CTM Order Selection MTO scenario

Hi,
I  have cfreated a Sales Order in ECC with Requirement Strategy as Made To Order and CIFed the order to APO.
The order is getting CIFed and is reflecting in APO.
The issue is that when I try to do Demand Simulation using CTM the order is not getting recognised.
Is their some setting that needs to be done in case Sales Order for MTO scenario.
Please help me in this regards.
Thanks,
Sanjog

Hi Sanjog,
can you see the sales order in APO (/sapapo/rrp3).
please maintain in the demand prioritization profile the category for this sales order and then try simulating the demands.
let me know if it works.
Thanks
Binod

Similar Messages

  • Error While doing settlement for Sale Order in MTO scenario

    Hi,
    In MTO Scenario - when i try to settle Sales Order i am getting the below error. Even i have maintained the settlement cost element for PSG in allocation structure A1.
    Kindly help me
    Define a settlement cost element for receiver type PSG
    Message no. KD506
    Diagnosis
    In allocation structure A1 (controlling area BP01), you did not define which cost element should be used when settling costs/revenues of the sender. Nor did you define receiver type PSG.
    Procedure
    Assign a different allocation structure to the settlement sender (-> Master data -> Settlement rule -> Goto -> Settlement parameters), or maintain allocation structure A1.
    Thanks
    Kishore

    Hi
    Please check your allocation structure , it looks that settlement cost element that you have assigned in the allocation strcuture is not having correct cost element category.
    Go to Allocation structure configuration (OKO6) and check your allocation structure A1.
    check settlement cost elements is it by cost element or you have assigned separate cost element for settlement.
    if you wants to settle with same cost element select By cost element.
    if you wants to settle with different cost element create a cost element and assign settlement cost element.
    http://help.sap.com/saphelp_di46c2/helpdata/EN/9d/1f4b6e5733d1118b3f0060b03ca329/frameset.htm
    hope this helps you.
    Regards

  • Sales order costing - MTO Scenario

    Hi Experts,
    I am working on SAP ECC 6.0 on a Make-to-order scenario.
    I have created sales otder; run MRP for the sales order and converted the planned order to Production order and confirmed the production order.
    But I don't know the period end processes of make to order scenario. Please answer my following queries:
    Whether <b>WIP</b> will be calculated at Sales order level or individual production order level related to this sales order?
    Whether <b>variances</b> are to be calculated at each production order level or at sale order level?
    Which t-code should be used for calculation of variances if it is calaculated at sales order level? The production orders have TECO status. 
    Whether variances are to be settled at sales order level or each production order level?
    Which Transfer Control should I use in Costong Variant "Sales Order KDN" or "Complete Transfer"?
    Please also forward me some documents, if you have, which explains the whole step by step cycle from creation of sales order to settlement of sales order.
    My email id is  [email protected]
    Request your help.
    Thanks & Best Regards,
    Bijay Kumar Deo

    Hi Bijay
    To add few more checks and points - please note the following
    1)  Whether WIP will be calculated at Sales order level or individual production order level related to this sales order?
    A)  You need to selected RA for sales order in WIP RA version to ensure WIP is calculated for production orders which are linked to sales order
    2)  Whether variances are to be calculated at each production order level or at sale order level?
    A)  This would depend on whether u r following valuated or Non Valuated sales order stocks / costing
    If is is non valuated u cannot determine variances, actual costs of production order are settled to sales order item
    If it is valuated sales order following sales order costing, you can transfer production varainces to sales order item
    3)  Create settlement profile having sales order as valid receiver and assign profile to production type created for the sales order - MTO scenario
    4)  Which Transfer Control should I use in Costong Variant "Sales Order KDN" or "Complete Transfer"?
    4A)  Suggested to have complete transfer as transfer control strategy
    Hope the above clarifies.  Please assign points if useful as a way to say thanks
    Any more suggestions / corrections to above points for the above scenairo are appreciated from forum members

  • Re: Error while making a Process order in MTO scenario

    Hi All,
    I am having a secnario, where I am using MTO scenario. I want that the sales order should trigger the process order.The components in the BOM for the FG material .
    1. Raw material: procured from outside: Stock & value relevent.
    2. This one is non valuated one :procured from outside: Stock &  Non-value relevent.
    Now when I create a sales order, I can see a plan order in the MD04 scree for this FG . But on drilling down this plan order I can only create the PR for the 1st component only ,for the second component I cant create anything.
    The second item should be non valuated & stock relevent.
    Please help me in this regards,
    Vivek

    I have taken help from some other threads to resolve this issue.

  • How to Copy Cost Estimate from Quotation to Sales Order in MTO Scenario

    Hi,
    We are working on a MTO scenario- Sales order Costing with Valuated Stock.
    And our case we are creating the Cost Estimate at the time of Quotation using PP qty structure. Now we wan to transfer the cost estimate to Sales Order as we don't want to recost the sales order.
    Currenty it's transferring only the EK01 condition as total planned costs in Sales order but we want to see the itemization also.
    Please suggest is there any way to transfer this cost estimate with itemization from Quotation to Sales Order.
    Regards
    venkat

    Hi
    As far as I know the CO esimate does not get copied from Quotation to Sales Order
    You need to recost the SO again.. If your Qty Structure has not changed between Quotation to SO and your valuation variant is also the same - it would give the same result
    br, Ajay M

  • Transfer of Sales Order stock - MTO scenario

    Hi,
    We have a situation in a MTO scenario, in MMBE we see a Sales Order stock for a material.
    THe Sales order is archived from the system and he corresponding PP order is also in TECO status.
    We need ot use that Sales order stock and transferit unrestricted.
    We cannot use any of the movement types as we get the error message Sales order is archived and does not exist.
    Is there any way we can use the Sales order stock. Please suggest something orther than reversing the PP cycle.
    Rg,
    Vipul

    Hi Vipul,
    Please check OSS note 202345.
    BR
    Csaba

  • Changing the Assignment of production order in sales order in MTO scenario.

    Hello all!
    I have following problem:
    After the MRP a production order was created for a sales order. Because of the production in another plant
    the production order which was created automatically had to be technically completed and a new one
    created.
    If you want to check now the availability, the sales order finds nothing, because it's linked to the one,
    which was technically completed. Now is the question how can I change the production order for this
    sales order. (In the production order the correct sales order is connected!)
    As I found out it's connected to the field AUFNR in the table VBEP. But how can I change this
    field within a transaction and not in the database?!?

    No replies

  • MTO Scenario - Deletion flag not active in Production order

    Hi,
    I have a production order with MTO scenario, even if the order is CRTD status, i could not set the deletion flag to the order. Deletion flag activate and revoke options are grayed. What could be the reason for that..? how can i set the deletion flag to that order now..?
    Thanks in Advance,
    V.S.Sabitha

    Hi,
    My status is CRTD PRC  MANC SETC.
    The status profile header field is 'Blank' for my order type in spro settings.
    In BS22 for I0076, BFRZ - Revoke status 'Released' is set to 'Forbidden' radio button.
    Only for the MTO material, i could not activate the deletion flag. For other materials, the deletion flag option is active both in Created and Released status.
    Sabitha

  • No FI document generated while doing GR for Production Order in MTO Scenaro

    Hi All,
    In material master the strategy group is 20.No FI document generated while doing GR for Production Order in MTO Scenario. Then strategy group changed from 20 to 50 but still No FI document generated while doing GR for Production Order in MTO Scenario.
    Could u please let me know whether FI document is generated at the time of GR against production order in case of MTO scenario.
    Regards,
    Nandan.

    Hi,
    While doing GR with ref to Production order check whether price is picking up or not for the production order.
    Regards
    Ravi Shankar.

  • Change in Sales Order Qty in a MTO scenario

    Hi,
    We had confirmed 5 Qty for the Production Order created with reference to Sales ORder(MTO scenario), now after confirmation of 5 qty, sales order qty is reduced to 3., then in this situation, what we need to do for the already confirmed extra Quantity 2 for this sales order. I think we need to cancel the confirmation for the extra qty 2?. Please clarify and explain what we need to do this for this extra Qty 2 in detail.
    Case 2) If the Sales Order qty is changed to 7, then we will be creating a new Production Order for this new quantity 2 with reference to the same sales order.  Am i correct?.IF wrong, please suggest how should we balance the extra requirement of 2 EA.
    Thanks in advance.

    Is your query being posted even before you actually tried the 2 cases which you refer to in your system?
    If so, then first do the simulation in your sandbox, check how system behaves when you do that. Also check by clicking on ATP check for the material within SO.
    Once you do the above your query will be self answered, if you still face any issue then revert with the specific details.

  • Block production order creation in MTO scenario when sales order is blocked

    Hello Experts,
    We are using the MTO scenario and creating production orders with refernce to sales order using CO08.
    The requirement is to not allow the creation of production order when the sales order has a block. It can be an overall block or a credit block.
    Right now the systme allows me to create the production order with refernce to the sales order even when the sales order is blocked.
    Is there any way by which this check can be activated.
    Thanks
    Ritesh

    Hi!,
    Please try follow:
    Go to path IMG > Plant Maintenance and Customer Service > Master Data in Plant Maintenance and Customer Service > Technical Objects > Serial Number Management > Define Serial Number Profiles. There enter "2" in Stkck column for your serial profile.
    Regards,
    Uday

  • Not getting Material Costs in Production Order - MTO Scenario

    Hi,,
    When we are execting MTO Scenario, We are not getting Material costs in Cost analysis of Production Order (Transaction Code CO03).
    We have executed cost estiamte. but we are not gettig the material cost.we are getting only Activity price of Labour Hours.
    The problem is -
    1. we have created Sales order
    2. we have Run MRP & Planned order changed as production order
    3. But in this production order Costing Relevancy check box was not activated automatically. it is in gray mode and not able change this.
    4. Is the problem with SD configuration? Kindly help me in fix this issue.
    Note  - if we create production order directly - it is showing the Material cost. But only in MTO scenariod it is not giving the material cost.
    Kindly help me how to fix this issue.
    Thanks
    Kishore
    Edited by: Emergys Corp on Nov 5, 2009 7:02 AM

    In Requirement class (SD Configuration - OVZH)- we have to give valuation & Costing Sheet assignment.
    Thanks
    Kishore

  • No Accounting Document generated for goods issue in case of MTO scenario

    Hi all,
    I have MTO scenario & the industry is trading. So I have all trading goods. In SPRO - Sales & Distribution - Availability Check and Transfer of Requirements - Transfer of Requirements - Determination Of Requirement Types Using Transaction I have determined requirement type as KE.
    In material master I have used strategy group as 20 for Make to order scenario. In the settings "Determination Of Requirement Types Using Transaction" I have determined the requirement type as "KE".
    The requirement type "KE" determines a requirement class "040 - MkToOrdNoValW/o cons". Here the account assignment category is "E-Ind. cust. w. KD-CO".
    Now I created a sales order, the system determined the requirement type as "KE". I saved the sales order, assigned the stock to the sales order  & created a delivery.
    I did the PGI also. But when I check in the document flow, for the material document the system has not generated any FI document where we see the accounting document for the "cost of goods sold" & "inventory" G/L accounts. The system gives a message "Material document 4900000023 does not include an accounting document".
    Note:
    1. When I create the sales order with normal MTS scenario, the system creates an accounting document for the material document at the time of goods issue.
    2. The valuation class in the material is 3100 for trading goods.
    3. The following settings have been made in OBYC.
    for GBB, the G/L accounts have been assigned for general modifier "BSA", "VAX", "VAY" & "VKA".
    Please suggest me as to where i am missing any settings.
    With best regards,
    Niyaz Sayyed.

    Dear Niyaz Sayyed
    You need to check in the following areas:-
    -  check whether the material is defined as non-valuated stock
    -  go to OME9, select your Account Assignment and see whether you have checked the box "GR non-valuated".   It should not  have been checked
    thanks
    G. Lakshmipathi

  • Planning Strategies for MTO scenario

    i have an FG which has strategy 20 assigned to it. I have an SFG which i want to link to the sales order. i also want the planned order to be generated to capture the minimum and maximum lot size and not generate on per requirement basis. example for the semi-finished, a sales order needs a reqt of 20, but min and max lot size is 12000, planned order should be 12000. how do i do this?

    Hi Raf,
    as you know that, for MTO Scenario the Lot sizin will be EX and no other settings are allowed.
    But there is a provision fulfill the requirement.
    Now in the Transaction: OMI4 for the lot size : EX
    For MTO Lot size select 1  Lot-for-lot with rounding
    Maintain the rounding value in the MRP Views as per your requirement like 12000 PC.
    Now every time system tries to round it to 12000.
    Hope this helps..
    Regards,
    Siva

  • How can we assign a different scope of planning in MTO scenario?

    Hi,
    We are using MTO scenario. In this case, during sales order creation checking control AE is getting triggered. We want to use a different scenario during rescheduling transaction. But as per my analysis, V_V2 is also calling the same AE checking control eventhough we assigned a different checking control for Back order processing.
    In this case, can we assign a different checking control (scope of check) for back order processing?
    Regards.

    Let me explain my requirement here....
    This is a kind of trading or sub-contracting. Initially we will give the forecast to vendor...but Vendor will start the finished product production only after getting the confirmed order from us. Hence we thought to use strategy 50. So we will create a PO to Vendor only after getting a confirmed sales order from customer.
    But in strategy 50 ATP confirmation is based on PIR. Hence we created a new requirement class (copy of 45 with ATP active). So in this new strategy ATP is against actual receipts instead of PIRs.
    But sometimes Vendor may not be able to supply as per lead-time...and he may postpone the delivery date. In this case we are getting exception message 10 for the PO...even though PO is specific to a sales order. Still rescheduling job (V_V2) is not populating the new confirmation date as it is referring to the TRLT.
    Hence we want to use ATP based on TRLT during sales order creation. And during rescheduling we want to use a different scope of check ('without TRLT' and with 'No storage location check'). Hence we created a new checking rule for rescheduling and this we assigned for that specific plant.
    As per my observation, rescheduling job is not picking the scope of check that is assigned for rescheduling....it is calling the same checking rule AE during rescheduling also.
    So my question here is... can we call a different scope of check during rescheduling run while using make to order strategy?
    Regards.

Maybe you are looking for

  • (CS4) (AS) Syntax for assigning existing Preflight Profile

    Building an AppleScript workflow to tie a FileMaker database to IDCS4, using Triple Triangle's Job Spec Cubed. Very fun. I'd like to add a tell statement to assign existing Preflight Profiles to existing documents. We have four standard preflight pro

  • My new ipod is showing that it is full but I have only loaded about 3gb

    My new ipod is showing that it is full but I have only loaded about 3gb

  • How to relate a button to "control+c"

    Hi: I am using runtime class to run a java program from within the original java program. My question is if I run a endless loop program from within the original program, is there a way for me to just click a button and let the endless loop program t

  • Help with HTML form,please!

    Hi everybody, I'm trying to write an HTML form that would allow user to login if he/she has already created username and password AND that would let him/her create an account in case the user is not registered yet. The code below creates a form that

  • Error when upgrading Aperture library on an external drive

    I have a MacBook Pro and am in the process of upgrading to Aperture 3. When Aperture wants to upgrade the existing Aperture library, it fails saying that there is insufficient memory. (My hard drive is very full). I have copied the Aperture library a