hi pp gurus
can anyone guide me
I want production report shift wise ,how
much production carried out
i hav three shift
and howmuch rejection is carried out against production order
Regards
Dev

HI
you can use t: code : COOIS : order infomation system
give you all order number and qty
with reference to date and time
Please reward points
Sunil

Similar Messages

  • Error (Rejection) Report (QM Module)on Daily Basis

    Dear All,
    I have been assigned the development of a Daily Defects (Rejection) Report for the QM module. A similar SAP standard report MCXX (RMCQ0900) is available but that gives the result on monthly basis while our requirement is of daily basis.
    I had a look on the code of this standard report(RMCQ0900)
    and found that the code for 'daily report' has also been written with in it. In the selection-screen also select-option for 'daily report' is present and enabled but there it shows some incosistencies. I tried to remove these inconsistencies by copying the standard report to a ZReport and edit the same but I couldn't.
    Can anyone help me on this?
    regards,
    Alok.
    Can anyone provide the logic for the same.
    Thanx in advance.
    Alok.

    Hi,
    Please check the report ME80FN. or any standard report ME2L/ME2M etc will give the details.If not check the table EKBE.
    Regards,

  • Daily Product Cost

    Hi,
    Is it possible to get a daily product cost. Can any one explain me the implications for getting daily product cost from PP point of view and also CO point of view. Whether Repetitive manufacturing solves this issue? Please reply immediately.
    Regards
    Prashanth

    Hi Ashok,
    I am asking is it possible to get daily product cost report. What are implications or difficulties in getting daily product cost report from CO point of view. From CO point of view we need to settle the production orders daily where settlemet is a monthly activity and also the allocations. I request you to tell me what are implications in doing the daily product costing to arrive at daily product cost report.
    Regards
    Prashanth

  • Delay time data at Daily Production Report

    Hi all
    We hereby crated the Daily Production report which has the delay deatils of all depts. The delay details we are using with notifications. The problem is users required the shift wise delay according to the production.
    SAP std we couldnt keep the shift at notifications level (exit also helps but time couldnt assign). The Shift A is 7 am-3 pm, B- 3 pm to 11 pm. C- 11pm-7 am. The malfunaction start time some time may exceed from the A to B shift. But delay calculation hours is only one. With out going for hard coded how could assign the delay hours shift wise.
    At notification level is Capacity requirements will appear as per shift ?
    please suggest

    Hi,
    1.Select a capacity category for which the actual capacity requirements are to be calculated on the Capacities tab page in the resource.
    2.Choose ActCapReqmnts.
    3.The Settings for Determining the Actual Capacity Requirements dialog box appears.
    4.Set the Calc. actual cap. reqmts indicator.
    5.If the actual capacity requirements are to be calculated from activities:
    Enter one activity for each actual capacity requirement in Actual capacity requirements from activities. Determine the standard value parameter that identifies the corresponding activity.
    regards,
    Venkatesan Anandan

  • To prepare daily production report in grade wise

    Hi,
    Need your help regarding grade wise Finish Goods. My finish goods product code is in database 1601001. When bulk receipt from production how to separate grade wise quantity.
    Example:
    My production order quantity is 100000 pcs and receipt from production in stock is 95000 pcs. Now in 95000 pcs, 75000 are grade u201CAu201D quality and rest of 20000 pcs are u201CBu201D quality.
    There is any option that I can prepare daily production report in grade wise.
    Regards,
    Mizan

    Hi.....
    Go to Item master data whihc you want to maintain Gradewise.
    In general tab you find Serial or Batch Number under which just select Batch and select on every transaction......
    This will hjelp you to manage your inventory by Batches which you consider as grade......
    Regards,
    Rahul

  • Daily Production Report In coois

    Dear All
    When we r checking in Coois report for production entry Of SFG.FG--it will give us the Total qty,
    exactly we want that suppose one order qty is 15000 and i have put a production order of that Qty.  But according to Production Its going On With 500 or 600 per day produce.  then how can we see the production report of particular production confirmed qty and delivered qty  500 on which day . or we can see the Daily production report of Particular FG & SFG.
    Rgds
    Pankaj Agarwal

    Dear Pankaj,
    One way of addressing this issue is go to MB51, movement type 101 & 102 7 other relevant criteria.
    Plant n storage location.
    Execute>CtrlShftF12, you will see the list of material recvd. in the storage loc. you can also find the Production Order no.
    you can see when GR has happened against Prod. order.

  • Daily Production Report with Variance or receipt of Production

    Hi All..
    my one of the clients want the Daily Production Report with Variance or receipt of Product?
    Please let me know what does it mean and how can I fetch this report
    Thanks
    Rahul

    Hi Rahul,
    Try This
    Daily Receipt From Production report
    SELECT T1.[BaseRef] as 'Production Order No', T0.[DocNum] as 'Receipt No', T0.[DocDate] as 'Receipt Date', T0.[CardCode] as'Customer/Vendore Code', T0.[CardName], T2.[ItemCode], T2.[ItemName], T1.[Quantity] as 'Receipt Qty', T1.[OpenQty] as 'Open Qty against Pro Order' FROM OIGN T0  INNER JOIN IGN1 T1 ON T0.DocEntry = T1.DocEntry INNER JOIN OITM T2 ON T1.ItemCode = T2.ItemCode WHERE T0.[DocDate] >=[%0] and  T0.[DocDate] <=[%1] and
    T1.[BaseRef] IS NOT NULL
    Summary Report For Production Order
    SELECT T0.[DocNum] as 'Production Order No', T0.[PostDate], T0.[DueDate], T0.[RlsDate], T0.[CloseDate], T2.[ItemCode], T2.[ItemName], T3.[CardCode], T3.[CardName], T0.[PlannedQty], T0.[CmpltQty], T0.[RjctQty] , (T0.[PlannedQty]-T0.[CmpltQty]-T0.[RjctQty] ) as 'Open Qty' FROM OWOR T0  INNER JOIN WOR1 T1 ON T0.DocEntry = T1.DocEntry LEFT OUTER JOIN OITM T2 ON T1.ItemCode = T2.ItemCode LEFT OUTER JOIN OCRD T3 ON T0.CardCode = T3.CardCode WHERE T0.[PostDate] >=[%0] and  T0.[PostDate] <=[%1]
    Thanks,
    Srujal Patel

  • Developed a report for the daily production done.

    hi experts,
    please give me tables and fields for following report, and also exlain me briefly,
    Developed a report for the daily production done.
    thanks in advance,
    radhakrishna

    Hi Prabhakar,
    Well you can opt for ALV display...
    You want to generate report based on plant data..
    Once the user enters the plant, you can extract the remaining info from table MARA, QALS, EKKO.
    The radio buttons will decide your selection critera.
    I dont think any functional guy will give you everthing spoon feeded. You will have to explore those tables and the relevant fields.
    In case you are finding it to difficult to get the relations between the tables or finding list of tables,
    i shall send u docs which will help u solve the problem.
    Give me ur email id
    Regards,
    Tanveer.
    Mark helpful answers
    Message was edited by: Tanveer Shaikh

  • Daily Production reports

    Dear Frndz,
    Are there any ready-made daily production reports available in the system.If so, pls help me with what are all the reports available and the transaction code /Path of the same.
    Regards,
    Srini

    Hi,
    You can find useful reports of PP in Production--> Shop Floor Control--> Information System as below :
    COOIS - Order Information System
    CO24 - Missing Parts Info System
    MD09 - Pegged Requirements
    MD04 - Stock/Requirements List
    MMBE - Stock Overview
    CO09 - Availability Overview
    CO46 - Order Progress Report
    MD4C - Order Report
    Further you can find other reports also under information system by drilldown in following segments :
    Shop Floor Information System
    Capacity Evaluation
    Capacity Evaluation
    Use of PRT
    Controlling Reports
    Hope this helps.
    Revert if you have any doubt.
    Regards,
    Tejas

  • Production Planning Reports

    Hello friends,
    My client wants following reports from System. Please tell me how can i get these reports  and from where?
    Reports are:
    1) daily & monthly prod report        
    2) daily & monthly m/c utilization
    3) daily & monthly productivity
    4) daily & monthly tooling consumption report
    5) daily & monthly operator efficiency
    6) daily & monthly m/c idle time
    7) daily & monthly rejection cost     
    8) daily & monthly down time cost
    9) m/c capacity/actual prod
    11)required tooling wrt component
    Thanks in advance!

    Hi Kiran
    Its difficult to find Standard reports in PP directly as per the client requirement. Most of time we have to go for development in ABAP environment or else can make Quick view reports in SQ00
    You can view all the standard reports by using the T-code SAP1 for all modules including PP
    Regards
    Brahmaji

  • Creation of production order report as per format

    Hi!!!!
    Gurus!!!!!
    I want production order report in some required format.
    How to see the format on production order
    How to see the report in the following format.
    Company name:-
    Material requirement Number:-
    date :-
    Time:-
    Due Date:-
    Plan Date:-
    Production Details:-
    Item Code:-
    Item Description:-
    WH:-
    Planned Quantity:-
    Completed Quantity:-
    Completed date:-
    Rejected Quantity:
    Waste and Scrap:-
    Evaporation Quantity:-
    Components:-
    Sr.No.      Item No.   Desription             BOM Quantity  Planned Quantity  Issue Quantity
    1     1000     RED                 20                     200                      200
    2     1001     BLUE                 30                     300                      300
    3     1002     Waste and Scrap -0.45987     -0.9845           -0.984567
              Total Quantity      50.45987     500.9845                     501.98888
    Order Remark.
    I want to see the report in this format.
    Thanks with Regards,
    Nitin

    Nitin,
    Your requirement certainly qualifies for creation of a new Production order Print form and custom print program if you are looking at printing at individual order. If you are looking at report, then certainly a custom report.
    Regards,
    Prasobh

  • Daily Production:Table

    Helll Experts,
    My req is to get daily production plant wise .
    Can anybody tell me std,report to know daily production & corresponding fields & table.
    Ravi.

    No Replies Yet, thats ok.
    This has been resolved by SAP.
    Thanks,
    Ram.

  • Opportunity Product Revenue report using Narrative option

    Hi,
    I have created quote report using "Opportunity product revenue report" with the use of narrative option and its working fine but the problem here is if opportunity has multiple product revenue items it shows in multiple quotes. For me it should show in a same quotation if there are multiple opportunity product revenue items in a opportunity. Could anyone help me how can i achieve this.
    Any help would be appreciated. Thanks in advance
    Thanks & Regards
    Ambarish

    You need to modify report and club all revenue to single item / row.

  • Acrobat Pro 6 Average Daily Production and Math.round problem

    Acrobat Pro 6 Average Daily Production and Math.round problem
    (Production.0) (154) (whole units) . (Production.1) (90) (fractional) / (divided by) 31 (days) results in (Average.0) (4)(whole units) . (Average.1) (10) (fractional) using :Math.round.� Noticed that 154 (whole units) . 85 through 99 (fractional) also show 4.10. (without Math.round : 5.00)
    Method:
    �Production.0� (whole units) . �Production .1� (fractional) / Days = (Average Daily Production) (�Average.0� (whole units) . (Average.1) (fractional)
    � Production.0 (value not calculated)�, � Production 1 (calculated) (event.value = util.printx("0099", (event.value)).substr(-2,2); � �Average.0 (value not calculate)�, and �Average.1 has following calculation:
    var punits = this.getField("Production.0");
    var pfrac = this.getField("Production.1");
    var average = 0.0;
    average = (punits.value + pfrac.value / 100) / this.getField("Days").value;
    this.getField("Average.0").value = average - average % 1;
    this.getField("Average.1").value = util.printx("0099", Math.round((average % 1 * 100))).substr(-2,2);
    �Math.round� appears to be a problem. Also, could you explain the purpose of �0099� . Anyway, why would 154.85 through 154.90 divided by 31 give 4,10. Also, their must be a better way, to find the average daily production. All you have to do is divided the production (whole. fractional) by the days, and display the average daily production as (whole. fractional). Any suggestions??

    There are a many loose ends in your question.
    First, I have never seen before a variable type called 'var'. Is it a java primitive or a class?
    Next, I cannot seem to find any class that has the printx method.
    When it comes to substr(-2,2), I get confused. First, I thought that it was a method of the String class, but I only got as far as substring(beginIndex, endIndex).
    If you really must break the production and average into pieces, try this:
    float average = (punits + pfrac/100) / days;
    int avg_units = (int)average;
    int avg_frac = (int)( (average - avg_units) * 100 );My guess is that util.printx("0099", x) formats x having two optional digits and two mandatory digits, showing 0-99 as 00-99, but allows to show numbers with three and four digits.
    154.85/31 = 4,9951612903225806451612903225806
    154.99/31= 4,9996774193548387096774193548387
    If you round the fraction of theese numbers multiplied by 100 ( = 99.51.. and 99.968...) you get 100, and this will be the output of printx. My guess for "4.10" is that substr(-2,2) returns the two first characters of the string, because the start index should not be zero. (According to java docs, substring throws an exception on a negative index, so what kind of class are you really using ??????)

  • No Daily Sales/Trend Report for today?

    Has anyone received your iTunes Connect Daily Sales/Trend Report for today (1/25/10)? I have not received mine yet. First time it hasn't been up at this hour.
    It usually arrives at 2:30am (it's 9:30am here now) or if it's delayed, usually in another region, there's a note in big red text on the reports page.

    As I recall (back when I only had a few apps just starting in the store), yes, no daily sales means no daily report. Wait for the weekly report to confirm.

Maybe you are looking for

  • Computer is getting a new hard drive and my iPods are full of all my stuff!

    I have a 3rd generation Nano and a 160GB Classic iPod. Here is my problem and I am hoping that someone can tell me how to proceed through this. My computer crashed and is getting a new hard drive installed now. I have all of my music on the Nano and

  • Error in the Dynamic query in AME

    Hi Experts, I am using the below query but i am facing the error "Ensure the query selects exactly 1 column" in AME Approval group under Dynamic query. But the query returns only one column when i ran in toad. select 'person_id:'||a.person_id  from (

  • 14" iBook G4 will not power up.

    I left it on last night and when I got home this morning it looked like it was asleep so I moved the mouse, hit the space bar and nothing happened, the glowing sleep light was still on. I waited a few minutes and tried again. Being impatient I took t

  • Check if the Sales Order is credit block.

    Hello Everyone, I have a requirement related to third party sales order and delivery. In the first system, a sales is created and then the PO gets created. Upon the creation of the PO a IDOC gets generated. The inbound IDOC in the other system trigge

  • Fonts in MIDP

    I am going crazy trying to get fonts to work with MIDP. It appears that I have to extend the StringItem class, override the paint method and do a graphics.setFont - this sounds way too cumbersome - there has to be an easier way. Don