CTS+ object-import to repository shows red status

Hi all,
we are using CTS+ for our PI systems. We are using NW7.0 SPS15 and used the HOWTO guide for SPS14 to implement CTS+.
Every thing works fine, beside, that if somebody starts a transport the cache notification for the object-import to the repository always shows an error (integration repository) the integration directory shows no problem. If the cache notification is repeated the error disappears.
Does anybody have an idea what could be the problem or how to track the error?
Thanks for your help.
Christian

Hi Hemant,
thank you for your reply.
My problem is, that note 780747 describes the problem, but does not help...
It could not be a
"Temporary connection error" because the error can be reproduced and vanishes when "Repeat cache notification" is used (other user is used).
It could not be a
"Errors during the retrieval of cache data" because there is no problem shown in the "Problems" tab.
It could be a
"Incorrect configuration" but how do I check this? The rwb shows no problems (other user used than in CTS+) and as mentioned before, there are no problems shown in "Problems" tab.
I think the problem is, because the user NWDI_CTSADM is missing some permisions to start a cache refresh, but the user owns SAP_XI_CMS_SERV_USER, SAP_XI_DEVELOPER and SAP_XI_CONFIGURATOR as described in "How Tou2026 Configure Enhanced CTS for SAP NetWeaver Exchange Infrastructure 7.0 SPS14".
So my question is, how do I start a cache notification with a special user?
How can I check whats the problem?
Thank you for you help!
Best regards
Christian

Similar Messages

  • Why PSA data show red status when opened but green on PSA page?

    Run RSA1 -> click PSA to open PSA page, locate one infosource and find the PSA under it, find the status column shows it's green, but when opening it, find the 1st column shows red for each row.  How does the inconsitance occur?
    BTW, if we open the infopackage monitor for the above one, find a weird thing is that each request get two consecutive processes running with a circle of red ball and green ball in the left frame.  Double click one of them, in the right frame and click the monitor Status tab, the msg window is as following (in between two dashed lines below):
    Incorrect data records - error requests (total status GREEN)
    Diagnosis
    Data records were recognized as incorrect.
    System response
    The valid records were updated in the data target and can be used in reporting.
    The incorrect records were not written to the data target, but were posted retractively under a new request number in the PSA.
    Procedure
    Check the data in the error requests, correct the errors, and post the error requests.
    Sounds like the data failed to uploaded to data target due to error in PSA, but why the status show green in somewhere?   And if clicking the Details tab, all show green!  Weird!
    Thanks

    Hi Kevin,
    In your InfoPackage Update tab, click the Error Handling button. It seems that the Valid records update, request green option is chosen. This is why you see the green request and some error records.
    This means that the corect reocrds were loaded and are available for reporting, but the incorrect ones were left behind. This is used to check the erro records separatelt so that they do not disrupt the entire data load.
    Hope this helps...

  • In PI7.1 channels showing RED status actually working without issue

    Dear All,
    In PI prod environment, we have two decentralized server on which SFTP channels are deployed.
    once few SFTP channels got into error with socket exception stating: Could not connect to remote host or directory.
    However there was something strange to see that the communication channels were in the error status but the messages were still processing. No issues reported by the business: business impact = 0.
    this incident has happened twice.
    Can someone tell me what could be the reason of this wrong status?
    before raising OSS , I want to know if someone has faced this issue?
    Regards,
    Ratnapriya

    Hi ,
           There might be some issue with the channel initialy but it would have resolved after some time. When the channel retried after certain time the channel polled successfully.
    Channel shows in RED status untill all the 25 entries are filled in your channel processing details(if all your channel entries in processing details is filled with successfull message ID's  the channel will automatically change to green ).
    Regards,
    Naveen.

  • MDS 9216 - showing red status LED, not starting up

    Hi,
    In a recent power loss (took out our R&D UPS in the process), an MDS 9216 we have in R&D failed.
    On power up, it shows a red status LED, and does nothing. We've pulled and swapped PSUs (something we're told is a common fix for a common problem with these chassis), to no avail.
    Strangely, we pulled the fan card (which had a green light), and put it back in to see it now also has a red status light.
    We've swapped all cards around for new and spares (even the main cards) and they show up with red status lights in the chassis (can't test them in another chassis at present) so I assume this problem is with the chassis itself (ie the backplane or PSUs).
    Any ideas, any similar experiences?
    Many thanks,

    As far as warranty, it would be covered for 1 year or 90 days from purchase....not sure which, but since the 9216 is end of sale for a few years now, I doubt that is covered under warranty. If you have a maintenance contract covering that 9216 serial number, then it would be covered. The design on the 9216 is that the module 1 is not field replaceable. There is no Cisco part number for the slot1 line card. It is a hybrid of a 16 port FC module with a supervisor daughter card. It is basically considered part of the chassis. If you have your own spare 9216 and feel energetic you could replace the slot 1 line card....but from the official support perspective, it is not replaceable.
    There are no other replaceable parts besides the chassis and PS that would cause this problem. (I assume you have removed any line card from slot2 to be sure it was not causing the problem).
    Thanks,
    Mike

  • FILE TO IDOC SCENARIO-Receiver Business system ECC showing Red

    HI
         In File-idoc scenario Business system showing red status in RWB .And i have given the role for the business system as application server and configure related integrated server . But the error in a RWB  for the ping and self-test is as follows
         Unable to log on to system buss_ecc_200 in language en with user PIRWBUSER .
    I thing from XI side every thing is ok. But for bussiness system side ECC might miss some configuration .
           could any help in this issue:
    regards..

    Hi
    Please try one of the followings:
    1) In Configuration --> Business service --> Service --> Adapter specific identifiers. Give logical system name for the sender system (e.g XI_00_800)
    2) In Design --> mapping objects. Give all information of sender n receiver in EDIDC40 segment and
       In configuration --> receiver communication channel in that enable the checkbox take sender from payload.
    3) In configuration --> Receiver Agreement --> Header mapping --> Sender Service (Give XI1 i.e ur sender system).
    Also check the RFC destination that is the major problem with idoc...

  • Biar file import does not import any repository object

    Hi,
    I have extracted a Biar file from Business Objects Enterprise XI 2.0 Server and it has size 20 MB. When I import this file into another Server using Import Wizard which has Business Objects Enterprise XI 2.0, the outcome is unfavorable. Inspite of both the source and target system being on same enterprise version (11.5.8.1111) plus both on Service Pack 2 Fix Pack 2.7, the repository objects log within the Import Wizard shows 0 objects imported.
    What is the remedy to this situation ?
    Regards,
    Neonevin

    Hello,
    Not really that I know of.
    Well this is a big problem since we can not export projects easaly between different computers. Or back to the same computer using this metod insted of the whole project fils and associated files.
    Also there might be a problem exporting to different editing programs as Premiere.
    And Apple do not seem to bother. We have to try to solve problems like this in forums and searching for answers and plugins for hours.
    This i think will make us to leave final cut as editing software.
    Also this version of final cut x - apart from final cut 7 does not seem to be able to export audio in a proper way.
    Especially the audio that can be a little bit lika a worms nest seems to be impossible to export with all or most of the options left. It wants to put everything together in mixes audio tracks.
    POskar

  • ODI objects import in new Master and Work Repository

    Hi,
    I have created a new master and work repository.
    Now,I need to import rest of the ODI objects which are associated with different Master and Work Repository.
    How do i proceed. I need a proper sequence to import the ODI objects.
    I mean topology,projects,model how to initiate.
    Thanks.

    Hi,
    Is it essential to create a new master and work repository and import the master and work repository xml files.
    Or if we just click on import master repository and give the connection details of where we want it will also work without creating it.
    when I click on new in ODI tool, it shows two options create master repository and import master repository.
    In my case which option should I go for?
    I just need to create development env on new server by importing all the required xml files on my local machine.
    Please guide...
    Thanks.

  • Importing Development Objects in Integration Repository ?

    Hi ,
    How do i import development objects that have been exported ? e.g , i export a "message mapping" object using Tools->Export Development Objects, could see it stored in a folder in the XI server m/c , however , when i try import development objcts option from Tools menu, i don't see an option to specify the location of the .tpz file which has to be used for import !!
    Also , if i try to import the message mapping object which was created in a different namespace to my new namespace, will there be any issues ?
    Are there any changes that have to be done in my new namespace( assuming i will be able to do the import in the first place).
    Ne pointers as to how to do it are welcome
    Thanks
    Saravana

    Hi,
    When you export 'a message mapping object'/repository objects (all objects in repository is called repository objects), it is stored under
      <install_path>/xi/repository_server/export
    To import this object, you must manually copy this into
      <install_path>/xi/repository_server/import
    and then choose the Tools -> Import Design Objects..." menu option to import the repository objects (only the files from the import directory can be selected).
    If the import is sucessful, the import object will be moved to /importedFiles folder.
    While importing, i don't think you can change the namespace of the object. After importing also it will have the same namespace as before importing.
    Hope it helps.
    - Sreekanth

  • Request shows in Red status after extraction of Data from Planning area

    Hi Experts,
    I am extracting data from DP planning area to APO BW Info Cube. It was working fine but from last few days after extraction we are getting Red status of that request. However whatever data packages we are extracting we are getting same in to Info Cube also. But only status of that request is in Red.
    I gone through step by step analysis I found "Data selection succesfully finished?" statement in Red status & rest are in green. When I gone through the details of this statement then I found Missing "Message:Selection Completed" in yellow status.
    Any Idea? How do i resolve this issue?
    Please advise..
    Regards
    Sujay

    Hi Sujay,
    Check the logs obtained after the extraction.
    This only will tell you fare idea for you to proceed further
    to resolve the error that has happened.
    Also check whether the extracted data is correct by
    random sampling of extracted data
    Regards
    R. Senthil Mareeswaran.

  • SAP_APPL,600 is showing Red Cross after upgrade the EHP3

    Hi All,
    I have applied EHP3 for SAP ECC 6 on Window server 2003.
    Almost all support packages successfully upgraded except SAP_ALL and EA_APPL,
    There are SAP_APPL,600 is showing Red Cross under the following tree.
    SAP_APPL
       -->SAPKH6001
          -->Prerequistie set 01
            --> SAP_APPL, 600        X (Red Cross)
            --> SAPKNA7001           OK
    and above highlighted issue is looking same in remaining prerequistie of
    all Support Package under the software components SAP_APPL and EA_APPL.
    How can i resolve this issue?
    Regards,
    majamil

    Dear Majamil,
    What does the Import Status show?
    As per me if the import status shows Green there is nothing to worry. As I have checked in our EHP3 system its the same but we are not facing any issues. I guess we can ignore that.
    Regards,
    Antony Chaitanya.

  • Orphan objects in Central Repository

    Hi guys
    I need to identify the orphan workflows and dataflows that exist in the Central Repository but are not linked and used anywhere. They were used to be referenced but as not anymore and I want to idenify and delete them from Central Repo.
    Have you any idea how to do that?
    Thank you.

    Hi,
    Go to the top level object as per the hierarchy in the Central Repository (Project / Job / Work Flow etc.), right click the object and choose checkout with filtering / get latest version with filtering (based on the permission full / read) on your object.
    This will show a window with all the dependents of the object which you have chosen. If the window shows destination status of only one object (the object which you have already chosen), then you can confirm that there are no dependent objects for this in the Central Repository. If you have full permission on this object, you can right click and delete the same from Central Repository.
    Regards,
    Suneer

  • Snapshot agent showing red mark in replication monitor!!!(Merge replication)

    few days before snapshot agent showing red mark in replication monitor without any changes...
    synchronizing from publisher to subscribe working fine...
    and how to clean up snapshot agent job history...
    plz give me a solution...
    Thanks in advance.......

    error:
    The replication agent has not logged a progress message in 5 minutes. This might indicate an unresponsive agent or high system activity. Verify that records are being replicated to the destination and that connections to the Subscriber, Publisher, and Distributor
    are still active.
    snapshot agent showing red mark...
    Hi Baraiya Kirit,
    According to the error message, the issue could be caused by that the agent is busy or the agent cannot log in to one of the computers in the topology.
    To troubleshoot this issue, please perform the following steps. For more details, please review this article:
    MSSQL_ENG020554.
    • If the agent has stopped, please restart it and check if the error still occurs.
    • If this error is raised frequently because the agent is busy:
    You might need to redesign your application so that the agent spends less time processing.
    You can increase the interval at which agent status is checked using the Job Properties dialog box.
    • If an agent cannot log in to one of the computers in the topology:
    We recommend that the -LoginTimeOut value be set lower than the interval at which the replication agent checkup job runs.
    There is also a similar blog for your reference.
    http://maginaumova.com/the-replication-agent-has-not-logged-a-progress-message-in-10-minutes/
    Thanks,
    Lydia Zhang

  • Workflow attached to content type shows the status as 'Starting'

    Hi,
    I have developed a workflow to distribute documents from Drop Off library to different SharePoint libraries based on the content type that the document uploaded to.
    The drop off library has been configured incoming mail settings hence the documents would be on boarded to drop off library through e-mails. In this scenario, my workflow should be triggered when the document is on boarded through email.
    Another scenario, the user can upload the document to different content type manually and updates the respective meta data values. This scenario, my workflow should be triggered when the item updated.
    So, I have configured my workflow should run on the content types and trigger when item is created through e-mail and item is updated by manual.
    The document on boarded through e-mails are working fine as soon as the item is created.
    Issue:
    The workflow associated on a content type which needs to be triggered on item created is triggering as soon as the user uploads a document manually and shows the status as 'Starting'.
    The workflow associated on a content type which needs to be triggered on item modified is triggering as soon as the user updating meta data values after document is uploaded. Hence, throwing an error
    'cannot open a file from drop off' library exception when I try to read file using C# code as file stream bytes.
    Configuration:
    1. The content types are having mandatory fields which has a default values set.
    2. The document version settings are set as check out the document when editing the properties.
    Please help me to resolve this bug and let me know if you need more details.
    Also, let me know how can we cancel the workflow if it is in 'starting' mode.
    The workflow should run the document is onboardedwhen an item is created and

    Hi,
    According to your description, my understanding is that you want to get data from content type in JSlink.
    I suggest you can get the content type data in JSLink using JavaScript Client Object Model.
    Here are some derailed code demos for your reference:
    http://sharepoint.aspcode.net/view/635399286724222582163436/sharepoint-how-to-get-field-value-using-jsom-jslink-without-async-call
    http://sharepoint.stackexchange.com/questions/93777/how-to-get-contenttype-name-in-clientsidejavascript-jquery-csom-etc-in-editf
    Best Regards
    Zhengyu Guo
    TechNet Community Support

  • How to UnLock the object in Integration Repository of XI.

    Hi Experts, when i try to edit the object in IR, i am getting following message.
    Object Message Mapping EmpResponce_MM | urn:pas.com/neh currently being edited by user 9SGRANDHI.
    Note: it is saying my ID itself, i logged off and logged in, still its showing same mesage, how to unlock the object in Integration Repository of XI.
    please help me out.
    thanks
    siva

    Hi,
    Go to Home page of XI,there u will have Administrator,select it and click on localobjects.There u will have IR and ID in that select lockoverview and remove ur lock.
    this authorization will be given to basis guys check u have it or not.
    Regards,
    Phani
    Reward points if helpful

  • Business Process Engine is showing Red Led in RWB

    Hello to All,       I installed PI7.1 and after client copy - Business Process Engine is showing Red Led in RWB. 
    When I click on BPE, the message at bottom of screen (in Yellow Status) indicates " Schedule background job for clearing report".  Please let me know if any one has the solution with details.
    I gone thru the link in SDN, but no resolution yet.
    Re: Business Process Engine is  showing Red Led in RWB
    thanks, Srini

    Hi Mark,  All the nodes are green under "Maintain Runtime Environment" and "Maintain Definition Environment".
    In RWB, component monitoring --> Display -- Business process engine is RED with message as
    "Schedule background job for clearing report" in Yellow.
    I looked under batch jobs "SWWCLEAR" and it is already ran successfully.
    Please let me know how can i make BPE green.
    thanks, Srini