Creation of production order while mrp run

hi
ppgurus
can any body explain how to create a production order by mrp run
ie
sysytem should create the production order directly while mrp run not PLANNED ORDERS
what settings i need to do for  this plz explain
urgent requirement
regards
sasikanth

HI
you gave a good way to solve the problem
if it is a make to stock REM
i  need not convert planned order to production oreder right
plz suggest in  that scenario where i need to  do availability check
in REM for which oder type (say PE IS STANDARD)
to be assigned for availability  check
plz suggest because in spro (t -code opjk) at order controll
i dint see the order type PE
the order controll (opjk) in discreet  :- avialability checking rule assigns
in which setting this setting to be done in REM

Similar Messages

  • Sales Order Assignment not seen in Production order after MRP Run

    Hi,
    I am running a Scenario with Strat 50.
    I am maintaining Strat 50 thru MRP Group in MRP 1 View.
    Creating Production Order through Sales Order.
    When i am running MRP thru MD02 I am able to convert it to Planned Order but when i convert Planed Order to Production Order, i am not able to get Sales Order assignment in production order
    Please guide me,
    Thanks in advance,
    Harris

    Dear Harris,
    Sales order planning is done via MD50 not MD02.Hence,please execute the MRP run via MD50.
    This will copy the requirement from SO and the appropriate procurement proposal will be generated,say planned order.
    Here we will be able to view the sales order assignment.
    Regards,
    Joseph Charles Vaikathussery
    Edited by: Joseph  Charles on Nov 3, 2010 4:26 PM

  • Sales order while MRP run

    Hello friends;
    My requirement is such that when i run mrp in MD02, system should not consider those sales order that are planned in previous MRP run. System should consider new sales orders that are created after MRP run.
    Waiting for reply.
    Thanks.

    Hi,
    One solution is go for individual Sales Order/Line Item MRP run using T.code MD50.
    But I can't understand problem with use of MD02.If Receipt element(Plan order)is there which contains the Account Assignment of that Sales Order line Item then I don't think system will replan for same Sales Order Line item.
    Regards,
    Dhaval

  • BOM Selection Mandatory while creation of Production Order

    Hello Friends,
    I would like to know that is there any option other than production version which makes it mandatory to have valid BOM must for creation of Production order / coversion of planned order to Production order.
    I have tried with Production version option but it doesnt throw any error in case BOM with inactive status has been selected in it & also Production order gets created & released.
    Before going for user exit / enhancement option, I just wanted to ensure that it is not possible with standard SAP.
    Kindly share your views on the same.
    Your urgent replies will be highly appreciated.
    Regards,
    Tejas

    Hello Tejas,
    I think this is standard SAP Behaviour.
    Try with following exits:
    PPCO0018
    PPCO0012
    Also check out the following link:
    [How To Make BOM Mandatory while creating Production Order;
    Regards,
    Vinod

  • Production orders in place of planned orders in MRP run

    Hi,
    Please help me with this senario,
    we receive saleorders through CRM interface then these are chnged to redistribute to different plants by changing the plants in saleorders.
    we want to run and create production orders directly for these saleorders without creating planned orders.
    I tried using strategy 82 but it makes the production order online, but we want it to be created after mrp run.
    Is there a way to create production orders instead to planned orders in MRP run.

    Hi You used Right strategy only.Use Strategy '82',  Transfer requirement from CRM and execute MRP run in Background.It will generate Production order.But i didn't understand what you mean by 'Online' 3
    Pl.  Correct me If I am wrong.
    Edited by: Velmurugan S on Mar 4, 2008 10:02 AM

  • Incorrect component in production order by MRP

    On conversion of production order via MRP, in production order one of the component is incorrect with reference to BOM where
    as on creation of PO manually by T code CO01 the component is correct even in planned order too it is correct by manually.
    suggest any clue for the above.
    Edited by: jayalakshmi999 on Mar 5, 2011 12:52 PM

    Dear ,
    Please check the following :
    1.BOM validity and componenet valididty  while MRP run .Basically , during MRP run , system cheks set up in MPR4 view -BOM Selection and Explosion Indicator  and then explode the BOM with its compoenet having correct valididty date .If  the componenet does not have correct valididty (From and To date )  , then BOM may be selected without this compoenet  and generate planned order as well as subsequenetly , carried out the same in Production Order .
    2.In case of Direct PO , you have Production Order Basic Finish  and Start date which comply with the BOM Valaidty including this component so system will copy the BOM along with all the component listed inside .
    3.If you are maintaining PVs with differenr BOM Alternative and routing with Lot size and valaidty , if it is not matching  according to MRP4-2/3 indicator in BOM Slection /Explosion methods , then it may selecting the other alternative not having thew companet listed .
    Check in test system and come back
    Regards
    JH
    Just check in the

  • Creation of production order with reference to sales order

    dear all guru's,
                       i m having a requirement of creating production order with ref to sales order but without changing my old strategy of make to stock.
    regards
    ujwal

    Hi,
    For the purpose of creation of production order with reference to sales order while maintaing MTS strategy you need to maintain Make to stock strategy 40 in strategy group in MRP-3 View of Material Master.
    This is the only Make-to-Stock Strategy which enables you create Production Order against both Sales order as well as Demand / PIR.
    So if your strategy group is already 40 then you need not change it.
    However if you are using any other Make-to - Stock strategy like 10, 11 etc. then it is not possible to create Production Order against Sales Order since they dont consider Sales Order in planning.So you need to change them and set strategy group as 40.
    Hope this helps.
    Revert if you have any doubt.
    Regards,
    Tejas
    Edited by: Tejas  Pujara on Sep 27, 2008 8:50 AM

  • Purchase Requisition on creation of Production Order

    Dear Experts,
    Please clarify the following points
    1 In our Business Scenario on creation of Production Order for a Material, Purchase Requisition is being created on creation of Production Order itself for all Dependent Materials where the items are declared as Non Stock items in BOM  and for the stock items only on MRP run the Purchase Requisitions are created. Is this the standard procedure, or can we customize to create the PRs for all the items on creation of Production Orders??
    2 What exactly the processing indicator in MRP list indicate?
    Thank you,
    Regards,
    Ramakrishna

    For Non Stock items it is understandable, that a PR has to be created with production order creation , as they are not in the stock.
    For Stock items, the creation of PR cannot be linked with Production order creation but can be done with MRP run.
    We can make the system create planned orders or Purchase requisitions or PR in opening period during MRP.
    Processing indicator gives you the scope of PLanning.
    PLanning all the materials within the Planning horizon  --NETPL
    Plaqnning all the materials beyond also--NETCH
    Deleting the current plan and recreating the plan.-regenarative PLannng
    regards
    Ratan

  • Block Creation of Production order Unless released in Order.

    Hi Experts.
    we have a requirement where we want to block the creation of production order inless it is confirmed. Is there any User exit / or anyother indicator where i can define or configure so that the MRP run and also the Creation of the production order can be block for a sales order.
    Plz advice.
    Thanks in Advance
    Rishi

    Hi
    But Manually it does allow the user to create Production order .
    I want unless, Say the delivey block at item level is removed , User should not be allowed to create the production order for the relevant line item of the sales order.
    Any more suggestion
    Thanks
    Rishi

  • Creation of Production order for FInished Product through Project

    Hi,
    Pls clear me on how we can create a Production Order for finished product.  
    If we confirm the production orders in PP, cant the same be confirmed in PS.. Should we consider the same activity types in both PS and PP
    Pls clarify

    hi srikanth,
    your answer has been very helpful... but could u clarify  why MRP is run in MD51 for WBS element and in MD02 for network..
    Pls clarify...  My scenario is like this ...                                                                               
    A
                            B                                                                                C
                    D  E F G H I                                                                                J K L M N O
    I have  a Assemblies B and C which are always delivered in sets.. under assemblies B and C,  we have 6 sub assemblies which has its own components.  I am assigning sub assemblies to differenet WBS elements 01 and 02. so, initially these sub-assemblies are produced to stock. this should happen in PP i.e., through production orders generated in MRP run ( MD51 ). In the next phase i will assign Assemblies B and C to another WBS element.  Again system should generate two Production orders thru MRP for this. Here the 6 sub-assemblies produced earlier will be consumed in confirmation of the production order...
    What i am doing is this correct...
    and the procurement for the components is happening thru the purchase requisition generated via MRP. the components themselves are not directly assigned to the project..
    Pls advise and clarify?

  • Creation of purchase order in MRP

    Hi All,
    Is it possible to create purchase order as an output of MRP? If yes, then how?
    regards,
    Mohit

    Hi Mohit,
    SAP has not provided such facility of directly creating the Purchase Order in MRP run, intentionally, so as to
    1. Provide an Authorization Level over the P.O. creation
    2. Provide a chance to change the Planned order or Purchase requizition before PO creation
    3. As this is a procurement proposal that is directly linked with the vendor, quantity and Price, it has to   be created very carefully.
    I hope you got it.
    with regards,
    gnk

  • Automatic creation of production orders via planned orders

    Hello experts!
    is there a way via customizing to trigger an automatic creation of production order from a planned order when the planned order finished date is within the next week?
    thanks

    David,
    Not in customizing.
    Most people create a job step after the RMMRP000 program step in their MRP job, using program PPBICO40.  Dynamic date range is available as a selection criteria against the opening date, which is the standard criteria for selecting and converting planned orders (not finish date).
    Best Regards,
    DB49

  • Reg:Bapi for mass creation of production order/confirmation

    Dear Experts,
    I wanted to know with the following BAPI is it possible to create Multiple production orders for different semifinshed Materials along with material availability check and other functions similar to CO01 transaction.
    I knew there are standard transactions for mass confirmation for production orders. But i need a confirmation on this BAPI . As i am planning to go-ahed with ,mass creation of production order creation / Order confirmation in single custom transaction.Need back flush activity even supported.
    BAPI_PRODORD_CREATE to create the orders.
    BAPI_PRODORD_RELEASE to release the orders.
    BAPI_PRODORDCONF_GET_TT_PROP to get the default data for the confirmation.
    BAPI_PRODORDCONF_CREATE_TT to ost the confirmation of production order.
    Along with this BAPI do i need to commit any other BAPI to carry out back flush for components.
    Need your suggestions to take it further.
    Regards,
    Daya.

    Dear SAP Daya
    If the issue has been solved, please close this thread.
    You have already mentioned that the issue has been resolved, thefore, you should not ask for help on another thread before closing this one, as it looks like you are trying to force people to answer your threads.
    Users are always trying to answer as many threads as possible on good will we don't need this kind of "incentive".
    Please read carefully the The SCN Rules of Engagement, especially point 8:
    Be responsive. If an SCN member has answered your question, please mark the answer as "helpful” or “correct”. Mark the discussion as “answered,” so that other members can find the answers more easily
    Also, I checked your old threads and I could observe that there is only one closed. Please review your old threads and close those already solved.
    BR
    Caetano

  • Header Material Repeated during creation of production order

    Sir,
    I have defined bom as one component and 3 co product.
    During creation of production order in operation overview i found header material is repeated in components.
    Pl. suggest me where i have made mistake.
    Regards,
    Vivek

    Hi
    Check whether BOM is recursive or not? also check the movement type against the header material.
    Also check in CO03>Goto> Material list
    Regards
    Anupam Sharma
    Edited by: anupam sharma on Jan 30, 2012 12:17 PM

  • FM for creation of production order creation

    Hi All,
    Can anyone tell me the BAPI for the production order creation.
    BAPI for creation of production order through CO01 transaction code.
    Thanks in advance
    Ramesh.

    Hi,
    Please check this FM CO_ZF_PRODUCTIONORDER_CREATE.
    Regards,
    Ferry Lianto

Maybe you are looking for

  • GW8 and MS Office 2010

    Our company recently send an emergency alert notice to all of our customers via email (GW8) Total sent was approx 17K emails. I have received approx 4K in returns for bad email address. My question is this: Is there a way to extract/export all of the

  • Sorting XML using DOM4J

    Hi All, Below is a sample XML which needs to be sorted based on the "id" attribute of the "key" element. <?xml version='1.0'?> <main> <key id='16066'> <key id='16061'> <key id='11'> <key id='1'> <key id='2'> <key id='1001'> </main> I am trying to sor

  • Unknown ALERT while loading class

    When I try to load a class in the kvm I get the following error: "ALERT: Cannot create class in system package" I've done a Google search, and a search on this site, with no luck. Am I the first person to get this error? I have a few ideas about what

  • Is Company Code Activation (Set to Productive) typically included in Mock Cutover

    Hello. In a typical mock cutover, is the setting of the Company Code to productive typically included? Given that it can be re-set, I can't think of a down side to doing so. I'm just looking for what is standard practice. Thanks.

  • BOBJ with NW BI 7.3

    HI, How is the BOBJ connectivity is planned with NW BI 7.3? What will be the version of the BOBJ for NW BI 7.3? Please advice as we may plan an NW 7.3 upgrade soon once it is available. Thank you, SC