errors in file /oracle10/app/oracle/admin/SIDB

  • Deskjet 5525 Server Connection error 403 - scanning documents

    I cannot scan and send documents/photos to email or computer. It is connected wirelessly to internet, but keeps coming up with Server Connection Error : 403. I have reset to factory settings on the printer, but no change. What do I do, to be able to

  • Project Spartan and the WebBrowser control

    I'm a C# WinForms developer working in Visual Studio 2010 and I use the WebBrowser control in my desktop applications for users to view web content through the desktop app. I have 2-questions related to the upcoming Project Spartan browser, which is

  • Heavy performance issues using Adobe Interactive Form PDFs generated by SAP BPM

    Dear experts, we use Adobe Interactive Form PDFs (generated with LiveCycle Designer) as Human Tasks within SAP BPM processes. The PDFs are generated and transmitted correctly, but when they are opened at the receivers PC, Windows freezes for 2-3 minu