We are doing a mere job wok. Customer is sending raw materials with delivery challan and 57f4 challan. We are processing the raw material and sending the finished material to the customer. I am receiving the raw material by 561 or also i can use 501 mvt type. I can enter the customer DC number in the TEXT field.
But how to capture the 57f4 challan in SAP. Since we have to do ageing analysis to send it within 180 days.. How to do this?
Thanks in advance,
Raj.
hi
1. Define your customer materials (both component and finished product) as non valuated material, because these materials not effecting the our inventory.
2. create Bom for finished product.
3. Create sales order for service charges with reference to your customer PO.
4. Receive the component from your customer through 501 E (with out po sales order specific).
5. Create Production order with reference to sales order through MRP or manual.
6. confirm the production order and receive the
finished product.
7. Delivery to customer as in normal sales process.
8. Then create performa invoice or billing to your customer.
Please maintain the customer excise challanas manually or you can develop z development for tracking purpose
http://help.sap.com/bp_blv1600/V5600/BBLibrary/HTML/150_EN_IN.htm
regards
kunal
award if helpful
Edited by: kunal ingale on Sep 13, 2008 2:09 PM
Similar Messages
-
Subcontract process (57F4 challan)
Dear SAP Guru,
I implement a scenerio of subcontracting. A new requiremnt is come under subcontracting. i.e A plant send a Material X to subcontractor through 57F4 Challan. And soncontracotr process that material and add some material with X (i.e. Excisable Material which is add to X) and generate FG Y. when we receive the material then subcontractor want to converison charge with ED of adding material. How do we process this scenerio and how we to capture ED with material and how to pay the excise duty to vendor.
thanxHi,
U can Map as -
solution1)
If material code u want for added material then -
Create PO with 2 line item against the vendor.one is procurement item i.e added material and second is s/c item i.e. Y.
Solution2)
If u dont want material code then-
Create PO with 2 line item one is service item which is nothing but the added material cost and second is S/c item i.e Y
regards,
sujit -
57F4 challan print - getting parent item no and po number for child item
Hi ,
In 57F4 challan, Subcontract components - i.e Child items are used for creating the challans.
However while printing needs the parent item no with the purchase order number for that child item number.
It is getting stored in RM07M structure.
Any inputs / suggestions how to retrive parent item number and purchase order number for child item i.e for subcontract items?
Thank you .
Prasad.Thank you for the reply. I checked the table RSEG table for material document and PO details, however the RSEG gets populated when there is credit or debit entries.
In this 57F4 challan there is no credit or debit enteries hence would not get in RSEG table.
Appreciate your inputs for any other alternative.
OR is there any table or Function Module to get the enteries of the struture of RM07M . -
57F4 Challan printing with Purchase order number and parent material
Dear Team,
As a SAP standard 57F4 subcontracting challan will have only legal entities,child materials, quantity, assable value etc.
but as a client requirement we need to incorporate the PO number and line item in the 57F4 challan, additionally client requires the parent material also printed in 57F4 challan
Anybody can help me how to get the PO number and parent material in 57F4 Printing, because i have already searched in MSEG table but for the material document number iam not able to find the PO number and line item.
iam posing the GI with referenc to purchase order only. but even iam not getting the PO number with reference to the posted document number in the table.
J Sridharan
Satyam Computer Services Limitedthanks for your reply hemalatha,
i have tried with OMJ3 transaction, but it is purely a print parameter settings for J1IF form. please help me where i can maintain this settings to get the output in MSEG table.
moreover iam creating all the subcontract material documents with ref to PO number only through MB1B transaction. please advise.
Regards
Sridharan -
57F4 Challan no. re. to PO. No.
Hi,
Is there any std. report with which we can find the subcontract challan number and goodws transfer number ref. to the Subcontracting PO number.
Also in which table we can get the information easily as if we select the Table MSEG to get the material transfer doucment with movement type 541 , syetms it taking lot of time then after that i have to seelct the challan number from another table .
regards,
zafarHi,
Thanks for your reply, it is very usefull, one more think i want to know is there any report in the same way but it should also give the PO numbers for which still there is No GI and 57f4 challan made as in JI17, it is displaying the Po for whcih challan is made.
regards,
zafar -
Hello Friends,
i am facing the below error while do the reconcilation for the 57F4 challan.
"Challan not valid, material doc., is valid for another scenario"
Kindly share your ideas to fix the same.
regards,
sathesHi Dear,
In IMG u have left the Setting.
Logistic General-->Tax on Goods Mvt->Business Transaction-->
Subcontracting--->Maintain Mvt Type groups---->
0001 541
0002 101
0002 542
0002 543 O
0002 545
Please don't enter Subcontracting challan manually...select subcontracting challan number by pressing of F4 and Select it and ente rthe year..... -
Closing of 57F4 Challan or Making GR after 180 Days
Hi,
I want to know if we have made a 57F4 Challan and partial material we have received from the vendor and remaining material we have not recd till the specified period of 180 days then how to make the GR after 180 Days or how to close the challan
second scenarion if we have send material to vendor with 57F4 channlan and we have not receievd material with in 180 Dya then how to close the challan.
regards,
zafarHi niti,
Thanks for reply, i want to know even if after 180 days we have not receieved the material and if we want to cancel all the document how is the sequemce and process for it as we have created PO , MB1B, and J1IF01 challan then how to cancel all the documents
and as u have steps for making GR after 180 Days with J1IF this is std. procedure avalibale for this is there any effect of this on other FI entry etc.
regards,
zafar -
SubContracting Challan (57F4 Challan)
Dear Experts
I want to print the 57F4 challan through system.
I have done all neccessary configuration & able to print the challan. Output type used in this case is J1IF.
Now I have created one output type YJ1F by copying the above output type. Also I have copy the sap script of 57F4 challan & made the neccessary changes & assign to new output type.
Also I have assigned new output type in sub-contracting attributes.
still I am not able get print from the system with required changes. Also system is not giving any message.
So please let me know if I missed out any configuration. or any constraints in regards CIN.
KuldeepHello Kuldeep,
I have completed this requirement for our client and here is the "how to do" SAP wiki page.
<[http://wiki.sdn.sap.com/wiki/display/ERPLO/SubcontractingChallan57F4_J1IF01_J1IF11|http://wiki.sdn.sap.com/wiki/display/ERPLO/SubcontractingChallan57F4_J1IF01_J1IF11]>
Let me know if needed further information.
Regards,
Arif Mansuri -
57F4 Challans. CIN version
Hi Gururs,
We are using CIN version 4.0A. Here is one major problem we are facing.
Just after SAP implementation in 2003, materials were sent to subcontractor along with 57F4 challans. When the goods came back, due to lack of awareness, user created new subcontract orders, raised new 57F4 challans and received the goods against them. So original challans are still open. How to close these challans.
What will be the accounting entries ?Hi,
after a lot of analysis, I found the problem is actually like this:
Initially some subcontractor challans and subcontractor stock was uploaded in the system in 2003 just after implementation.
When the goods came back, for whatsoever reason, user created new subcontracting PO, new subcontracting challan and received the goods against the new challan. The original challan is lying with status "Posted" in the system till date.
(It is also noticed that while creating the challan the system does not create any accounting document. Neither it does any if the goods come back within 180 days.accounting entries to CENVAT account is only made when the goods have not returned fully and somebody tries to complete the challan. At that time system debits the CENVAT account with the amount equal to the excise credit of the unreturned goods)
Now, user wants to close the challans somehow.
My question is, how to close these challans ? If I try to reverse the challan, system tells me to reconcile first. If I try to reconcile, it tells me to reverse first. How to go about it?
Can we just change the status of the challan using ABAP at the tables ? Or is there any better way to do it ? -
hiii...
here we using sap yearfrom 2006 .when i m using j1ifr for display the subcontarcting challan ...then system showing 2006 pending qty...how we clear 57f4 challan?
Thanks
Rekha ShramaHello,
I also facing same problem with 57 F4 challan,
But before reconciling it we need to reverse the open qty towards the vendor then reconcile and then close.
but again the period goes beyond the specified days specified in attributes (180)
Also period not open for last year.. what to do as rekha also facing same problem..
So correct me is that i am correct or wrong
Abhinay Waikar. -
Hi everyone,
Suppose i am transferring material from my plant to Subcontractor place through 57F4 Challan. I have to get back the material within 180 days. If not i have to pay excise from the day one. Is there any transaction so that i can monitor the material lying in the subcontractor place by Day wise???????
Regards
kamalhi
If you want to monitor the Challans use report J1IFR - Challan Listing , & select the options reversal due . this will list you the challans
If you want to monitor within 180 days period.... select the returns dtae from & to Option.... -
Hi experts,
I have a problem with the report for 57f4 challans-J1IFR. In this report it shows "Quantity pending" even when I have reconciled & completed a particular challan. What does this mean?. I have seen the standard Annexure IV, but nowhere this kind of a remark appears. Is there anything else to be done to remove this message?
Regard
nabilHi Expert
I did all the step properly..................GR qty against excise qty. and material document is also correct.......can someone send the step from Subcontracting Po to Subcontracting Challan complete.
regard
nabil -
Dear All ,
If i do not reconsile the 57f4 challan in MM module what impact it will have in account side ? where ? How to see the same ?
RegardsThere will be no impact in accounting. Only thing that the challan will remain open.
The annexure IV register has to be filled acc.
If partial Qty is received then u can keep on reconciling the challan for annexure -4 acc and then close the challan where in the sytem will issue a mesage that no further reconciliation is possible.
you can see the reconciliation status in Tcode - J1IFR -
Hi friends,
I have created the 57F4 challan wrt the 541 E doc...
Then i have to do the MIGo for the good from Subcontractor.... my doubt is how the 57F4 challan related with this GR?
regards,
sathesHi Vipin,
I don't get you....
first i wish tell what i did
i have to issue my special stock to sub-contractor against the SB-PO which is created based on sales order....
i did this through (MB1B; 541 E) transfer posting... 311 E is not for Sub contractor stock transfer posting, it is for location to location....
now i have created 57F4 challan against the document 541 E....
Then i have received the material from Sub contractor and need to do GR. Here my question is how should i link this GR with 57F4 challan?
regards,
Sathes -
Hi Friends,
When i do the "57F4 challan completion", system throws a error "Excise modvat accounts not defined for 57CM transaction and 01 excise group"
How can i fix it?
regards,
sathesHi,
1. Go to SPRO > Logistics - General > Tax on Goods Movements > India > Account Determination > Specify Excise Accounts per Excise Transaction > Here maintain following;
57CM CR Credit CLEAR CENVAT clearing account
57CM DR Debit RG23AT1 RG 23 AT1 Account
57CM DR Debit RG23BED RG 23 BED account
57CM DR Debit RG23ECS RG 23 ECS Account
57CM 01 CR Credit CLEAR CENVAT clearing account
57CM 01 DR Debit RG23AT1 RG 23 AT1 Account
57CM 01 DR Debit RG23BED RG 23 BED account
57CM 01 DR Debit RG23ECS RG 23 ECS Account
2. Go to SPRO > Logistics - General > Tax on Goods Movements > India > Account Determination > Specify G/L Accounts per Excise Transaction > Here maintain GL Accounts for ETT "57CM" with Subtransaction Type "Blank" and "01" both.
Maybe you are looking for
-
How do I change my flash settings? I said I wanted to be prompted about flash wanting to store things on my computer but the prompts are too frequent and annoying!
-
How to hide a control in jdeveloper adf
hi guys, I am using jdeveloper 11 release 02 I would like to implement a control which is displayed based on the of the value of first control. example I have list choice control with options as yes and no if the user select yes the input text appear
-
Automatically Clearing a Form When Document Closes
I'm trying to find a way to automatically clear the information in a form without using a reset button. Our forms are used by many individuals, and this way the form will be cleared of data when the next person goes to use it. These forms will be upl
-
Can't get shared Gmail calendars to work (Exchange)
Long time Android user bought an iPhone 5 last night. Having serious trouble getting shared Google calendars to display. I have my Google account set up as Exchange. That seemed to go through smoothly and my main Google calendar shows up just fine. I
-
Using gigabit connections with 350N
I have been experiencing some problems with my 350N recently. I've upgraded to the latest version when it was released(1.03.2) and it's been ok. Recently I've had a problem getting onto the internet. I've isolated the problem to be the router when I