Cut over for WIP in MTO..

Hi Experts,
Client Using SAP from last 13 years and not using the COPA. Now we are going to implement COPA..
•     Client using MTO with valuated stock.
•     To complete one order it will take 45 to 70 days.
Now we are implementing COPA here, based on the requirement we are changing the Activity types and Cost component structure. Because of change on activity types we are going to change Routings of all products (Not using existing activity types all new activity types are using).
Now are going live on first of August, as part of cutover the below activities are we going to do.
1.     Changing work centers
2.     Changing Routings
3.     We have changed CCS totally.
Now we are struck with one thing… How to handle the open production orders?
I have two options in mind with partial answers, please give your suggestions or propose new solution.
Option 1: 
Deleting the all planned orders
Open production orders will be confirmed with old activity types
After taking the standard costing run, again MRP run. All orders will be created with new activity types.
Problem: We need to use two set of activity types for a period of time.
Option2:
Closing all open production orders and sales order and create new orders.
Problem: not possible to close all orders.
Please suggest best solution for this…..
Thanks,
Chandu

Hi Chandu,
We faced similar issue and went for option 1.
With option 2 there are two issues:
- how to close orders which in reality should not be closed
- how to load initial balances to new orders that represent the closed ones
Option 1 is much simpler.
Regards,
Szymon

Similar Messages

  • Cut Over list for CIN implementation

    Hi friends,
    I am on the completion of the CIN implementaion. I am in need of the the CUT over list which has to be in PRD server before Go-Live. Please help me in this regards
    Thanks & regards
    Prabhul

    If you have made changes for existing notifications and orders then you have to create test case for work order create,change,display and complete work order cycle testing from creation to completion.
    Test settlement process for proper costing settling.Work order and notification integration testing.
    New equipment category will require number range to be defined in production system.
    Create,change,display and installation on functional locations are important test case of equipments with new categories.
    Regards,
    Tehsin

  • FM- Cut Over Activities

    Hi,
    I am implementing FM in the mid of the year.
    What all documents should be considered for cut over
    1) Open PO's - If I want them to create commitment items.
    2) Close PO's  - invoicing done, but in case credit memo in relation to those invoices is to be posted.
    3) FI documents - If reversal of those document is done.. then it wld require Fund Center.
    4) Open Sales order
    I was planning to use dummy fund center for this.
    What are the steps to be followed :-
    Like FMCN, FMCT.. FMN3N, FMN4N... so how it is to be done.
    Do I have to assign FM Account assignment for current fiscal year or for all fiscal years in which data exists before FM implementation.
    Please help me.
    Thanks & Regards,
    Jyoti

    Hi Eli,
    There are following methods in BADI.. which should be used in current scenario.
    CHECK_DRULE_BEFORE_SAVE
    CHECK_DRULE_ENTRY
    GET_STRATEGY
    SET_ACTIVITY_ CHECK
    STEP_CHECK_ON_ENTER
    STEP_CHECK_ON_EXIT
    SET_DISPLAY_MODE
    SET_STRATEGY_BUTTONS
    STEP_DRULE_ACTIVITY_CHECK
    Derive
    Besides this in COBL Parameters, I could only find  the parameter Posting date on which basis I can segregate the documents before and after FM Implementation.
    Credit Memo/Reversal of documents where posting date of original document is before FM implementation should be replaced with Dummy Fund Center. Would it be possible with this?? Or is there can be any other criteria.
    Thanks & Regards,
    Jyoti

  • Hi, I need a video editing software for my Power Mac G5 system. Hunted all over for one! Can anyone help me and point me in the right direction. Everything I come across is for intel based systems. Many thanks in advance.

    Hi, I need a video editing software for my Power Mac G5 system. Hunted all over for one! Can anyone help me and point me in the right direction. Everything I come across is for intel based systems. Many thanks in advance.

    I have Final Cut Studio V1 - the PPC/Intel V5/5.1 cross-grade version, which would suit your requirements perfectly. (I have it for sale at present down here).
    If you keep looking, you're sure to find a similar second hand copy in your area, without the need to upgrade your graphics card.
    I'd go for Final Cut Pro as above over any version of Express. FCP has the full version of LiveType - not the truncated version that was released later on.

  • Help reqired in the steps involved in Cut-over Strategy

    We are implementing some sub modules of SAP-HR for a customer. The sub modules implemented are Organizational Management, Personnel Administration, and Recruitment. We have completed the UAT phase successfully. We need to complete the u201CGo Liveu201D phase. I am not clear about the cut-over strategy that we should be adapting. The customer has already implemented SAP-FICO and it is already live. As far as I know, the following activities are involved:
    1.     Move all the Customizing  settings to production
    2.     Move all the Workbench settings (none in our project) to production.
    3.     Upload all the master data and the transaction data to the production using LSMW/BDC.
    Are there any other activities to be completed? I am aware that some activities like creating Users, Authorization etc. are involved, but not sure about the details. Please guide me.
    Also, during SAP-HR configuration, we have created Company Codes, as it is an essential part of enterprise structure, which is set up in SAP-HR. However, Company Codes are actually set up Financial Accounting and since FICO is already live, the configuration for company codes would be already available in production. Now if I move the SAP-HR customizing settings, as it is, to production then it may be wrong, because it may overwrite the company code configuration already available in production. I am a bit confused. Please guide me.
    -Shambhvi

    Dear Shambhvi,
    The purpose of cut-over strategy is to communicate all concerned members to aware and maintain the necessary data for upload for different Phase activities. so, ensure to communicate different Cut off date for different transactions.
    1. Are you using existing company code or different company code?
    2. Ensure to move IMG activities in a sequential way
    3.. Start uploading all master data in Quality Client and check the correctness
    HCM Master data are; Leave Data, Tax Related Data, Department and Position, Execute the Payroll Cycle, Check Gross and Net Payments in Payroll results, Check PF, PT, IT, ESI, LWF, Check Bonus, Gratuity and Superannuation, Execute off cycle Run, Posting to FI, Statutory Forms and Reports
    4. Based on outcome, initiate master data upload in Production client
    Thanks,
    Regards - Muralidhara

  • Moving to Exchange Online from SBS 2003/Exchange 2003 using PST files instead of cut over migration?

    I have a friend who runs a small company with approximately 10 users.  They are currently using Small Business Server 2003 and are using Exchange 2003 to a limited degree.  They are using POP accounts with a hosting company for external email and
    are using Exchange for internal email and calendar sharing.  They have several different versions of Outlook including 2003, 2007, and 2010. Most of the users have two mail accounts configured in Outlook - one Exchange account and one account with a hosting
    company which provides POP mail boxes.  Their MX record currently points to the hosting company not their exchange server.  As far as I know, they do not have any static IP addresses or if they do, they are not using them.
    I do not believe Outlook versions about 2010 will work with Exchange 2003 and their server is getting older and probably needs an upgrade.
    I think they should probably move to Exchange Online since they do not have an IT person on staff.
    I've done some research and it looks like the recommended solution is a cut-over migration from Exchange 2003 but it looks like that would require some changes to the existing SBS 2003 / Exchange 2003 server and I'm not sure that we would be comfortable
    making those changes.
    Would it be possible to sign-up and create the user accounts using Exchange Online and just import the data from the user's PST files?
    I tried doing some research it looks like it is possible but one post mentioned needing to modify the mailbox’s legencyDN or they may not be able to reply to old messages.  How difficult is that?  Can it be done after the messages have been migrated
    to Exchange Online.
    They only have about 10 users so we are looking for the simplest way to move to Exchange Online, not necessarily the fastest or most efficient.
    Any advice would be greatly appreciated.

    Hi,
    Based on your description, I understand that you want to migrate Exchange 2003 Public Folders to Exchange Online. We can get following messages from this article:
    Public Folders in Exchange Online
    You can’t migrate public folders directly from Exchange 2003. If you’re running Exchange 2003 in your organization,
    you must move all public folder databases and replicas to Exchange 2007 SP3 RU10 or later. No public folder replicas can remain on Exchange 2003.
    It seems that can’t migrate on-premise Exchange 2003 public folders to an Office 365.
    àOn the client
    side we are using Exchange 2007
    Did you mean Outlook 2007? Please refer to the following thread and check if can help you.
    Migrating Exchange 2003 Public Folders to
    Wave 15 Office 365
    Hope this helps.
    Best regards,
    Justin Gu

  • PO Cut-over Utility

    Hi Gurus,
    We have requirement to get the POs into SRM which were created in R/3 as a part of Cut-over.
    Client wants all the POS which were created in R/3 with their goods receipt to be showed into SRM and they can perform PO changes in SRM not in R/3 any more.
    Somehow with the standard SAP SRM - R/3 integration through Central Receiving functionality we are able to see Goods Receipts needs to be performed but is there a way we can view /modify POs in SRM which were created in R/3?
    Please advise.
    Thanks
    Ritesh

    Hi Mani,
    Thank you for your quick response. We are using Extended Classic scenario. PO has already been created in R/3 and we wanted to finish remaining PO process (i.e. PO Changes, Remaining Receiving Etc) in SRM which then flow into R/3.
    Is this possible? Can we call you to discuss this further if possible. We are in Los Angeles.
    My Number is 818-777-5058.
    Regards
    Ritesh

  • Using Final Cut Express for video editing without attaching external device

    Hello,
    I am a newbie to Final Cut Express as well as Mac's in general. I am wanting to use Final Cut Express for video editing of files, but without an attached camera. Is there any way to have Final Cut Express startup without having it prompt for an external A/V device? I just want to do some basic editing and use the chroma key feature. Can anyone help?
    Greatly Appreciated,
    Knight2000
    iMAC   Mac OS X (10.4.9)  

    Hi Zak,
    Unfortunately, I've tried that and I get into an issue that was addressed in this posting: http://discussions.apple.com/thread.jspa?threadID=836595&tstart=120 where FCE will show the splash screen and then the program doesn't start. I then have to delete FCE preferences and then I will get the Easy Setup dialog box prompt me again for choosing the external device.
    I am looking for a way to use FCE for video editing of files that I already have on my computer that I created using iClone software and is in .avi, or .mp4 format. I get FCE to work one time without the external device actually being attached, but then when restarting the program I get the dialog box asking for the external device and if it's not there, the program just closes, and to get it to work again, I have to delete the preference files and go through the process all over again which is time consuming especially when this is at work. If FCE is not the right program, can anyone suggest a good video editing program that doesn't require an external device and is as good or better than FCE?
    Thanks again for your help and support,
    Knight2000
    iMAC   Mac OS X (10.4.9)  

  • Uploading the Cost to Network - Activities in Cut over

    Hi All,
    As a part of Cut over activities, Is that possible to upload actual cost to Network - activities in Producion environment?
    As a best practice, till now in my projects, I have uploaded the Intial cost to WBS only.
    Regards
    Prabu K

    Hi Abdul,
    While using KAFD, we can post legacy or historical actual cost.
    The most important this is that, define one WBS element in your project structure and name it as Historical WBS element which will receive all your legacy costs. By doing so, we are posting all our legacy costs to One WBS element only.
    Here what you have to do is difine the Historical cost elements which are used only for these migrated projects and not for regular opeative structures.
    Input the current period - current period always be in which period project is being migrated.
    then input the Year - in our case we have not defined multiple years but as a lumpsum amount in current year (the year project is migrated)  that will stay as historical cost. You will not see any break up of historical costs in SAP but you can see break up of actual coss in legacy system.
    Hope this clarifies and let me know if you need any further inputs.
    Regards,
    PSR
    Edited by: PSR on Oct 10, 2011 4:09 PM
    Edited by: PSR on Oct 10, 2011 4:29 PM

  • Quality Management - Cut Over

    All
    We are shutting down our 4.7 and moving on to ECC 6.0. Any recommendations on how to handle
    - Open Inspection Lots
    - Stock in Quality
    Regards
    TOM

    Identify the materials/batches in QI just prior to cut-over.
    Use QA08 to turn off all inspection types or ideally don't set up any inspection types at all until after this process.
    Load the QI stock to QI with your normal load programs and use a 523 movement type.  Or load with a 561 and then use 322 to move to QI.
    Make sure in config, for each plant, in the QM plant settings, on the "Insp. lot creation" tab you have defined an inspection type for "InspTypeForInspStock".  Most people use either an 08 or 09 for this.  I usually create a variant of the 04 or 08 for this. (04LOAD or 08INIT).  Something that when you look at the QA32 list with inspection types, you know right away this was a lot from the initial load.
    Now use QA08 to add and activate your inspection types for all your applicable materials. 
    Those materials with stock in QI should have an inspection lot created.  It should be the same inspection type you defined in the QM plant config above.
    You can now record results and make UD's on these.
    Craig

  • Cut over strategy

    hiii pl some one can explain about regarding  CUTOVER STRATEGY
    regarding enter work flow in implementation

    Hi,
    Cut Over Strategy is the plan of Migrating the Actual Data into SAP System.
    sending all the open items in the Legacy will be sent to SAP According to Some Preprepared plan carefully in order to avoid errors.
    All these plan of Action are Called Cut Over Strategy.
    I think, This is useful to you to understand
    for more Information See www.help.sap.com
    Thanks,
    Purnachandra Rm

  • Plano de Cut over

    Pessoal,
    Estou precisando criar um plano de Cut Over, gostaria de ouvir algumas opniões.
    O que é melhor e porque...
    E mehor fechar as Ordens TODAS ou não ?
    Em caso de projetos como vocês trataram ?
    Em caso de Ordem com valor antigo, como vocês resolveram ?
    Alguém teria uma descrição de plano de Cut Over para mostrar e me ajudar.
    Grata desde já pela ajuda

    Julio,
    Segue abaixo o plano de Cut Over que tenho usado desde 2009 quando coloquei aqui a pergunta.
    Graças a deus muitos projetos se passaram e deu tudo certo.
    Não consegui anexar o XLS, então copie e colei a planilha
    Tarefa nº
    Tarefa
    Preparação do sistema produtivo NF-E
    PREDECESSORES
    1
    Cadastrar Impressoras
    2
    Atribuir Usuários a J1BNFE
    3
    Atribuir Usuários ao Monitor GRC
    4
    Atribuir  Conecção entre R/3 e e GRC
    5
    Atribuir Assinatura XML ao GRC
    6
    Preparar plano de bloqueio Corporativo de Transação VA01/VA02/VL01N/VL02N/VF01/VF02/J1B1N/J1B2N/ME21/ME27/Z*
    7
    Confimar último Nota Fiscal emitida em cada local de negócio
    CUT OVER
    8
    Transporte de Request ABAP - NOTAS SAP MP135 e NF-E
    9
    Transporte de Request de Customizing FI/MM/SD MP135
    10
    Transporte de Request de Customizing FI/MM/SD NF-E
    11
    Trannsporte de Request ABAP - Programas Z
    12
    Transport de Request GRC PI
    13
    Preparar mandate de PRD para entradas Manuais (Range de Numeração/ VK11/J1BG, MM?)
    14
    Atribuir  a Coneção (RFC) do R/3 com GRC PRD - Atualização do caminho via request
    15
    Revisar Perfil de Acesso R/3 e GRC
    16
    Atribuir Imporessora (J1BG)
    17
    Atribuir manualmente - Nova Range de Numeração NF-E aos locais de negócio
    18
    Atribuir  manualmente Saída de Nf-E ao Formulário
    PONTOS DE ATENÇÃO/ATIVIDADES MANUAIS
    19
    Trocar o caminho da RFC do R/3 para apontar para Produção SEFAZ e nào mais Homologação
    20
    Alterar o Range de Numeração para iniciar com numeral após a ultima emissão de NF-E
    21
    Criar a VK11 para Mp135
    22
    Retirar a TAG de Homologação da BADI
    23
    Cadastrar Impressoras
    Boa sorte
    Luanna Priscilla

  • Is it possible to create a SHORT CUT key for a Workspace in CS 5.5 ?

    Is it possible to create a SHORT CUT key for a Workspace using In Design CS 5.5 ?

    Edit Menu > Keyboard Shortcuts > Product Area: Window Menu > Workspace Load 1st, 2nd, 3rd, etc. Create a new set and assign a shortcut

  • To set the short cut key for the menu when using CommandDesign pattern

    Hi All
    I have a menu File which has two menu items Load and save.
    Here for implementing the actionperformed iam using the command design pattern.
    Now iam not able to set the short cut key for the menu item......
    Please help me..............
    Thanks
    Arch

    The Java Tutorials: [How to Use Menus|http://java.sun.com/docs/books/tutorial/uiswing/components/menu.html]
    db

  • Create custom short cut key for colon

    I have a Macbook Pro 10.8.4 Lion, but when I upgraded from Mountain Lion, my keyboard went a little wacky. I could of spilled something withnot noticing, but honestly I think I would remember. The help support had no ideas to fix the issues despite our attempts.
    So is there a way to create a custom short cut for a key not in a menu? I need to create a short cut key for the colon and semi colon lol.
    Thanks!

    Edit Menu > Keyboard Shortcuts > Product Area: Window Menu > Workspace Load 1st, 2nd, 3rd, etc. Create a new set and assign a shortcut

Maybe you are looking for

  • Need help setting up at local testing server

    I have Coldfusion 8 installed on my hard drive and DWCS3 installed on an external hard drive hooked up to computer. I have set up a DSN in Coldfusion I can't however get setup the testing server so that I can test my site it is asking for a HTTP addr

  • How to Handle pop up error message in BDC

    Hi Friends, Right now I am working with CA12 transaction. In this transaction for each group I need to update the details of the operations( lablour and overhead value). after updating the details, When I click on save I get a error pop up message sa

  • Does BusinessObjects 5.1 can run on an Oracle database 10g?

    Hello, Can anyone tell me if BusinessObjects 5.1.6 can run on an Oracle database 10g? Thanks in advance for your answer Thierry

  • What is a factory method

    Can anyone tell me wat exactly is a factory method??

  • Sales Order data on Label

    Dear Team, I am working on GLM whereas I wanted to print the Label via CBGL_MP01 for 'Delivery' Scenario. In that, now I wanted to fetch the Sales Order Number. Since there is NO standard Report symbol for Sales Order, need to go for FM development.