DAC Configuration Tags - Include Tasks option

Hi all,
Environment
Oracle BI Applications 7.9.6 (Financial & Project Analytics)
Oracle E-Business Suite 11.5.10
Question
I am configuring the DAC (10.1.3.4.1) for our install and I want to enable Multiple Calendar Support and Enable Project Dimensions in the DAC. After the install several of the Subject Areas already include one or both of these Configuration Tags. My question is whether the Include Taks checkbox is required to be checked. If so, then I have a problem as this checkbox is not active (unable to be checked). Can someone please explain to me the reason behind this?
As a sub-question in relation to the Integration between Projects and Financial Analytics. From the Oracle documentation Oracle Business Intelligence Applications
Configuration Guide for Informatica PowerCenter Users Version 7.9.6 (E14216-01) section 5.3.2.10 How to Enable Project Analytics Integration with Financial Subject Areas states that:
You can configure the following Oracle Financial Analytics for EBS subject areas to use Project Analytics for EBS tables:
    •  Financials - Budget
    •  Financials - Payables
    •  Financials - Receivables
    •  Financials - Cost of Goods Sold
    •  Financials - General Ledger
    •  Financials - RevenueIn my install all but two of these Subject Areas (Financials - Budget and Financials - General Ledger) already have the Enable Project Dimensions Configuration Tag added (albiet set at Inactive). I'm assuming that all the listed Financials Subject Areas require this Configuration Tag to exist and not have the Inactive checkbox checked.
Thanks for your time.
Kind Regards,
Gary.

Bounce!

Similar Messages

  • How can I include installer options?

    Hi to everyone.
    I'm trying to include an option on the  installer of my application. I want to include a com port selection option (such as the selection of the installer directory for example)  when the installer runs, so the user only have to give this information one time an the port is configured when the application runs.
    Is this possible with labview?. I'm using LV 8.6.
    Thanks in advance 
    Solved!
    Go to Solution.

    Hi Pelicar,
    Thanks for your reply - sorry for any confusion. 
    There is an advanced installer setting Hardware Configuration—Includes
    the hardware configuration information configured in Measurement &
    Automation Explorer in the installer. Click the Configure button to launch the Measurement & Automation Explorer Export Wizard to create a hardware configuration file. This allows you to move your hardware configuratin on the deveopment machine onto the deployment machine. 
    For more information on MAX configuration files please see this Knowledgebase article:
    MAX Does Not Save or Apply VISA Port Settings
    http://digital.ni.com/public.nsf/allkb/8EBAEC8A57BB48BE862574F90072D3DD?OpenDocument
    Hope this helps, 
    Kind Regards
    James Hillman
    Applications Engineer 2008 to 2009 National Instruments UK & Ireland
    Loughborough University UK - 2006 to 2011
    Remember Kudos those who help!

  • Project Server 2013: Remove Task Option Causing Orphaned Timesheet Lines

    We are experiencing a major issue with the "Remove Task" option in PS2013 that is leading to orphaned timesheet lines with no related assignment.  This can result in actuals in a project with no corresponding timesheet entry.  We are
    using SEM.
    The scenario to reproduce the issue:
    PM - Assign the task and publish
    Resource - Enter time against the task and submit
    Resource - Recall the timesheet (the task update approval is still in the PM’s queue)
    Resource - Remove the Task from the timesheet using "Remove Task" button or right-click
    PM - Approve the task update and publish, only the task update appears in the PM’s queue, not the delete assignment request
    PM – Approve assignment deletion
    PM – Go into schedule and actuals show against a task with no assignment.
    When you return to the timesheet and recall it, the fields are all disabled.  If you click on the task, you will receive an error message as the assignment no longer exists.  The workaround is to have the PM reassign the task to the user, publish,
    open the timesheet, readd the task and hours, remove the orphaned line, and resubmit.
    As many others have reported, the "Remove Task" option is very dangerous.  We are exploring the recommendation to configure the screen to remove the button, but I am curious is anybody has experience with modifying the right-click that allows
    the same "Remove Task" operation.
    Opinion:  This feature is awful and extremely unclear.  To the lay user, it reads like it will simply remove the line from the timesheet.  There is no language or warning to the user about the action they are actually taking.
    Thanks,
    Nate

    Hi Nate,
    In PS2010 implantation I already used to remove the "remove task" option and others from the timesheet ribbon.
    I guess you already find this documentation but just in case:
    http://msdn.microsoft.com/en-us/library/office/gg549101(v=office.14).aspx
    http://epmsource.com/2011/12/07/hiding-disabling-ribbon-items-in-project-server-part-i/
    Concerning removing the "remove task" from the right-click context menu, since I'm not a developer and I didn't yet faced this concern, I'll let my colleagues from this forum go further.
    Hope this helps.
    Guillaume Rouyre - MBA, MCP, MCTS

  • Windows 7 upgrade: discs will include the option for a 32 to 64-bit upgrade via a clean install?

    I would like to know whether the Lenovo Windows 7 upgrade discs will include the option for a 32 to 64-bit upgrade via a clean install?  I called Mentor today and was told the answer is no, but I was hoping someone here could tell me differently.
    If "no" is truly the answer, I would like to voice my complaint: The upgrade discs from Microsoft (i.e. the retail upgrade discs) include both the 32 and 64-bit versions, so I don't completely understand why Lenovo's upgrade program doesn't offer the same thing.  I purchased my T500 in August, and back then Vista Ultimate 64 was not offered, so I chose Vista Ultimate 32 thinking that I could later upgrade to Windows 7 Ultimate 64.  This assumption was based off of the info. on Microsoft's website indicating that all upgrades would contain the 32 and 64-bit versions.  I even customized my computer with 4 gigs of RAM thinking that I could take advantage of the extra gig once I installed Windows 7 64. 
    I don't understand what Lenovo or Mentor Media have to gain by restricting a 32 to 64-bit install.  I voiced this opinion to Mentor Media over the phone, who responded by saying that I should be happy since I am receiving a "free" upgrade.  I don't think this is an accurate assessment for two reasons: (1) I had to pay $17.03 for shipping, and I still haven't received the upgrade and (2) The total cost of my computer was almost $3,000, and the purchase was made a mere few weeks before Windows 7 was released.  $3,000 is a lot of money.  I waited for the details of the Windows 7 Upgrade Program to be announced BEFORE purchasing my machine.  When I finally bought my computer I accounted Windows 7 into the price I was paying.  In addition, when I bought this computer I did so expecting good customer service as a given.  Not providing a 64-bit upgrade without a rational explanation as to why does not qualify as appropriate customer service.
    As most of you know, 4 gigs of RAM is useless with a 32-bit OS.  Also, NOW Lenovo is building new T500s with the option of having Windows 7 Ultimate 64 (why wasn't Vista Ultimate 64 offered when I bought my computer???).  And the price for choosing Windows 7 Ultimate 32 is EQUAL to the price for choosing Windows 7 Ultimate 64, which proves that there is no cost difference.  I just want to know what Lenovo has to gain by denying customers a 64-bit upgrade?  There would really be no additional cost since as I mentioned before, Microsoft's retail upgrade includes the 32 and 64-bit OS on one disc.  If anything I would think that it's costing Lenovo money to strip the 64-bit install from the upgrade discs.
    Can anyone please address my problems?  Do you think there is anyone at Lenovo I could contact to voice my opinions?  I have been a loyal Thinkpad customer for over 5 years now, and I expect better from Lenovo.  Thank you for reading!
    moderator note: core question add to title, as stated in the forum rules and it will help others too answer your questions.

    Daventry wrote:
    Is there any way to request a 64-bit OEM?  Why should Lenovo care whether I want a 32-bit or 64-bit as long as it's the same edition (Ultimate edition)?
    if your system shipped with a 32-bit version of vista then you will be sent 32-bit windows 7 upgrade media.   the reason for this is two-fold.
    first, because this is upgrade media, it's impossible to install a 64-bit version of windows over a 32-bit version.   doing so would require a clean installation and upgrade media simply won't allow this.   this is the case with retail media, too.   if you had 32-bit vista installed and wanted to upgrade it to 64-bit using retail media, you'd have to wipe your system or set up a dual-boot.
    second, the COA (certificate of authenticity) on the bottom of your system is for vista.   because of this, your new license is of an upgrade from vista to 7.   this is how microsoft licenses it and it is their policy, not lenovo's.   microsoft's policy with OEMs is that you must install vista first, then upgrade to 7 (unless, of course, you purchased your system native with 7 on or after the 22nd).   since your original lenovo preload is of a 32-bit OS, the issue becomes circular and you'll have to refer again to the first reason.
    i understand your frustration and wish this stuff were made easier for everyone.   it's repetative reading post after post of people with 4GB installed who don't understand the limitations of a 32-bit environment.   i wish both manufacturers and users switched to 64-bit OSes sooner.   the same thing happened when the industry went from 16-bit windows 3.11 to 32-bit windows NT4/95 and limitations went from 16KB all the way up to 4GB (which, in 1995, no one thought we'd ever exceed).   the difference is that people were complaining on BBSes over 14.4k modems instead of on GUI-based forums using broadband connections.   times sure have changed.
    ThinkStation C20
    ThinkPad X1C · X220 · X60T · s30 · 600

  • How to include the option for people to download adobe reader in an email campaign?

    We need to attach some terms & conditions as a PDF in our mails (sending to a few thousand people), but would like to include an option to download adobe reader to read the PDF if they haven't already got one.
    Is this a simple 'link to download page' or is there a widget/code or something that already exists for this? Just to make it quick & simple for email readers
    Many thanks in advance!
    Kathleen

    Icons and web logo guidelines | Adobe

  • BPM process and manage task  option should avaible at Portal

    Hi Expert,
    Assigned User will see BPM  process and manage task option in  directly in portal not required to login as NWA.
    Please help me on this.
    Thanks,
    Padmindra

    Hi Mithileshwar,
    Start BPM Process Trigger - Read timed out
    Regards,
    V Srinivasan

  • How to remove Include/Exclude option on variable screen

    Hi,
    How to remove the include/exclude option in the variable screen for the variable of type selection option.
    Regards,
    Suresh.

    Hi Pradeep,
    You mean in the Query Designer.I tried to create a new variable There is nothing like select appropriate variable.
    Be more specific.Thanks.
    Regards,
    Suresh

  • Configuration of project stock option

    Dear All,according to the standard  application and SAP help,when we create a project,we can make an option on the control tap with three choices,non-stock,non-valuated stock and valuated stock.But after we save the project,we can never make any changes among these three(turn gray).
    What configuration should I make if I wanna make the non-valuated stock option hidden and the other two can be selected after saving(just like the fields).

    Hi Kishore,
    Concerning the issue on the statment that you made on configuration of the stock option whereby you have mentioned that after a project with profile of non-value stock option had been created, there is no turning back on choosing the another stock option. May I know what is the reason behind? i.e why the system does not allow a change?
    Thank you very much.
    Patrick

  • How to include zoom option for images and video in adobe captivate5?

    I am developing an elearning software with captivate 5 which has images and video.
    I want to include an option to be able to zoom the images and video if clicked on the particular area.
    It should zoom any part of the image when clicked on it during run time and go back to original size when clicked again.
    How can I do this?

    1. I try with two images: The thumbnail y the Big Image Zoom image Detail.
    2. I Use Dinamic Images
    3. check this tip

  • Configuration planning Strategy task bwtn PP/SD Consultant

    Hello Consultant
    As we known, planning strategy is incdluing two elements( requirements type for PIR; Requirement type for customer requirement) path:SPRO>Production>Production Planning>Demand Management>Planned Independent Requirements>Planning Strategy>Define Strategy)
    In you experienced project, if PP consultant was in charge of config "Reqmts type for indep.reqmts" and SD Consultant shoud be in charge of Config"Reqmt type of customer reqmt "?
    or PP Consultant should be responsibled for two parts configuration? including(Reqmts type for indep.reqmts/Reqmt type of customer reqmt).
    Please advice.
    Benny
    Edited by: benny zeng on May 20, 2010 10:26 AM

    Dear ,
    PP consultant is the in charge of Planning Strategy -Define Planning Strategy (SPRO) based on the Requirement Type(OVZH) and Requirement Class(OVZG)  for for sales Item categoery  under basic function of SD module .
    Now , most of the parametrs which have activated or relevent from sales side (Req.Transfer ,Account Assingment Categoery , Customer requirement type , Order Type etc) are configured in OVZG by SD consutnat  and same has been assinged to requirement type in ovzg .
    Once you did this , PP consultant will decide on the Planning Strategy group in SPRO-MRP-PIR and check wether respective parametrs are flowed in that strategy  .
    So i would rather say , its a combine effort based on the clinet requirement .
    Regards
    JH

  • Help with "DAC Configure for Quadrature Mode.vi" in "ni5640R Frequency Translation" Example

    Hi there:
    I am also using the the NI PCI-5640R and I've been "studying" the
    program: "Frequency Translation", my intention is to modify it and
    produce a  closed-loop between I and O. 
    I am also interested in transferring what i am reading through the
    input port, directly to the output port but filtered AND with a
    phase-shift (final Objective: Q-Control). 
    I need to visualize the signal in the HOST, so I need both FIFOS (DMA
    FIFO and  Local FIFO), and the "Quadrature Mode DAC Configure"
    I would like to know:
    1. How can I directly transfer the data acquired through the ADC port
    into the DAC?  (it is unclear due to the Event structure in the
    "Frequency Translation" example)
    2.
    How can I configure the "Quadrature Mode DAC Configure.vi" for it to
    bandpass-filter the signal comming from the ADC at a given frequency
    and BW, specified by the user in the HOST? I have read that it is possible to filter a signal comming to the DAC using DUCs (Digital Upconverters) Does anyone has more info about this topic?
    3. Is it possible to
    configure the "Quadrature Mode DAC Configure.vi" to produce a
    phase-shifted signal (phase shift also specified by user in the host)
    I've
    been working for almost 2 months trying to program the 5640R, doing
    examples, and modifying them.  After playing with different examples
    I've come up to the conclusion that the "Frequency Translation" example
    is the one that best-suites my application.  My problem now is that I
    AM LOST because i need more information regarding the configuration
    parameters of ALL the different VI's inside the NI-5640R VI Tree  to
    exploit them correctly, specially the "Quadrature Mode DAC
    Configure.vi".
    Can anyone please help me?
    Cheers...Antonio

    Hello again:
    Jerry:
    1. I referred to the Event structure, but in the HOST, but now, with your commentary and Philippe's explanation i've undestood better the concept.
    2. Regarding the filtering, I read the datasheet of the AD6654 (DAC from "Analog Devices" which is part of the n5640r) and in pages 36 and 37, it explains with an example, the possibility of designing a Bandpass CIC Filter by changing the interpolation (or decimation) factor of the DUC (or DDC).  The filter can't be fully customized (the rejection and passband are limited to an "Alias rejection Table" in page 36), but it could fit the application to filter certain frequencies.
    I also tryed what you guys suggested, meaning: I designed a simple digital bandpass butterworth IIR filter in the FPGA target inside a 3rd SCTL with a faster clock (i.e. "Top level timing source") and using a 2nd Local FIFO.  The filter was done with FPGA discrete delays (z^-n) departing from a "differences equation" [y(n) = x(n-1)+x(n)+0.9996858*y(n-1)].  But I have problems with the 0.99... constant which is always rounded to 1 (check the pic).  I changed the variable's type and digits of precision, but it still rounds up to 1 Any suggestions?
    3. I was thinking as well of shifting the phase (as Jerry said) by configurating the NCO in the DAC.  Again, more information is given in AD6654's datasheet  (page 35).  I will quote the info:
    "The phase offset register can be written with a value that is added as an offset to the phase accumulator of the NCO.  This 16 bit register is interpreted as 16-bit unregistered integer.  A 0x0000 in this register corresponds to a 0 radian offset and a 0xFFF corresponds to an offset of 2pi*(1 -  1/2^16) radians.  This register allows multiple NCOs (multiple channels) to be sinchronized to produce complex sinusoids with a known steady phase difference:"
    Any ideas of how to program this register inside the "ni5640r ADC Configure NCO" to have a fixed phase offset of 90º?
    Thanx in advance for your replies
    'till the next post...Antonio
    Attachments:
    Digital IIR.JPG ‏122 KB

  • Extra pair of HTML /HTML tag included at web source

    I have created a report of JSP format. The charset of the file was UTF-8 and the report contained some Chinese words. When I previewed the file using Reports Developer, it displayed the Chinese words correctly. Then I deployed the report to Oracle AS server. However, when I browsed the report from web browser using "rwservlet?report=abc.jsp&userid=system/manager@ccc&destype=cache&desformat=html" command, it could not display the Chinese words correctly because the charset encoding is set to ISO-8859 (English).
    I have already set the report to use charset UTF-8. Then I opened the file in the "cache" directory at web browser. It displayed the Chinese words correctly and the default encoding was UTF-8. The next step was viewing the source code of the content displayed using "rwservlet" command. I finally found that there was an extra pair of <HTML></HTML> tag at the beginning of source code. The source code therefore looks like:
    <HTML>
    <Head>
    <base href="http://dev.abc.com:7777/reports/rwservlet/getfile/rep_dev/1/06587041.htm">
    </Head>
    </HTML>
    <HTML>
    <Head>
    <meta http-equiv="content-type" content="text/html; charset=utf-8">
    </Head>
    <Body>
    </Body>
    </HTML>
    There are two pairs of <HTML></HTML> tag!
    The content of the pair of tag include a reference to the corresponding file at the "cache" directory, but it did not specific any charset encoding. When I manually changed the encoding from ISO-8859 to UTF-8, the Chinese words were displayed correctly.
    Can someone tell me why there is an extra pair of <HTML></HTML> tag at the beginning of source code? Where can I set the charset encoding of the extra pair of tag?
    Actually I face the same problem when sending the output to printer by setting the "destype" to printer. The Chinese words are not printed correctly.
    Thank you very much for any help and idea.
    - Man Ip

    Sorry that there is some problem on the displayed source code.
    The 3rd line should be as follow:
    base href="http://dev.abc.com:7777/reports/rwservlet/getfile/rep_dev/1/06587041.htm"
    - Man Ip

  • Robocopy - Include directories (as opposed to Include files) option?

    Hello,
    I would like to copy only a given set of directories using robocopy. How can this be achieved? Is there an option that I am missing?
    Details of my requirement:
    - I already use robocopy to sync a large number of binary files. I use robocopy obviously because I want to copy only the files that are changed since the last copy. (something like rsync)
    - Almost always I can run the robocopy on the top level directory. But once in a while (very infrequently), I need to copy a few files (~100 files) from 3-4 directories. I do not want to copy anything else. Again, not all files within these 3-4 directories have changed. But I know that the files that have changed are within these directories. So again using robocopy will be ideal because it will detect and copy only the changed files.
    From what I see so far, there is no way to provide just these directory names to robocopy and copy the appropriate files. I will have to loop through these directories and then robocopy individual files. Is that correct? Or is there an option in robocopy that can achieve this?
    Many thanks,
    -Hari

    Hello Bill,
    Thank you very much for the quick response.
    Yes, that is an option. I am trying to avoid making wholesale changes to the script that I currently have and that is why I was desperately looking for a robocopy option that takes files/dirs to include. I guess I should give more details to explain why it will require wholesale changes.
    We already have a script that goes through various processing and does something like this at the end:
    robocopy MySourceDir MyDestDir /E /XD <...>
    Here MySourceDir and MyDestDir are top level directories. So far the script's work (before it executes robocopy) has been to determine the MySourceDir and MyDestDir (where to push to, which branch should the files come from etc..) and also what files to exclude.
    The requirement that I mentioned above (need to copy certain directories only) came in now. And an additional point that I missed is that along with the certain number of directories, a few top level files can make it to the list as well.
    This essentially means that I will need to
    (a) write a section to first identify if its a file or a directory
    (b) then create an appropriate robocopy command, depending on if its a file or a directory
    (c) in addition, the file in question can be there in any number of sub-directories. For example, I might have a hari.xml file at the top level + a couple of sub-directories. But I just want the hari.xml at the top to go out. Since the file syntax of robocopy does not take the path (AFAIK), it gets a bit more complicated.
    In order to avoid all these, I was looking for an option where robocopy will just take an include pattern of sorts (just like rsync's --include or --include-file options).
    It looks like I will have to rework the script quite a bit to get this done. But just wanted to check in here in this forum to see if there is a better solution out there.
    thanks,
    -Hari

  • [svn:bz-trunk] 10057: Update the sample configuration to include a comment to warn people not to use debug level logging in production .

    Revision: 10057
    Author:   [email protected]
    Date:     2009-09-08 10:58:36 -0700 (Tue, 08 Sep 2009)
    Log Message:
    Update the sample configuration to include a comment to warn people not to use debug level logging in production.
    Modified Paths:
        blazeds/trunk/resources/config/services-config.xml

    Remember that Arch Arm is a different distribution, but we try to bend the rules and provide limited support for them.  This may or may not be unique to Arch Arm, so you might try asking on their forums as well.

  • [1.1.1.25.14] Clear Filter removes "Include Synonyms" option

    I have happily been using the new "Include Synonyms" option in the Table and View nodes and it has been working great.
    That was until I used the Clear Filter option rather than manually deleting a number of filter criteria (which can be a pain, because the cursor doesn't stay in the criteria list after deleting a critiera).
    Now my "Include Synonyms" option has disappeared from the node on which I cleared the filter and I can no longer filter on synonym based objects (I did have Include Synonyms switched off when I cleared the filter).

    Yup, it's a bug.
    Not a solution, but work around for now - A restart of SQL Dev will return the synonym checkbox.
    I tend to have single % and synonym checkbox checked as filter on my tables.
    Sue

Maybe you are looking for