Creation of Maintenance Plan through IBIP t.code

Hi,
I want to create the Maintenance Plan in Mass using the IBIP t.code.
I am using Record name as IBIPMPLA, and trying to create the Plan but instead of providing Plan description in t he file error is coming for Plan description.
If any procedure is available, kindly provide the same.
Thanks in advance

Hello
can you please provide the detail information of error message. is it the error for the formating error in the field RMIPM-WPTXT?
If so, then please check if the below information can be any of help:
When using IBIPMPLA structure it is also necessary to create at least on item with structure IBIPMPOS. If IBIPMPLA used on it own then you will get the error 'Formatting error in the field RMIPM-WPTXT'.
Please refer to the documentation for the program RIIBIP00:
Structure - IBIPMPLA  - Maintenance plan
                  >>  IBIPMPOS     Maintenance plan item
                           >>  IBIPTEXT   (see comment below)
                           >>  IBIPOLST   Object list
                           >>  IBIPBDCD   (see below from maintenance
                                            plan item)
If you create an entry for the structure IBIPMPOS and maintain 1maintance plan item then IBIP should create the plan successfully and the error should not occur.
In IBIPMPOS structure do NOT maintain a value for TCODE, otherwise an error will occur.
Regards,
Jane

Similar Messages

  • BAPI for Creation of Maintenance Plan (TCode - IP01)

    Hello
    Kindly help me with the BAPI for Creation of Maintenance Plan (TCode - IP01)
    Thanks and Regards
    Avishek

    Hi
       Check Tcode: IBIP. and LSMW method and below link it may be helpful.
    [link|Re: LSMW for uploading equipment.]
    Thanks,
    Asit Purbey.

  • Automatic Creation of Maintenance Plan, Measurement plan

    Hi Pal
    Business : The equipments are procuring for the purpose of supplying into customers.It is installed (via sales delevery) at customer location as requirement. From  the installation date rental will start and periodic visit is applicable after every 3 months. The technician will capture  some reading In initail installation time, periodic maintenance time.
    Requirement : The equipment will be created automatically thro serial no when doing the GR(Its possible) . Automatic creation of Maintenance Plan for the equipment  for 3 month frequency, 70% call horizon, early and late completion of 100%. Additionally the scedhule start date need to pick it from the notification end date of its respective equipment.Also measurement points should be generated in automatic way (Its fixed& common for all equipments).
    Is there any possiblity to complete this requirement? Please help me and suggest.
    Regards
    Thenna

    There is no suitable BAPI available to create Maintenance plan.
    Try for BDC.

  • Making task list field mandatory in creation of maintenance plan?

    Dear All,
    I need your help in configuration of Making task list field mandatory in creation of maintenance plan. I checked with sceen variant config but that also not giving me any option to make the field mandatory.
    Is there any note or user exit for it?
    Regards,
    Kaushal Rai

    Dear,
    Pls check the exit IPRM0004:Maintenance plan / item: Customer check for time "SAVE".
    Regards
    Sunil

  • PM archive maintenance plan data

    Hi all,
    I try to archive maintenance plan by use t-code sara
    - select archive object PM_MPLAN
    - select maintenance plan for archive
    and run will shown message "no maintenance plan was selected"
    please help me to solve this problem,
    Thanks

    hi
    have you set the deletion flag for the maintenance plan ,kindly refer the following link for the prerequisite for Archiving the maintenance plan
    http://help.sap.com/saphelp_47x200/helpdata/en/a4/96ba49e41c11d1951d00a0c93029cf/content.htm
    regards
    thyagarajan

  • LSMW Maintenance Plan (IP01) - Header texts

    Hi,
    LSMW Object 0460 (Maintenance plan) Method 0001 (Create),
    Maintain Structure Relations show the following:
    IBIPMPLA IBIP: Maintenance Plan
    IBIPMPOS IBIP: Maintenance Item
    IBIPTEXT IBIP: Long text line
    IBIPOLST IBIP: Objectlist
    IBIPBDCD IBIP: Direct BDCDATA: formatted BDCDATA: expert use only
    Problem / question: I need to maintain the text for the header. Why is there no IBIPTEXT immediately after IBIPMPLA?
    Thanks for any help.

    Hello,
             I need to migrate Long text for Header in Maintenance Plan, Does any one has solution for this?
    Thanks in Advance.
    Regards,
    Ravi Kishore.

  • Maintenance plan creation

    Hi All,
    We have created maintenance items using transaction code IP04. Now with reference to this we want to create the new maintenance plan.
    When we go to transaction code IP01, it asks us to maintain all the details like equipment, order type, planning plant, task list etc. We do not want to give them again as we already have the maintenance items created.
    Kindly let us know how can we create the new maintenance plans by assigning the maintenance items directly.
    Regards,
    Smart

    Assign the Maintenance items through this icon.
    n the selection screen, click on multiple selection button  and there give the list of items.
    In the selection screen, click on multiple selection button of Maintenance Item field and there give the list of items.
    Select multiple lines in the output, and click on Green Tick. Your items are assigned to Plan.
    Jogeswara Rao K

  • Reversal of a maint. order which was released through a maintenance plan?

    Hi All,
    Is there a way to do reversal of a maintenance order that was released through a maintenance plan?
    Because I do not want to process the order; as such I would like to put a reversal indicator for that order and go ahead with the next order that was called through a maintenance plan.
    If YES, kindly let me know how to do it?
    Many thanks in advance.
    Kannan J

    Hi Thyagarajan, Thanks for the response!
    When I want to skip the maintenance call object that was generated through a plan, the system gives me the following message.
    "CALL CAN NO LONGER BE SKIPPED"
    When I press for further help, system gives me the following message:
    "Call can no longer be skipped
    Message no. IP405
    Diagnosis
    You have tried to skip a date that has already been called.
    System Response
    Since maintenance call objects, for example, maintenance orders, already exist for the dates that have been called, you can no longer skip a date within the scheduling process.
    Procedure
    If you do not want to perform the maintenance call objects due on that date, you must reverse the orders that have been called.
    You can select the maintenance call objects that have been called using the list editing functions in maintenance processing."
    Which means there should be a way to reverse the order, isn't it?
    May be with this message you may be able to throw some help on this.
    Many thanks in advance
    Kannan J

  • Single Maintenance plan creation for multiple equipemnts with different cyc

    Dear Experts,
    I had a following scenario to map in PM module. can anybody guide me to map this process?
    we had no.of equipments under one functional location and will go through preventive maintenance on yearly basis. For this, i will create the single cycle yearly maintenance plan which comprices of maintenance items, which is fine. out of these equipments some of the equipments will go for routine maintenance like quarterly, half-yearly, tri-quarterly. user want to club these scenarios also in single preventive maintenance plan. when we scdule this plan, system has to deliver monthly orders and as well as yearly orders from single preventive maintenance plan.
    Thanks & Regards,
    Krishna

    Hi Krishna Murthy,
    It can be acheived in the following Manner.
    Create a Strategy say "Test" with Packages 1M, 2M,Q,H,Y packages.
    Create 5(say) Equipment Task Lista for each of the 5 Equipment at that FL.
    1st Task List will have Operations related to say Monthly(1M), Quartely(Q), yearly (Y)
    2nd Task List will have Operations related to say Monthly(1M), Quartely(H), yearly (Y)
    And so on... as per Business Requirement.
    Now create a Maintenance Plan with 5 maintenance Items with respective Task Lits.
    Now Schedule the Plan and give the Last Completion date as the Yearly package (A date one year less than the day you wanetd the yearly plan).
    Then check the calls.
    Regards
    MLN Prasad

  • Creation of PM Notification based on UD Code

    Hi Seniors
    I am new to PM/QM module and facing an issue while configuring UD code follow-up actions.
    My requirement is once the Valution Code is set to "Rejected" in UD code then follow-up action should be generated and in this follow up action, couple of actions should take place :
    1. Set the equipment status (QFOA_OBJECT_STATUS_SET). It is happening
    2. Set the order status to TECO (QFOA_ORDER_TECHNICAL_COMPLETE). It is also happening
    3. Creation of a Notification so that based on that notification, corresponding order followed with PR/PO to be created for procuring of the equipment.
    I am not able to find out the way how to address Pt. No. 3. Kindly help
    Thanks
    Manmohan K Bajaj

    Hi,
    Thanks Seenu,
    So i have to clasify based on Maintenance activity types. If there are activities like repair, shutdown, testing etc. then i will have to create work center based on that?
    So i can create some activities like, Modification, Repair, standby, waiting etc and assign work center for each?
    Here we are following 4 maintenance planning preventive, predictive, breakdown & shutdown so is it possible to make 4 work center according to those.
    please correct me if i m wrong. i really have no much idea in this. any help or suggestions will be appreciated.
    Thanks in advance
    Ramya

  • Maintenance Order through Measuring Point

    Dear all,
    I want to know whether it is possible to create the maintenance order on the basis measuring point .
    I know how to create the order on the basis of measuring counter.
    Is there any procedure to create the maintenance Order through measuring point as done in case of counter?
    kindly provide the solution for Creation of Maintenance Order using Measuring Point..

    Really very thanks for the solution.
    I have one more query, we can create the measuring point using the t.code IK01.As you told we have to create the measuring point with upper and lower range.
    Is that we have to create 2 measuring point for upper as well as lower range or in one measuring point it is possible to accumulate both the upper and lower range.
    If it is possible to accumulate both the upper and lower range in one measuring point then kindly provide the procedure.
    Thanks in advance.

  • Assign particular measring point to Particular Maintenance Plan

    Hi,
    I would like to know whether it is possible to assign measring point to maintenance plans.
    Here it goes the scenario
    Equipment= PUMP
    I have maintenance plan weekly & monthly
    In weekly maintenance plan ( Every Monday)I have to check
    1.Vibration,
    2. Speed,
    etc upto 10 measuring point
    In Monthly maintenance plan (30 days) I have to check
    1.Bearing Condition,
    2.Oil Level,
    3. Pressure
    4.Temperature
    5. Current,
    6. Voltage 
    The above mentioned measuring point is created w.r.t equpt PUMP by T-Code IK01.
    Now problem is whenever I get call object i.e maintenance order according to weekly & monthly maintenance plan.
    Weekly order- 100001 is generated while confirming (IW41) this Order & its operation activity
    I will update measuring point but it is displaying all the measuring point of an equipment.
    I want only measuring point pertaining to weekly maintenance plan should only display.
    How can I link measuring point to particular maintenance plan?
    Is there any solution available or does anyone come across this scenario?
    Pls revert back for any more information.
    Regards
    Pradeep

    Hi,
    I have been able to see measuring point in a task list since upgraded to EhP4.
    I was just trying to assign measuring point to operation But it is throwing error message saying measuring point doesnot exist.
    When I  press F4 none of the measuring point is existing though I have created Measuring point to equipment?
    Can someone help me or guide where am  I going wrong?
    I have gone through the below link for details on inspection rounds but there is no elaborative & detailed procesure existing
    http://help.sap.com/erp2005_ehp_04_sp/helpdata/en/48/689d3dd2613c87e10000000a42189c/frameset.htm
    Could you pls tell me the detailled procedure or provide the material?
    Regards
    Pradeep

  • Condition Based Maintenance Plans

    Dear All,
    My client has the requirement of condition based maintenance plans without interfacing etc. An example is described below:
    Compressor bearing has temperature limits of 70 deg C and 90 deg C. If measurement document reading is recorded outside the range specified here a maintenance call / maintenance order should be triggered.
    Please give an example or process for the above dsicussed condition based maintenance plan upto two or three calls.
    Thanks and Regards,
    Saif Ali Momin

    Hi,
    As such there is no functionality directly. You can use the following user exits and can develop your on logic to trigger notification in case measured values are out of tolerance values.
    IMRC0003 Menu exit - measurement document
    As I remember there is sample code available for ythe same. You can check through SMOD transaction.

  • Measuring Point in Maintenance Plan

    How can I link a measuring point (not a counter) to the Maintenance Plan?
    Currently, I can only link a counter to a Maintenance Plan but not a measuring point.
    The reason why I am asking for this is that I would like to trigger automatic creation of a work order whenever a measurement reading for an equipment goes outside the specified upper and lower limit of a measuring point.  I would like to define a condition in the maintenance plan for this based on the measuring point say for example temperature.
    I believe activating userexit IMRC0001 is just part of the solution.  Is there something else that needs to be done?
    Thanks.
    Giscard

    I have already activated userexit.
    Is it correct that the userexit is triggered upon saving a measurement reading (tcode IK11)?
    Do you have sample code for the userexit so that a Notification or Work Order will automatically be created when the reading entered is outside the upper and lower limit?
    But my questions actually is this - Is possible to link a measurement point (not a counter) to a Maintenance Plan?

  • Segregating maintenance plan with reference to planner group & cycle.

    Hi,experts,
    Is there any t-code to search maintenance plan as per planner group as well as cycle length?I tried with t-code IP15, but there is neither planner group or maintenance item field?please,suggest .thanks in advance.
    rgds
    rajib

    Hi,
    There is no relationship or filed which directly u can get like planner gr,section etc. One way  can use is use filed named as Maint Plan Sort Field. Provide here some details after making proper codification through Customeriastion.
    One way Like Maint plant + Planner Gr = Maint Plan Sort.
    Attach appropriate sort filed in each plan then with ip10,1p30,1p19,ip24 u can retrive the information.
    Ramesh

Maybe you are looking for

  • How Do I Reset Indicators in User Interface?

    I have a VI that has got out of control.  I have created several test sequences that were developed, proven and built into individual VIs.  I created a Main VI and placed (cut and paste) each invidual test VI into a sequencial Frame.  Long story shor

  • Replacing low res album artwork in mini player

    Here's a slightly neurotic question for the iTunes album art lover community.... I like the new miniplayer in iTunes 11.04 very much. The problem I've discovered is that much of the album artwork I once added to iTunes 10 and which looked fine in the

  • Accounts in STO , Consignement, pipeline stock

    Hi, First of all " Wish you a very happy new year 2008" Please guide me regarding the Accounts updated in 1. One step STO 2. Two Step STO 3. Consignement Cycle 4. Pipeline Materials consumption. Best Regards, Shreya

  • Javascript - custom datetime converter problem

    Hi all, JDev version 11.1.2.4 After migration from JDev 11.1.2.1 to new JDev 11.1.2.4 my custom datetime converter stop working. After debuging I found out that client javascript converter is problem. Here is javascript code: function DateToCalendarC

  • Creating Regions Using APIs

    Hi, I am trying to create a Content Management System using APEX 4. I was wondering if it is possible to create regions on the fly using APEX API. The regions will act as modules having custom attributes to load its related region template. It's appr