Dear experts
I have encountered error messages during data realignment.  The error messages are:
1. Multi-level error propagation carried out
2. Realignment of liveCache time series aborted
I've run the Consistency Check for the Time Series Network(/SAPAPO/TS_LM_CONS_CHECK) and consistency check for Planning Object Structure(/SAPAPO/TS_PSTRU_CONS_CHECK). 
On the first time these were run, there were inconsistencies found with the livecache anchor - there were wrong and duplicate CVCs.  These CVCs have already been corrected and consistency checks are already error-free.
Upon execution of the realignment again, the same error messages are still encountered.  Please help.  What needs to be checked for realignment to be sucessful?
Thanks.

Hi,
I am assuming that you have maintained the Realignment table properly meaning you have only the necessary entries and removed all unwanted entries. Having assumed that the other reason why this error can come up is when you try to realign more than 1 Characteristic Value in the same table entry.
For Example.
Let us you have 3 Characterstics viz, product, location,customer.
If for Product P1, you are trying to change the location from L1 to L2 and customer from C1 to C2 then there is a possibility such an error might occure.
In such cases we need to create 2 entries as follows
1) P1 L1 C1 to P1 L2 C1
2) P1 L2 C1 to P1 L2 C2.
It is better to avoid Multiple characteristic changes in a single step.
Thanks
Mani

Similar Messages

  • KEND - restrict realignment run for a period only

    Hi All,
    I would like to restrict my realignment run using KEND for particular period only.
    1) Is this possible by creating new characteristic? Or through any development activity?
    If possible which table or field is to be considered for creating characteristic?
    Thanks in advance
    Bala

    Hi Bala,
    I'm sorry, but there is no period option to run the realignment.
    The realignment tool only accesses the CO-PA object table CE4XXXX (XXXX = name of the operating concern).  The profitability segments stored in this table don't contain a date because this would lead to
    severe performance problems in CO-PA reporting due to the huge number of profitability segments created by the system.  So it isn't possible to perform a realignment based on a specific date, only the characteristics are possible as selection criteria for a realignment run.
    Please also note that only the characteristics activated in transaction KEQ3 can be used in realignments.
    A realignment is only carried out on those profitability segments which meet the selection criteria for that request. These are defined in the selection criteria. This criteria must be true for a PA segment before
    it is changed by the realignment.
    To run the realignment successfully, the following conditions have to be fulfilled:
    1) The system should find an entry in table CE4xxxx which meets the selection criteria.
    2) The source fields of the derivation steps which should be performed by the realignment run must not be initial.
    3) During the realignment the first successful derivation step overwrite any existing values for that characteristic. This is different from how derivation works when posting actual or plan data.
    You can find further information in SAP Online Help under:
    Controlling -> Profitability Analysis -> Master Data -> Realignment
    Regards,
    Abhisek

  • Realignment table cannot be activated - help needed - Very urgent

    Hi All,
         Iam new to SCM and in the process of learning it. Iam trying to work with the realignment transaction /sapapo/rlgcopy. When i try to create a table , after characteristics selection it gives error "Realignment table cannot be activated". How do i proceed from there. Please help.
    It would be helpful if somebody could send a link that explains realignment steps in detail. I tried help.sap.com , but could not understand clearly. Kindly help

    Hi...
    As mentioned earliar reply...
    Hope you are having Authorization of realianment transaction...
    Transaction
    /SAPAPO/RLGCOPY - Data Realignment
    Check that you have selected Realianment button
    entered the planning object structure name
    You have created table/change table
    selected char to be ralianed
    and then maintained entries

  • DP Security for certain data view

    Hi all,
            Did anyone know if there is authorization object for a specific data view in planning book ? I want user to have access to just a certain data view not all of them in the planning book.
    Thank you in advance for your help,
    Paranee

    Hello Paranee -
    <b>Planning Area, Book</b>
    <b>C_AP0_PB</b> - Planning book
    <b>C_APO_SEL3</b> - Selections in planning books
    Authorization objects C_APO_SELE (Release 2.0) and C_APO_SEL2 (Release 3.0 up to Support Package 9) still exist in the system. They are however obsolete. If <b>C_APO_SEL2</b> has been assigned to a profile, set all field values to "*".
    <b>C_APO_IOBJ</b> – Key figure
    <b>C_APO_CPY</b> – Copy function in data realignment
    <b>C_APO_ RLG</b> – Realignment, maintain realignment table
    <b>Authorization Checks in SDP</b>
    All authorization checks in SDP are performed by the function module
    <b>/SAPAPO/MCP_PERMISSION_CHECK2</b> for individual data objects and<b> /SAPAPO/MCP_PERMISSION_SELECT</b> for a range (table) of objects such as products, locations, or planning books. This second function module incorporates the first one.
    If you want to adjust the result of the check, or program your own authorization check, you can do so by using user exit <b>/SAPAPO/SAPLMCPR_015</b> in function group <b>XDMUSER</b>.
    Hope this Helps.
    Regards,
    Suresh Garg

  • SAP SCM and SAP APO: Best practices, tips and recommendations

    Hi,
    I have been gathering useful information about SAP SCM and SAP APO (e.g., advanced supply chain planning, master data and transaction data for advanced planning, demand planning, cross-plant planning, production planning and detailed scheduling, deployment, global available-to-promise (global ATP), CIF (core interface), SAP APO DP planning tools (macros, statistical forecasting, lifecycle planning, data realignment, data upload into the planning area, mass processing u2013 background jobs, process chains, aggregation and disaggregation), and PP/DS heuristics for production planning).
    I am especially interested about best practices, tips and recommendations for using and developing SAP SCM and SAP APO. For example, [CIF Tips and Tricks Version 3.1.1|https://service.sap.com/form/sapnet?_FRAME=CONTAINER&_OBJECT=011000358700006480652001E] and [CIF Tips and Tricks Version 4.0|https://service.sap.com/form/sapnet?_FRAME=CONTAINER&_OBJECT=011000358700000596412005E] contain pretty useful knowledge about CIF.
    If you know any useful best practices, tips and recommendations for using and developing SAP SCM and SAP APO, I would appreciate if you could share those assets with me.
    Thanks in advance of your help.
    Regards,
    Jarmo Tuominen

    Hi Jarmo,
    Apart from what DB has suggested. you should give a good reading on the following.
    -Consulting Notes (use the application component filters in search notes)
    -Collective Notes (similar to the one above)
    -Release Notes
    -Release Restrictions
    -If $$ permit subscribe to www.scmexpertonline.com. Good perspective on concepts around SAP SCM.
    -There are a couple of blogs (e.g. www.apolemia.com) .. but all lack breadth.. some topics in depth.
    -"Articles" section on this site (not all are classified well.. see in ECCops, mfg, SCM, Logistics etc)
    -Serivce.sap.com- check the solution details overview in knowledge exchange tab. There are product presentations and collaterals for every release. Good breadth but no depth.
    -Building Blocks - available for all application areas. This is limited to vanilla configuration of just making a process work and nothing more than that.
    -Get the book "Sales and Operations Planning with SAP APO" by SAP Press. Its got plenty of  easy to follow stuff, good perspective and lots of screen shots to make life easier.
    -help.sap.com the last thing that most refer after all "handy" options (incl. this forum) are exhausted. Nevertheless, this is the superset of all "secondary" documents. But the maze of hyperlinks that start at APO might lead you to something like xml schema.
    Key Tip: Appreciate that SAP SCM is largely driven by connected execution systems (SAP ECC/ERP). So the best place to start with should be a good overview of ERP OPS solution overview, at least at the significant level of depth.). Check this document at sdn wiki "ERP ops architecture overview".
    I have some good collection of documents though many i havent read myself. If you need them let me know.
    Regards,
    Loknath

  • COPA Re-alignement

    Hi All,
    I have a field PSPNR(Wbs Element) in COPA records. There are couple of documents which are already posted to COPA and the wbs element field got updated.
    Now, I have created a new characteristic in COPA and I have created  a derivation for the same to capture only first 9 numbers of wbs element (PSPNR) to the newly created Characteristic.
    My question is how can I update the new characteristic field for documents which are already posted to COPA? Is it possible through KEND (Realignment). If yes, please advise how to create the realignment request for the same.
    Any response relevent is appriciated.
    Thanks,
    Kumar.

    Hi Kumar,
    Note 94458 will give some insight to KEND. Yes you are correct that KEND is the programe to be used in your case. If you want to populate afterwards some characteristics that have newly been added to the operating concern in the old profitability
    segment numbers already existing you have to use the realignment tool (transaction KEND).
    But realignment will only be successful if it is possible to derive the new characteristic values somehow from the current data
    of the profitability segment number - in other words it depends on your settings in transaction KEQ3 (whether the sales order number is 'used' or not, whether the material is 'used' or not etc.). In case that all this information is missing in the CE4 segment numbers, the same segment number can be used for different sales orders or billing documents so that it is impossible to derive the data from one single billing.
    That is, new characteristic should be filled by realignment if it can be derived on the base of characteristics that are already filled even in the "old" CE4 segment numbers.
    The realignment only changes the characteristic values according the definitions in the realignment request in the table CE4xxxx (Segment table) and NOT in the CE1xxxx (actual line items) or CE2xxxx (plan line items).
    Please also note that only the characteristics activated in transaction KEQ3 can be used in realignments.
    A realignment is only carried out on those profitability segments which meet the selection criteria for that request. These are defined in the selection criteria. This criteria must be true for a PA segment before it is changed by the realignment.
    To run the realignment successfully, the following conditions have to be fulfilled:
    1) The system should find an entry in table CE4xxxx which meets the  selection criteria.
    2) The source fields of the derivation steps which should be performed  by the realignment run must not be initial.
    3) During the realignment the first successful derivationstep overwrites  any existing values for that characteristic. This is different  from how derivation works when posting actual or plan data.
    Sometimes it happens that characteristics are not corrected during the realignment. The realignment can be carried out only under the following conditions successfully:
       -  Characteristics were used in the 'Selection' which are not  filled in table CE4xxxx (possible cause: in transaction KEQ3
          flag 'Not used' is set for the characteristic).
       -  If characteristics are supposed to be derived again in the  realignment, the source fields of the corresponding derivation
          steps must be filled in table CE4xxxx. The realignment change  only changes the characteristic contents in table CE4xxxx. The  characteristic values in the line items (CE1xxxx) are not  changed. The realignment change (realignment run) can be
          tested. Select the realignment run in transaction KEND and choose 'Test monitor' (F8).
    Please, check attached notes 524590, 553626, 122578, 438077 and 407446.
    Finally you should not directly go in to the table and change the data. As I told you realignment does not affect the CE1 or CE2 table. It's only CE4 table that is update. But this doesn't mean that you will not be able to see the realigned data in KE24.
    In transaction KE24 you may also display the results of realignments by choosing the option 'Read acc. to current structure' instead of 'Read as posted'. This will make the system read table CE1XXXX and additionally CE4XXXX and if the characteristic values in table CE4XXXX are different from CE1XXXX then the values of table CE4XXXX are displayed. As to note 407446 it should be not advisable to update table CE1XXXX because of the large amount of data overhead produced by
    a reversal logic like in release 3.1I. Furthermore if postings are performed that affect already posted line items like the reversal of an FI document, which causes the system reverse CO-PA line items, also table CE1XXXX and CE4XXXX are read, i.e. realignments are taken into account here as well.
    You can find further information in SAP Online Help under: Controlling -> Profitability Analysis -> Master Data -> Realignment
    I hope this clarifies your issue. Please let me know if I can provide any further help on this.
    Kind Regards,
    Abhisek Patnaik,
    Please, check attached notes 524590, 553626, 122578, 438077
    and 407446.
    Finally you should not directly go in to the table and change the data.
    As I told you realignment does not affect the CE1 or CE2 table.
    It's only CE4 table that is update. But this doesn't mean that you will
    not be able to see the realigned data in KE24.

  • Tables /SAPAPO/9ADEMCRT and 9ARAWCRT transportable or they need re-init ?

    Hello SPP experts
    The tables generated by the <IInitialize data realignment of demand history>  /SAPAPO/9ADEMCRT and 9ARAWCRT do not seem to be transportable unless I request an access key, make a change and try to attach it to a package. When you do <Object directory Entry> in SE11 on one of the table the system says
    Object directory entry R3TR TABL /SAPAPO/9ARAWCRT does not exist.
    Before doing this attempt,   does anyone know if they can be tranpsorted or the initialization must be done in Q and P by way of manual config ?
    Please advise asap.
    Tx
    YB.

    Yes, a session bean is how I have been using, but wasn't sure if that was needed (there was a way for a page to hold it's own value).
    However, I am a bit confused (unsure) about the scope of beans in a portlet. Does the scope refer to the the portlet itself, or the entire portal? (IE, if I add variables into the application scope, is it for all portlets in the portal, or just the portlet I am deploying the variable into?). Same for Session Beans, are they available to all portlets in the portal session, or just that portlet?
    Beacuse of these questions, I have been weary of using beans (at a higher level then page). Thanks for the note.

  • MPOS Creation

    Hi colleagues
    We plan to use DP and GATP  in APO for FMCG industry.
    For which i have a following Questions:
    Level for Forecasting:
    Product, Product Group, Plant, Province are required.Forecasting is done in monthly level.
    Expected combinations = approximetly  9000 to 11000 CVC's
    For Forecasting we plan to use keyfigure fixing at Product and Plant Level.We  need to maintain aggregate at Product and Plant.
    For GATP Check and Allocation Check:
    Product, Product Group, Plant, Province,9AKNOB and Customer  are required.Allocations are done in weekly Level.
    Expected Combinations = 69000 CVC's
    In our process, Statistical forecast is also one of the input to decide allocation.
    For allocations we plan to do fixing at aggregate level at Product and Province Level.We  need to maintain aggregate at Product and Province.
    For designing MPOS:
    Option 1: Separate MPOS for Forecasting and Allocation
    Pros: 1) Performance increases for forecasting bcoz less number of CVC's since no customers in forecasting.
    2) Only single  Aggregate maintenance to the forecasting MPOS and Allocation MPOS
    Cons: 1) CVC duplication with 2 MPOS
    2) Data realignment need to handled twice.
    Option 2: Single MPOS for forecasting and Allocation
    What is your recommendations on my requirement.
    BR
    Katerine

    Hi Katerine,
    I too think that seperate MPOS may be a better choice.
    Just couple of points.....
    'In our process, Statistical forecast is also one of the input to decide allocation."
    For this point, how do you plan to have forecast updated for the CVCs for MPOS- GATP ?
    Generating in this GATP  MPOS itself or copying from the other MPOS ?
    Please also note that 69K total CVCs is not a huge number to me, we have operated in volumes of CVCs which were  10-15 times more.
    To have many additional  background jobs/ process chains means addtional dependencies, monitoring , scope for confusions , more BW info objects ( say back up cube, extraction cube, hsitory cubes).
    Regards
    Datta

  • How to realign elements of an array? Working with old Dynamic Data consumers

    Hello,
    I've got some code which was written with DAQ assistants years ago.  I'm trying to use tasks and arrays for my producer now for speed and efficiency, but I'm stumped on one thing.
    The consumers were written to have the data in a certain order - there's even a VI in there that selects certain elements and sends them to specific outputs.  I previously took care of this with a simple VI that split the dynamic data, wired them to different order terminals, and then set it back to dynamic;  Screenshot attached.
    Is there a structure like this for array where you can break out all the array elements, reorder them and insert constants, and then put them back into the array?  What this ends up feeding is a subvi that's an array builder which converts the DD to array and then reroutes it.  Seems almost like what I'm trying to do could be done there, but it's a bit confusing to me.
    Thanks in advance.
    Still confused after 8 years.
    Attachments:
    realign.jpg ‏166 KB

    Hi Ralph@NES,
    One thing I have done before for this is create a mapping array and a for loop to reorder the elements in your data array. Take a look at the example VI I've attached. If you know exactly where you want everything, you just need to go into the mapping array and set the index destination for the corresponding data. Hope this helps.
    Paul C
    Paul C
    Applications Engineer
    National Instruments
    Attachments:
    Reorder Array.vi ‏9 KB

  • Error while realigning aggregates through master data attr. change run

    Hi all,
    We are using Sales Overview cube (SD_C03) on which we have built aggregates. now during the master data attribute change run it tries to realign the aggregate once the master data is loaded via Process chain. In this step we are facing an error:
    "Error while procesing aggregate <aggregate technical name>"
    From ST22 we can find
    Database error text........: "ORA-14400: inserted partition key does not map to any partition"
    Internal call code.........: "[RSQL/INSR//BIC/F200009 ]".
    Whereas from SM21 we can find out:
    Database error 14400 at INS access to table /BIC/F200009.
    /BIC/F200009 is the fact table of one of the aggreates we have. really looking forward to your valuable suggestion.
    Thnaks,
    Abhishek.

    Hi Jogeswara Rao Kavala,
    When I am pressing back or NO option  it is showing error like this
    What is this OK- Code means?
    how can I resume this process, even it was not going to back screen also and only one option is available for exit from this is by going into MENU-SYSTEM-SERVICES-BATCH INPUT-CANCEL.
    Sunil Boya

  • Process Chain - Master data Reorganizing and Realignment

    Hello Experts,
    1) Could you provide me the best practice on using the Re-organizing the master data for Time independant and time dependant attributes/texts.
    2) In addition to attribute change run for Master data attr/hier/texts, how significantly it would help by adding Re-organizing the master data process step to the master data load process chains ?  Is it mandatory to have this step at all ?
    3) Is it sufficient to run the realignment for attributes alone or you have to run it again after loading the hierarchies ?
    4) Advice whether to add Re-organize master data step for every single attribute and texts since it cant be grouped like other process types such as attribute realignment run!
    Look forward for your updates!
    Thank you, Vijay

    Hallo
    Please have allok at the following link:
    http://help.sap.com/saphelp_nw04/helpdata/en/e3/e60138fede083de10000009b38f8cf/frameset.htm
    Probably it is not mandatory but if your masterdata is a mess than it would be better on performance
    Mike

  • Working with Groups, Region Data Somehow Misaligned Locations in Audio Files.. How to Realign?

    Hello All,
    I'm a nonexpert, so please excuse in advance any lack of knowledge that I probably should have. I've been heavily editing a recording of several days of jams for a long time, basically by cutting and aligning very disparate parts to form something new. I had been working with my drummer's audio tracks in group, so each would be aligned as I cut, pasted and stretched regions. Now to my dismay, the all of the kick drum regions have become unaligned with the other drum tracks. This isn't something I can simply nudge, because it has shifted the location of the audio data of all of the kickdrum regions back 5 or 6 seconds. Therefore, the proper start of the region is not even loaded. If you look at the screenshot below, there are two audio files, one drum overhead (0022 AIRE 2) and the kickdrum (0023 BOMBO). The regions 0022 AIRE 2.89, 107, 108, etc. should correspond in sample location with 0023 BOMBO.89, 107, 108, etc. But, as you can see, the BOMBO samples have been shifted leftwards, all of them.  All of the other drum tracks have the correct alignment for each region.  My question is: Is there a way I can copy the region mapping information between 0022 AIRE 2 and 0023 BOMBO? Or are there any other ways to tell 0023 BOMBO regions 89, 107, etc. to pull audio data from the same location as 0022 AIRE 89, 107, etc.? I really hope so, because if not I'm helpless. Thanks to anyone and all who might have some advice. JS

    Jeez, now it has happened to my other tracks as well.. If someone could please help, I would be grateful. Put too much work into it to have this ruin everything.. Here is another picture, how can I get these samples to realign? Remember, they are supposed to be part of a group and thus aligned. For some reason, the samples for the track 040 BOMBO have been all shifted leftwards in time from where they take the sample from the audio track. How can I fix this? Thank you anyone who can help..

  • Realigned data missing

    Hi there, APO guru's,
    I realign certain combinations of data. for example, i realign one product with another.
    I also set the delete souce data tick on.
    I run realignment and the log says that the run was successful. But when i go and display the data then the old data is deleted and the new data hasn't been realigned to the new values.
    Can anyone please give some feedback on this.
    Thanks

    Hi,
    As i understood from the discussion, CVC for new combination got created and data is not copied.
    Before u execute the realignment steps, check all keyfigures or the keyfigure for which you want the data to be copied to new combination( for example sales history).
    Also check in planning area, whether you are reading sales history from info cube by setting the scemantic code 002. In that case you cannot realign the data as it is not phisically storing the data.
    Still if you have the problem, then let me know the exact scenario.
    Hope this helps you.
    Regards,
    Jagadeesh.
    Pls reward points if it is helpful.

  • Use of function module to update Realignment data: Demand Planning

    Hi,
    Can anyone explain how the function module /SAPAPO/TS_RLG_STEP_CREATE works? I need to use it to update Realignment table(of CVC creation in Demand Planning).
    Thanks !

    I also need information about this bapi /SAPAPO/TS_RLG_STEP_CREATE
    Thanks

  • Loading data from Cube to Planning area

    Hi,
             If I am loading data from a cube to a planning area using transaction TSCUBE,
    does the system load data into planning area for the combinations that exist in the cube or does it load for all CVCs?
    For example,
    I have my CVC as Plant, Material, Customer
    If there are 4 CVCs in the POS that were previously generated as
    Plant--Material--Customer
    01--M1--
    C1
    01--M2--
    C3
    01--M2--
    C2
    01--M4--
    C5
    If the cube has data like this:
    Plant--MaterialCustomer----Qty.
    01--M1C1--
    10
    01--M2C3--
    20
    01--M2C2--
    5
    (doesnot have the last combination), then if I use TSCUBE transaction to load data to Planning area from this cube,
    is the data loaded as
    Plant--MaterialCustomer----Qty.
    01--M1C1--
    10
    01--M2C3--
    20
    01--M2C2--
    5
    Only for the 3 combinations that exist in the cube and not load anything for the last one
    OR
    is the data loaded as
    Plant--MaterialCustomer----Qty.
    01--M1C1--
    10
    01--M2C3--
    20
    01--M2C2--
    5
    01--M4C5--
    0
    Load all 4 combinations and send 0 as the cube doesnot have this combination?
    Hope I am clear on this question.
    Thanks.

    Thanks a lot Vinod, Srinivas and Harish. The reason why I am asking you is that we have a scenario where we get this situation.
    We initially get data from R/3 to BW to APO like the below:
    Plant--MaterialCustomer----Qty.
    01--M1C1--
    10
    Later when the customer is changed or bought out by somebody C1 is changed to C2. Some times when the business doesnot know who the customer is initially they just put C1 as dummy and then after sometime replace it by C2. Then the new record coming in is as follows:
    Plant--MaterialCustomer----Qty.
    01--M1C2--
    10
    BW can identify changes in transaction data  but not in Master data. What I mean by this is when Qty. 10 changes from 10 to 20, the system can identify it in deltas.
    If the customer (master data) changes to C2 from C1, the system thinks it's a new record all together then if I use delta loads, it gets me the following:
    Plant--MaterialCustomer----Qty.
    01--M1C1--
    10
    01--M1C2--
    10
    If I am looking at Plant and Material Level, my data is doubled.
    So we are planning to do a full load that works like this:
    1. Initial data like the below:
    Plant--MaterialCustomer----Qty.
    01--M1C1--
    10
    The CVC is created and the planning area has Qty.10
    Then we delete the contents of cube and do a full load into the cube with changed customer
    Plant--MaterialCustomer----Qty.
    01--M1C2--
    10
    This time a new CVC is created. Then we have another 10 loaded into Planning area.
    If the system loads all CVCs, then the it would send
    Plant--MaterialCustomer----Qty.
    01--M1C1--
    0
    01--M1C1--
    10
    If the system loads only combinations in cube,
    then it loads
    Plant--MaterialCustomer----Qty.
    01--M1C2--
    10
    But the system already has another 10 for Customer C1 duplicating the values.
    We are trouble in the second case.
    We had to go fr this solution instead of realignment as our business has no way pf knowing that C1 was replaced by C2.
    Hope I am clear.

Maybe you are looking for

  • Return from method

    Hello, I want to return all three arrays in this method. what�s wrong with this code.tnx public int prim(int arr[]) arr[0] = Integer.parseInt(textField1.getText()); arr[1] = Integer.parseInt(textField2.getText()); arr[3] = Integer.parseInt(textField3

  • Server-side includes in css

    I am trying to incorporate server-side includes for my nav. links. I created the website using css. I am able to preview the navigationals (with proper links when I hovered) with F12 iexlorer, but when I upload everything and view it from IE, Mozilla

  • Dynamic PL/SQL binding problem

    Hi all, i have some proble with my pl/sql code. Thisi is the code DECLARE Lancio_T VARCHAR2( 1) := 'N'; Rec_Cam VARCHAR2(100) := 'ALL'; BEGIN str_Sql := ' CREATE TABLE SIEBEL.TEMP_1074_SERVIZI                '|| ' AS      SELECT      /*+INDEX (temp I

  • Report help / question

    I want to pull a specific report. either from the p6 tool reporting or directly from the database. Using Primavera p6 version 7. All the Role names and capacity / demand time for each role over a timespan where the role is assigned to an activity, an

  • Include dbpnpcom error

    Hi, I copied the std program RPLICO10, it gives me this error message - In unicode program, the "-"character cannot appear in names, as it does here in the name "pnp-sw-found". what is this error message whats the remedy? regards Ravi