Creation of Plant in IS-Retail
Dear all,
We have IS-RETAIL system operative and we would like to create a new company code and plant which is not into IS-Retail .
We need to create a new plant which should work for ERP and not for IS-Retail.
I have changed the site profile to empty to make it as Plant ,but through which way i should create a plant ,through IMG or WB01
Please advice the appropriate method to create a plant by copying existing plant.
Tnx
Zubair
Hi
Do it with WB01. Check what steps you need to do with IMG. After, with an export/import you could transfer data between systems. Please, see these notes
SAP Note 737239 - Site export/import as of SAP R/3 Retail Release 46C
SAP Note 1835984 - Transactions WBTE and WBTI are obsolete
and related notes
Regards
Eduardo
Similar Messages
-
Issue in creation of plant related data at receiving server using BD10
Hi all,
This is regarding Material master creation using B10.I am using MATMAS05 message type for sending data from one system to another.Data is sent and received successfully.When i go in mm03 i can see all the views created successfully accept views related to PLANT.Please guide to resolve the issue.
When i entered into Log-
1)"The field MBEW-BKLAS is defined as a required field; it does not contain an entry".
2)"No material master data exists for material AB_08.04.09(30) in plant 4001".
My segemnt is as follows-
ZMATMAS05 matmas05
E1MARAM Master material general data (MARA)
Z1KLART KLART----
My extention
E1MARA1 Additional Fields for E1MARAM
E1MAKTM Master material short texts (MAKT)
E1MARCM Master material C segment (MARC)
Z1AUSPM E1AUSPMDistribution of Classification:----
My extention
E1MARC1 Additional Fields for E1MARCM
E1MARDM Master material warehouse/batch segment (MARD)
E1MFHMM Master material production resource/tool (MFHM)
E1MPGDM Master material product group
E1MPOPM Master material forecast parameter
E1MPRWM Master material forecast value
E1MVEGM Master material total consumption
E1MVEUM Master material unplanned consumption
E1MKALM Master material production version
E1MARMM Master material units of measure (MARM)
E1MBEWM Master material material valuation (MBEW)
E1MLGNM Master material material data per warehouse number (MLGN)
E1MVKEM Master material sales data (MVKE)
E1MLANM Master material tax classification (MLAN)
E1MTXHM Master material long text header
E1CUCFG CU: Configuration data
E1UPSLINK Reference from Object to Superior UPS
Thanks.
Edited by: sanu debu on Apr 27, 2009 7:10 PMCREATE CONTROLFILE SET DATABASE "NEWDB" NORESETLOGS ARCHIVELOGAlso when you are setting a new database, the option should be RESETLOGS and not NORESETLOGS.
'D:\APP\ADMINISTRATOR\ORADATA\NEWDB\ONLINELOG\O1_MF_2_7FK0XKB8_.LOG
D:\APP\ADMINISTRATOR\ORADATA\NEWDB\DATAFILE\O1_MF_SYSTEM_7FK0SKN0_.DBFWhy underscore(_) at the end of the datafile name. Any specific reason ? -
Dear Experts,
We have created three plant within a company code, in this one is Godown and other two is manufacturing unit. The Godown is 25 Km far from these plant. We will have transaction of Stock transfer between these plants. Now the problem is the revenue generation will be only at godown.
Is it correct that we have created Godown as Plant. I think creation of Storage Location far out of the Manufacturing premises is not correct.
Please reply me at the earliest.
Madhuri..Hi,
There is no harm in maintaining it as a plant or a sloc as the requirement may be as you rightly mentioned revenue will be accounted in that specific plant (godown) if that is the case what is the problem in that anyway it is further linked to the same company code.
By defining go-down as seperate plant it gives seperate valuation area.
Regards
Rang -
Assignment of purchse organisation to site (plant) in IS-Retail
Dear Friends,
Would like to have simple Query
We Have 3 Company Codes.
Is we need to have different purchase organisations, Company-Code wise and purchase organisations are assigned to sites
Or is it possible to have Centralised purchase Organisation for all Company codes in Specifically IS-Retail
The Assignment of Centralised Purchase organisarion with all sites belongs to different Company Codes is showing an assignment error in STATUS specfically in IS-RETAIL.
Plz advice.
B.Regards
JaveedIf you want only one purchase organisation for the palnts in different company codes,assigne the purchase organisation to plants across the company code and don't assign the porg to company code.
If we assigne the porg to company code then that porg can be used only fof rthat compnay code. -
Task list creation in plant maintenance.
Hi All,
I have the function module /ISDFPS/TASKLIST_CREATE which was used in my program under one more Z function module, we have a XI integration also here earlier we were using service pack SP10 so this program was working fine as integration with other interfaces was working fine.Now the client has upgraded to service pack SP14 and so the standard FM got one more parameter T_CUOB which was not mapped because in SP10 it was not available. Pls can anybody suggest me what is this parameter T_CUOB and what is the business significance of it.
The standard FM was used for creation of a task list in plant maintenance for Functional location, equipment etc.
Vishnu.Hi Vishnu,
I am just wondering if you got an answer to this question. We are having the same problem, but we do not care what the value is for t_cuob, therefore we need to default it to something like null or blank.
Thanks -
Ristrict sales order creation at plant level through authorizations
Hi ,
I want to ristrict users to create sales orders for specific plants . Can anyone please tell me how to do it through authorizations.
I am not able to find any authorization object for plant in VA01 and i have tried to add object from other module like MM or PP and maintain plant values but still it is not ristrict users to create sales order for that plant.
any other object for plant.
Thanks & regards ,
Nitin PatkiGenerally we control parameters like Sales Organization, Distribution channel, division, sales document type, billing document type etc through roles in SD but if you want to block the creation of sales order based on plant, then take the help of FI/MM people because if they will not give the authorization for Profit centre (in case you have taken that plant as a profit centre), The user will not be able to proceed further without profit centre.
Reward points if it helps,
Regards,
N -
Creation of Plant Specific Views while creating or changing the Material
Hi,
When saving a material (MM01/MM02), based on data in custom table, I have to extend the material for different plants and plant specific views such as
1. Purchasing
2. Foreign Trade Import
3. MRP1
4. MRP2
5. MRP3
6. Forecasting
7. Parts F&P Data (custom view)
8. Accounting 1
How can I achieve this? Is there any FM or BAPI that can be used to extend material for a plant and its specific views?
Also please suggest me the user exit or BADI which has to be used to achieve this functionality?
Best Regards,
KumarWe can use the BAPI, BAPI_MATERIAL_SAVEDATA to extend material to different views.
-
Hello,
Can u please let me know wat r the basic requirements for creating a plant?
can u create company code as valuation area and wat r its implications?
Thanks in advance.
SachinHi
You can create new plant in Enterprise structure of IMG in defination-logistic general-define copy delete check plant.
Copy this from standard one like1000.
Valuation level:-
Once set, it is not possible to switch the valuation level from plant to company code, or vice versa. If absolutely necessary to subsequently change the valuation level, contact your SAP consultant because a data conversion is required.
Your choice of valuation level affects the following:
Maintenance of material master records
Depending on the valuation level chosen, accounting data (in particular the valuation price) is maintained for each plant or for each company code in the material master record.
G/L accounts in which material stocks are managed
If material stocks are valuated at company code level, all plant stocks of a material are managed in a joint stock account for each company code.
If material stocks are valuated at plant level, the material stocks for each plant can be managed in different accounts. You can define a separate account determination for each plant.
If several plants are to use account determination, you can group them together in Customizing for Valuation and Account Assignment in the section Account Determination .
G/L accounts to which transactions are posted in Materials Management
reward if it helps
rb -
Im creating one depot foer which im copying data from already existing depot.I want to extend all the materials from existing to new plant.is there any t code for this apart from MM01.Plz reply.
Hi,
Better to create standard template for the same and upload the same through BDC(Using SHDB) ,and make the Tcode for the same so that it can be used and will be authorized to concerend person.
Or make the extension program with the help of abapor by using BAPIs
You can get the required BAPIs list with the help of below specified Link.
http://wiki.sdn.sap.com/wiki/display/PLM/MaterialMasterBAPIs
Regards,
Sandesh Sawant -
Role creation for Plant maintenence
Hi Folks ,
i need to create a ROLE only for Plant Maintenence (only Plant maintenence authorization).......
regards
sathishHi
> i need to create a ROLE only for Plant Maintenence (only Plant maintenence authorization).......
Search the roles for this module & make copy of this roles to zroles.After the zrole was created assign this new roles to that user.
Search the role by writing plant,maint & check which are related to plant maintenence & copy that role.
Again check all the transaction which are going to use in the module PM.Create a new role & assign this transaction in this role.this is another way to create the user with authorization only for PM.
For more details about PM modules transaction check the following link
http://www.sap-img.com/sap-pm.htm -
How to Debugg workflow for Article Creation using MM41 In IS Retails System
Existing system they are using business BUS1001006,Event Created for triggering workflow when you create article using transaction code MM41.
I could see one more business object named ZBUS100106 for triggering workflow when you Create an article.
I just want to debugg the workflow to add some additional validations to trigger workflow when i can create article using transaction code MM41.
Let me know how to debugg the workflow.
Thanks in Advance.ZBUS100106 is nothing but Custom Business Object of BUS100106 creating by extending BUS100106.
You can debug Business Object code thru putting breakpoint in Code and executing the Business Object thru SWO1.
For your requirement you could possibly use SWB_COND Tcode so as to limit workflow lanches.
Refer [this|http://mailman.mit.edu/pipermail/sap-wug/2003-November/011005.html].
Regards
Shital -
Automatic creation of PO in supplying plant
Hi ,
There are three plants A,B and C. Plant A procures from B and plant B procures from plant C. Note ::: A cannot procure from C due to some financial matters.
i.e, A<B<C .
A plant to plant purchase order will be created in plant A for plant B. Thus this PO will be displayed in MD04 of plant B as ConRel.
As this material will be procured by plant B from plant C ,,, Plant B needs to create a P2P PO for plant C.
Now as soon as plant A creates PO for plant B ,, we need automatic PO creation in plant B for procuring material from plant C.
Is it Posible in standard SAP?
Regards
Rohit ChavanHi,
As per my knowledge it is may not possible in standard SAP.
If any suggestions please do update.
avs -
Hi Gurus,
While creating a new plant in real time, is advisable to copy a standard plant or define a new plant ? Please give reasons.
When a plant is copied what are the various parameters that are copied to the target plant ?
Thanks & regards,
SurenderSurender,
SAP recommends creation of plant by copying. Generally when a new plant is created it should be copied from any of the existing plant which functions similar to the new plant.
The reason for this is when creating we may miss to update all the required configuration and all the configuration tables with links would not get updated. This also reduces time of setting plant as you need to just change/add configuration where ever required in the new plant.
But if you are a fresher trying to test in your test system... create it in create method so that you will understand in the hardway as what all needs to be configured, it will be a good learning which you will not forget. Please dont try this when you are working with a client system as this make give you lot of trouble and need lot time to resolve issues.
Regards,
Prasobh
Regards,
Prasobh -
Multiple plants creation is possiable with one Tcode in MM?
Hi All,
Is there any way to Create multiple Plants at once... like creating 500 Plants with one transaction code in MM? Don't want to use upload programme like LSMW.
Thanks in advance.
Shah YanHi,
I dont think its possible to create multiple plants using a single T.Code. Since creation of Plant includes the maintenance of Address details.
Hence the only option you have is upload tools/programs such as LSMW.
Hope its clear.
Regards, -
Plant selection missing from dropdown during PR and PO Creation
Hi Everyone,
Good day!
I am currently experiencing problems during PR and PO creation. Everytime I try to access the list of selection for the plant field, the system does not display any entries. (In our sandbox client)
In our dev box, I was able to perform the 2 fucntions succesfully. Can you guys please help me check what would be the issue for this? What would be the procedure that I should follow to investigate this concern?
Best regards,
DeLoHi,
It is up to the consultant who is configuring the system to decide how it ahould be done... one dev 1 TR or many dev 1 TR.
Say now you have created 2 TR's for plant creation and plant assignment.
The TR's should move in to other client has it is created.
now for example ur plant assignment TR is moved first and then the plant creation. the other client in which it was moved will contain only plant creation that is it has our assignment TR is overwritten by the 1 TR which is plant creation.
Usually consultants do it this way.
1 TR - Org Strusture
1 TR - Purchasing
1 TR - Inventory
1 TR - Invoice
1 TR - Valuation and AAD
and so on..
Thanks & Regards,
Kiran
Maybe you are looking for
-
Bbandtalk sip setup cant make outbound calls
hi i have extracted the sip settings for my bbandtalk service and loaded them into my 3cx server and it has registered fine. However, I cant make outbound calls. It comes up with a message saying 'sorry you cannot make or receive calls on this line'?
-
Business Partner Properties - Property Name
hi, can anyone tell me which table is used to store the 50 character Property name text field for BP properties? Thanks
-
How to set Shortcut keys for button in Apex
Hi Could anyone help me on how to set shortcut keys for buttons in Apex. I need to use say ALT + S to submit the page. The following thread pertaining to HTML DB refered to use ACCESS key. but that couldnt work in my case. Re: operation of the app. w
-
I have an animation that builds to create a logo, basically inividual shapes fade in. Once the logo is built I would like to run a lighting effect at the bottom of it that will loop, but do not want the whole animation to start over with the loop. Wh
-
How to Get Sametime (enterprise IM) on my playboook
I use Sametime Connect as my IM for work. I was able to download Enterprise IM (Version 2.5.46) to my Blackberry Bold. It works great. I am able to send and receive IM's just like I was at my computer. I have since purchased a Blackberry Playbook and