Customizing existing gantt chart view in project server 2013

Hi,
I want to customize existing gantt chart view in PWA to allow text labelling on task/milestone names,numberic dispaly of percentage complete,scroll to date functionality.
Please let me know how can this be done?
Regards,
Sufiyan

Hi Shaik Sufiyan,
If you know a little java scripting skill, you can definitely do this. You can use IE developer tools to grab the appropriate js file which controls the font.
Task color can be controlled from server settings -> Manage gantt view.
Vikram Daruru - MSFT

Similar Messages

  • Creating custom Category for Risk & Issue in Project Server 2013

    Dear All,
    How to Change Risk & Issue Category default as per business requirement when selecting them through drop down or radio button?
    I can do only Project wise from project site & then setting changes. But i want to customize it for all projects which are getting published in Project Server 2013. So doing manually every time project wise not making sense & consuming time also.
    Kindly help..

    I have created custom template but not getting as demonstrated in  blog
    post from Prasanna  specially
    end part where Risk, Issue n all content can be seen. In My case only simple 3-4 items can be seen apart from risk, issue etc.
    After that i saved this custom template to my
    one of EPT in Project Server 2013. But unable to customize my Risk & Issue Category options for all projects. However, i have gone through that post & unable to understand as described in 2010 & i am using 2013 version.
    Kindly let me know after saving custom Template
    to EPT how to move further to customize these risk & issue categories globally.!!

  • Create a Custom View in Project Server 2010 that is Visible in MS Project

    Hello All,
    We want our PMs to consistently report Physical % Complete, but couldn't find an existing "Status" or "EVM" view.  So, in Project Server 2010, using Server Settings > Look and Feel > Manage Views, I created a customized project
    view using existing fields (no customized fields, if that matters).  The problem is that I cannot find the view when I open MS Project.  Under Manage Views, in the Format View section, I have selected "Gantt Chart (Views)" for the Gantt
    Chart format field.  The view defaulted to "Timesheet" for the Grouping format field.  Under the Security Categories section, I have selected My Projects and My Tasks.  I have not applied a Filter.  Any ideas why I cannot find
    this new custom view in MS Project?  
    Was I supposed to create the new customized view directly in MS Project?  If so, where would I find the steps to do that?  Thank you!
    Julie

    Julie --
    Nice try, my friend.  Your only mistake was trying to create the Microsoft Project view in PWA.  You have to open the Enterprise Global for editing in Microsoft Project, and then create the custom view and table in the Enterprise Global. To
    open the Enterprise Global for editing, click File > Info > Manage Enterprise Global.  When you finish creating the custom view and table, then save, close, and check in the Enterprise Global file, and then exit Microsoft Project completely.
    The next time you or any of your PMs launch Microsoft Project and connect to Project Server, the custom view and table will be visible for every current and future project.  Hope this helps.
    Dale A. Howard [MVP]

  • There is a view named &gantt chart in this project which cannot be overwritten

    Hello,
    I'm using Project Server 2007 SP2. While opening a plan, we are getting the following error
    "There is a view named &gantt chart in this project which cannot be overwritten"
    However, we are not getting the same error for other plan. Is there any changes to be done in the enterprise Global? How to rectify the error? Kindly help.
    Thanks!

    Sandhya987 --
    In addition to Guillaume's excellent answer, you should know that this problem was not caused by the project manager.  The problem was caused solely by the actions of the Project Server administrator.  The Enterprise Global file is reserved for
    ONLY enterprise views, tables, filters, and groups.  For example, there is a default enterprise view named Enterprise Gantt Chart and there is a default enterprise table named Enterprise Entry.  The Project Server administrator should NEVER add local
    views to the Enterprise Global, such as the Gantt Chart, Resource Sheet, etc.
    So, how did the Gantt Chart view end up in the Enterprise Global?  I doubt the Project Server administrator did this intentionally.  Instead, my guess is that he/she applied the regular Gantt Chart view while he/she had the Enterprise Global file
    open for editing.  If the Project Server administrator applies any local view (such as the Gantt Chart view) while he/she has the Enterprise Global file open for editing, Microsoft Project COPIES that view and its default table into the Enterprise Global
    file.  So, if he/she applies the Gantt Chart view while he/she has the Enterprise Global file open, Microsoft Project copies BOTH the Gantt Chart view AND the Entry table into the Enterprise Global file, thus polluting the Enterprise Global file with
    a local view and table.
    To clean up the pollution, keep in mind that your Project Server administrator will need to delete all local view AND all local tables as well.  As the article indicates, as cited by Guillaume, the problem you are facing is a common one, so welcome
    to the club!  :)
    Hope this extra helps.
    Dale A. Howard [MVP]

  • Project Owner not allowed to see Gantt charts in Project Server 2013

    Hi
    A user of Project Server 2013 is unable to see the Gantt chart of his own project. It says in red letters (translated): "You are now allowed to access this page".
    I cannot see any difference between this users account and rights and I have tried as a test user to create a project, but I am unable to reproduce this error.
    Any suggestions?
    Regards
    Jakob

    Hi,
    One of the things I would suggest is to to Inactive the user and save and then Re-active the user and save in order to re-apply user permissions.
    I am assuming the user has the correct permissions etc.
    Hope this helps
    Paul

  • Custom Column for Project Code Number & Search Box to search Content in Project Server 2013

    Hi all,
    I want to add a custom column in Project Center view for showing some Numerical Projects codes like 4523, 5248,8956 like that... Each code will represent Project assigned with that code in Project Server 2013. Also let me now if i can add some search box
    in Project Center page through which i can search Project Code or Project Name. Currently, provided search bar not working in Project Server 2013.
    Need it urgent..Kindly help

    Hi,
    If you want to add this column in a project center view, be careful to choose a project view in the "manage views" views' list. Also it must be a project custom field and not a task field. As Paul said, we assume that the field with the code exists
    and has been previousky created by you.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, MCP |

  • Task custom field and formula custom field don't correspond Project Server 2013

    Hi people, I have an interesting case in Project Server 2013 SP1 CU Apr:
    I have a custom task number field called AM. This field get's filled by a PSI action with actual material costs from an external system.
    I also have a custom task cost formula field that is called AM*. This field is a formula field that has the formula [AM]. And summary tasks use the formula field as well.
    As soon as I create a project, assign costs in the external system and let PSI fill the values within AM I get correct values in AM. But nothing is calculated on AM*. If I edit the project in the browser and publish, check in and revisit the project
    AM* still isn't filled.
    If I open the project in MS Project Pro the calculation comes through nicely, however I do not want to use MS project Pro to see correct data in browser.
    Some tests I have already done:
    I have noticed that when I create a new calculated task field AM2*, this get's calculated correctly on the already existing task.
    I have also noticed that opening the custom field in server settings and just saving the field creates correct values on AM*.
    What is going on? I don't want to save the custom formula field every day... There are 11 custom formula fields in the environment at the moment.

    Hi Gary,
    Thank you for the quick response. Please note that the fieldnames are [AM] and [AM*]. There is a difference in field name due to the astrix. However I did think about the situation and changing one of the field names all together didn't do anything for the
    situation at hand.
    It looks like some kind of refresh thing, because without changing anything in the custom field just saving the field in server settings will turn op good values. However, values already turned up good in Project Professional 2013. And that suggest
    that there is a calculation error on the PWA side wouldn't you say?
    Anyway, thank you for taking time to look into this matter.
    Erik

  • Gantt Chart View not listed in View Selector

    View Selector is missing view of type “Gantt” for List based on list template “171” i.e. “TasksWithTimelineAndHierarchy”
    Missing Gantt View
    Visible in Ribbon
    What we have done to create the Gantt view is as follows
    We are working with remote provisioning pattern to provision the site and required lists
    A Task List is provisioned using CSOM (Managed .Net) via a Provider Hosted App that is hosted as Azure Web Site
    We are creating a view based of type “Gantt”
    Sample ViewXml used for creating the view. Highlighted below is the property we have set for the same
    <View>
    <Title>Tasks_View_GanttChart</Title>
    <DefaultView>false</DefaultView>
    <PersonalView>false</PersonalView>
    <RowLimit>30</RowLimit>
    <Paged>true</Paged>
    <Scope>DefaultValue</Scope>
    <ViewType>Gantt</ViewType>         
    </View>
    Standard View Menu (View Selector) does not show Custom Gantt chart (created via CSOM) in the menu list. Refer screenshot mentioned earlier
    Custom Gantt chart view is available in ribbon menu though
    The same custom Gantt chart is visible in the standard menu if we are in “out of the box Gantt chart View” (Below ‘OOTB Gant chart’ is created from front end using the template ‘Gantt chart view’)
    Sample Code used to create the view
    ViewCreationInformation viewInfo = new ViewCreationInformation()
    Title = listViewTemplate.Title,
            ViewFields = viewFields,
    SetAsDefaultView = isDefaultView,
    PersonalView = isPersonalView,
    Query = query.ToString(),
    RowLimit = rowLimit,
    Paged = paged,
    ViewTypeKind = viewType
    View view = list.Views.Add(viewInfo);
    web.Context.ExecuteQuery();
    Any clue on this behavior? We have the same issue with Calendar View Type as well for the Calendar List.

    I found solution:
    You need modify XsltListViewWebPart tool bar option from one value to another, and then back. That solves that bug in SharePoint.
    public static void FixGanttIssue(SPList list, string ViewName)
    SPSite site = list.ParentWeb.Site;
    SPLimitedWebPartManager AllItemsMan = site.RootWeb.GetFile(list.Views[ViewName].Url).GetLimitedWebPartManager(System.Web.UI.WebControls.WebParts.PersonalizationScope.Shared);
    XsltListViewWebPart wp = (XsltListViewWebPart)AllItemsMan.WebParts[0];
    wp.Toolbar = "Summary Toolbar";
    AllItemsMan.SaveChanges(wp);
    wp.Toolbar = "Full Toolbar";
    AllItemsMan.SaveChanges(wp);

  • View Workspace Document Library on a PDP -- Project Server 2013

    Regards!!
    In Project Server 2010 exists a Solution Starter called "Project Workspace List Viewer". I need the same solution but in Project Server 2013, is this possible?? does somebody has created the same solution??
    Thanks for your help!!

    As per the link mentined below it wont work for 2013.
    http://social.technet.microsoft.com/Forums/projectserver/en-US/bbedf949-acdc-4c75-83fc-e59f84fe77bc/displaying-the-contents-from-project-site-to-project-web-app?forum=projectonline
    kirtesh

  • Timesheet Error with custom Line Classifications in Project Server 2013

    We implemented Project Server 2013 last year and began using timesheets.  We are a billable consulting group.  In order manage our billing, we have created three custom line classifications, "Billable Onsite", "Billable Offsite",
    and "Non-billable".  We do not use "Standard" as a line where time is entered.  We are using SEM.  We have chosen no prepopulation on timesheets.  Our system is updated through the March 2013 update.
    The error we get is presented as "__error Loading" with the title bar of the pop-up reading "Message from webpage".  This occurs when you attempt to add a new line to a timesheet and choose one of the custom line classifications. 
    A confusing aspect to this, while we have prepopulation turned off, the timesheet is populated with "Standard" lines for the tasks that are currently assigned to the user.  We have come up with a workaround that works sometimes but not all the
    time.  When the user receives this error, they move away from the timesheet screen and then return.  They add all of the applicable lines to the timesheet with "Standard" even if they already exist on the timesheet and save.  Then
    they add the lines with the appropriate line classification and the time.  If they receive the "__error loading" error again, then the timesheet can not be corrected.  You must delete the timesheet and recreate.  We have been able
    to recreate the problem in a vanilla install with a custom line classification added.
    Just yesterday, I was able to find a error log entry that may help some of you identify the source:
    General Unhandled Exception in _TimeSheet.GetTimesheetForGridJsonFromViewUid_ Attributes:  System.ArgumentException: Assignment line already exists for assignment uid: d9afeb60-d589-e311-bd64-08edb9dd8afb     at Microsoft.Office.Project.Server.BusinessLayer.Timesheet.VerifyLineIsUnique(Guid
    assignmentUid, Guid taskUid, Guid projectUid, Guid lineClassUid)    
    at Microsoft.Office.Project.Server.BusinessLayer.Timesheet.CreateAssignmentLine(Guid assignmentUid, Guid taskUid, Guid projectUid, Guid lineClassUid, String taskName, String projectName)     at Microsoft.Office.Project.Server.BusinessLayer.TimesheetSEM.CreateAssignmentLine(Guid
    assignmentUid, Guid taskUid, Guid projectUid, Guid lineClassUid, String taskName, String projectName)     at Microsoft.Office.Project.Server.BusinessLayer.Timesheet.AddTimesheetLine(Guid assignmentUid, Guid taskUid, Guid projectUid, Guid
    classUid, ValidationType validationType, Guid lineUid, String taskName, String projectName, String comment)     at Microsoft.Office.Project.Server.BusinessLayer.Timesheet.ImportTimesheetLine(NewTask importedLine)    
    at Microsoft.Office.Project.Server.BusinessLayer.Timesheet.<>c__DisplayClass4c.<AddNewLines>b__49(NewTask line)     at Microsoft.Office.Project.Server.Library.PSUtility.Apply[T](IEnumerable`1 enumerable, Action`1 fn)    
    at Microsoft.Office.Project.Server.BusinessLayer.Timesheet.AddNewLines(IEnumerable`1 newLines)     at Microsoft.Office.Project.Server.BusinessLayer.TimesheetSEM.AddNewLines(IEnumerable`1 newLines)     at Microsoft.Office.Project.Server.BusinessLayer.TimesheetLoaderForGrid.Load()    
    at Microsoft.Office.Project.Server.BusinessLayer.TimeSheet.GetTimesheetForGridJsonFromViewUid(JsGridSerializerArguments gridSerializerArgs, Guid tsUid, Guid viewUid, String changesJson, String viewOptionsJson)     at Microsoft.Office.Project.Server.Wcf.Implementation.PWAImpl.<>c__DisplayClass2f5.<TimeSheetGetTimesheetForGridJsonFromViewUid>b__2f4()    
    at Microsoft.Office.Project.Server.Wcf.Implementation.WcfMethodInvocation.InvokeBusinessObjectMethod(String businessObjectName, String methodName, IEnumerable`1 actions)  . Standard Information: PSI Entry Point:  Project User: i:0#.w|mayberry\nunderwood
    Correlation Id: 91c4ca27-6492-e311-93ff-00155d149902 PWA Site URL: XXX SA Name: Project Services Application PSError: GeneralUnhandledException (42), LogLevelManager Warning-ulsID:0x00101622 has no entities explicitly specified.
    We have not been able to find any similar timesheet issues here or on other boards.  Our users, as you can imagine, are getting increasingly frustrated.  A ny advice?
    Thanks,
    Nate

    More scenario testing today. Tested with both "No Prepopulation" and populate assigned task options! no difference in our instance. We are only updated through March 2013, waiting for IT support. We have previously tried the deactivation/reactivation
    of custom classifications. Tried with and without template, no difference. So the new scenario and findings:
    1. Create a project with 2 tasks, one assigned and one not. Save and publish.
    2. Create a timesheet, do not use an existing timesheet. Here we found, in spite of population option chosen, the timesheet was populated with a Standard line for the assigned task. With no action taken other than creating timesheet, the reporting assignment
    table showed the new entry.
    3. Add an assignment to the other task in the project, publish.
    4. Open the same timesheet period. Now I saw the other task appear on the screen. It did not show in the database. I could not save to make it appear in the database unless I did something else to the screen to make it "dirty". Once I did that,
    I could save and the second Standard line appeared In the database. 
    If I tried to add a custom line class line to the TS when the Standard line was not in the database, I get the error. It doesn't matter if it shows on the screen.
    If it shows on the screen but not in the db, and I attempt to add a non-standard line, it will error, unless I manually add the standard line first.  The user would not know to do this.
    You will not be able to reproduce if you make the assignments and then create the TS. You need to try in reverse order.
    It appears as though there are issues with both the timesheet population options and the code that runs when the TS loads after it's initial creation. I'm wondering why on creation the standard line is created and committed to the db, but on reload with
    new tasks it doesn't' do the same. Also when No Prepopulation is turned on, why my time sheets are always prepopulated.
    Sorry for any typos, working from my ipad keyboard. Thanks for your help!

  • Gantt Chart view disappeard

    HELP! I'm new to using MS Project web and I accidently changed a setting that removed my Gantt chart view. How do I recover it?

    Hi,
    Can you be more explicit? Which setting did you change in your Gantt chart (security setting, filter, columns)? Changing a "setting" of a PWA view should not delete the view.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Can new PWA views be created whereby a filter can be set and associate to the view by default? (Project Server 2013 ONLINE)

    My main question is: Can new PWA views be created whereby a filter for that view can be set, and associate to the view by default? (Project Server 2013 ONLINE)? and can I have a filter set to filter on person logged on to...
    In previous versions of Project Server, when CREATING a PWA view, we were able to apply/ define a filter for that view.  Does not seem like it is the case in Project Server 2013 Online.  And if I remember, we could also use the URL Guid_view_id. 
    Please confirm; and / or tell me how-to.
    What I was hoping to do is the following... Given that our standard that we have adopted for reporting time is 'My Timesheets' (fyi, Single Mode Entry=ON), we have some resources who have others who do it on their behalf via 'My Tasks' (ie., accomplished
    by using the 'Assignment Owner' field, accordingly).  Therefore, when entering time on someone else's behalf within 'My Tasks', we like to present the user that is logged in only the tasks that they are are assigned to update on others' behlaf.
    I know that there is another more elegant approach to doing this which may be to use the Delegation feature. But since we are trying to stick to Sharepoint Security mode for now, this is not an option for the time being.
    Any help appreciated would be greatly appreciated.
    \Spiro Theopoulos PMP, MCITP. Montreal, QC (Canada)

    Hi Spiro,
    1- You still can define in Project Online a filter in the view settings, it is located just above the category setting. Here is a screenshot of the summary project center view:
    2- The view GUID is not anymore in the URL, since the URL triggers an action only on the webpart and not on the whole page. I agree this is annoying since it was great to send a URL with a specific view.
    3- Concerning the access to my timesheet versus my task, I'm not sure to get a full understanding but on a general way, it is much more easy to deal with those situation using categories which you cannot do with the SP permission mode.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • How to set a default date for a custom field of Date type in project server 2010.

    hi,
    can somebody help  me.
    How Can i set the default date for a custom field of date type in project server 2010 ?

    Dear Rohan,
    You can set default value to custom field thru Lookup table. Assign lookup table to custom field and set default value to some lookup value (Note: check the “Choose a value to use as a default when adding new item” checkbox).
    Regards,
    Avinash kumar | Blog:http://avigr8.wordpress.com | If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”.

  • Project Server 2013 Ribbon Customization using a custom action

    Is it possible to customize the ribbon in the Project Center through a Solution? Is the only way to add a button to the Ribbon through an app?
    I am using Project Server 2013 on Prem and every time I deploy a custom action - button to the ribbon in the Project Center the button becomes greyed out/disabled and says "This control is currently disabled." I haven't been able to find any examples
    of how to do this in Project Server 2013 using a solution.
    Here is the custom action, I have tried with and without the EnableScript attribute but nothing seems to work:
    <?xml version="1.0" encoding="utf-8"?>
    <Elements xmlns="http://schemas.microsoft.com/sharepoint/">
    <CustomAction Id="Ribbon.Library.Actions.AddAButton"
    Location="CommandUI.Ribbon">
    <CommandUIExtension>
    <CommandUIDefinitions>
    <CommandUIDefinition
    Location="Ribbon.ContextualTabs.ProjectCenter.Home.Editing.Controls._children">
    <Button
    Id="Ribbon.Library.Share.NewRibbonButton"
    Command="NewRibbonButtonCommand"
    Image16by16="http://s10.postimage.org/lhar0oijp/U16.png"
    Image32by32="http://s17.postimage.org/trf3y2ui3/U32.png"
    LabelText="UniqueId"
    ToolTipTitle="UniqueId Displayer"
    ToolTipDescription="Displays UniqueId for the list item."
    TemplateAlias="o2" />
    </CommandUIDefinition>
    </CommandUIDefinitions>
    <CommandUIHandlers>
    <CommandUIHandler
    EnabledScript="javascript: function ReturnTrue() { return true; } ReturnTrue();"
    Command="NewRibbonButtonCommand"
    CommandAction="javascript:alert('Hello, world');" />
    </CommandUIHandlers>
    </CommandUIExtension>
    </CustomAction>
    </Elements>

    Hello,
    You can add a new button using a SharePoint feature or via an app. If you haven't see the links below already, take a look. These are for 2010 but would be very similar for 2013:
    http://msdn.microsoft.com/en-us/library/office/gg549101(v=office.14).aspx
    http://msdn.microsoft.com/en-us/library/office/ff535984(v=office.14).aspx
    http://blogs.msdn.com/b/project_programmability/archive/2011/04/08/trials-and-tribulations-in-customizing-the-project-center-ribbon.aspx
    http://epmsource.com/2012/01/26/adding-print-capabilities-to-project-detail-pages/
    http://epmsource.com/2011/12/07/hiding-disabling-ribbon-items-in-project-server-part-i/
    http://epmsource.com/2011/12/13/hiding-disabling-ribbon-items-in-project-server-part-ii/
    http://msdn.microsoft.com/en-us/library/office/jj873844(v=office.15).aspx#pj15_StatusingApp_ribbon
    Follow
    some of those example to get those buttons working / hiding then modify your code.
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS

  • "View failed to load" error when I open Resources - Project Server 2013

    Hello,
    I get the following error when I open the Resources Page (I am using Project Server 2013):
    "The view failed to load. Press OK to reload this view with the default settings. Press Cancel to select another view"
    Help please.

    Hi,
    Is your environment up to date with the latest SP/CU?
    HAve you tried selecting another view?
    See those hotfix : 
    http://support.microsoft.com/kb/2760261/en-us
    http://support.microsoft.com/kb/2863881/en-us
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

Maybe you are looking for

  • Mac mini won't auto-sleep (via energy saver)

    I've tried almost everything! SMC reset, PRAM reset, scheduled works fine but the energy saver settings don't. I'm only getting a screen shut but the little lamp in the mini does't fade in and out. help please.

  • Transfer music and photos back to my computer

    I had a virus and resulted in my having to change my hard disk. I did not have back up of my photos or music, which they are safe on my Ipod photo. Now my computer is fully repaired and have downlowded my software for i-pod again, obviusly is empty.

  • Surface Pro 3 PXE Boot Error

    Hi there, I am using MDT 2013 on a WDS 2008 R2 and everytime i tried to image the tablet via PXE boot through the Surface Pro 3 ethernet adapter, i get this error: Wizard Error: A connection to the deployment (my deployment share) could not be made.

  • Webservice from WSDL XML

    Hi All I have a WSDL file in xml format. To create a model in webdynpro, how should i proceed ? Should i select Local File System or URL ? How can i create the URL for this WSDL ? What would be logical destinations ? Please guide me . I am new to all

  • Database transaction report

    There is way that i can find in oracle 10g durning last 24hours how much data insert/delete/update in my database. also how many transactions completed. Thanks