Hii
I want to archive the shipment cost document in my system for a particular date range.
When i go to the transaction SARA and put the object name as SD_ VFKK, it doesnt show me the date variant.
Whereas when i archive shipment(object: SD_VTTK), date variant is available.
Can anyone suggest any kind of setting which needs to be done in order to use the date variant for the object SD_VFKK
Thanks
Gaurav Manocha

Hi Gaurav,
Actually for Object SD_VFKK, when you to transaction code SARA and click on write variant, you dont have date option there. You can archive it only on the basis of Shipement Cost Document number.
If you will give me the details then I can see what you are actully looking for.
Regards
Sirfraz

Similar Messages

  • Required BAPI for Shipment Cost Document (VI01)

    Dear All,
       I required BAPI for Shipment Cost Document (VI01), pls help on this.
    Regards
    Ranjit

    Dear MM
      Thanx for replying, but the BAPI which you have provided will only show me the Cost with correct Tax calculation,
    But its not getting created, which system should show the Shipment Cost Document number.
    Regards
    Ranjit

  • Changes log for shipment cost document

    Hello all,
    We are using shipment cost documents in both inbound and outbound processes, and currently changes in the SCD are not logged anywhere.
    How can I keep track after the changes in the SCD?
    Any help would be appreciated.
    Regards,
    Dikla

    Hi Syed Hussain,
    The flag for change documents for the shipments is already set.
    My problem is with the shipment cost document and not the shipment it self.
    When I create a shipment cost document it reflects in tables CDHDR and CDPOS as changes of the shipment statuses,
    but when I change the shipment cost document after the creation - it does not show anywhere.
    Are you familiar with a flag like the above, but for shipment cost documents?
    Regards,
    Dikla

  • Service Entry sheet Creation for Shipment cost Document

    Dear All,
    While creating a shipment cost document .A service PO is getting generated in the back ground based on which a service entry sheet is created and LIV is made.But in the configuration we are mapping the Transportation planning point to Purchase organisation alone.
    Can some one let me know whether the generation of PO in the back ground for a shipment cost document in the back ground is a standard SAP feature if so can you tell me the configuration steps.
    Regards,
    K.Vivek

    Hi,
    Creation of Service PO in shipment cost document is based on the following SPRO setting or T-code.
    T code : T_56.
    SPRO > LE > Transportation > shipment cost Document > Shipment cost types and item categoires.
    Get into the details of item categoires, you can see the indicator Generate PO.
    hope this helps.
    Harish

  • Stages for shipment cost Document

    Hi,
    I have three vendors(service Agent) involved for a leg such as forwarding agent, transporter and broker. Our company is dealing separately with each vendors.
    how to handle this scenario. Kindly give the step to create stages. I have created stages but its not configured correctly.
    Is it possible to have different pricing procedure for a service or can we handle in one pricing procedure?
    Since I am new to shipment asking this question? If this is simple question kindly guide me to achieve it?
    Waiting for you reply.
    Regards
    Fazal

    Why isn't it configured correctly? you have to create item categories for each vendor type. For each vendor type you need one for the header of the transport and one for the legs.
    Then for each item category you can define a pricing procedure.

  • G/L account determination for shipment cost

    Hi Experts,
    I am having a problem setting up account determination for shipment cost document.
    When saving shipment cost document, SAP generates "service entry sheet" (PO) and GR with accounting document,
    but I would like to change the default G/L account by shipping condition type.
    So far, I have set up automatic G/L account (OBYC), GBB and WRX, but I could only define the default one.
    Could you please advise if it is possible to change G/L account for freight accrual?
    and if yes, how to change G/L account determination by shipping condition type?
    Thank you
    JK

    Hi,
    1. Menu Path: Logistics Execution > Transport > Shipment Costs > Pricing > Pricing Control > Define And Assign Pricing Procedures
    Transaction Code: SPRO
    Shipment pricing procedure is same as the standard pricing procedure and uses condition technique to retrieve the data from condition tables.
    2. Pricing Procedure Determination for Shipment Costs:
    Based on the combination of Item category Determination group, Service Agent Procedure Group, Shipping Type Procedure Group, pricing procedure is determined
    Menu Path: Logistics Execution > Transport > Shipment Costs > Pricing > Pricing Control > Define And Assign Pricing Procedures
    3. Search Procedure for the PO:
    TPPt: Transportation planning point is taken from the shipment document
    SCTy: Shipment Cost type is taken from the shipment cost document
    POrg: /Pgr/Plant: Purchasing Organization, Purchasing group and Plant is assigned to the combination of TPPt & SCTy.
    On these values the purchase order is searched for the Vendor mentioned in the shipment document
    Menu Path: Logistics Execution > Transport > Shipment Costs > Settlement > Assign Purchasing Data
    4. Automatic G/L account Determination
    I hope this information will help to you.
    Thanks & Regards
    Raju
    From the Transaction u201CGBBu201D and combination of General Modification key u201CVBRu201D and valuation class the G/L account is determined for the posting to the freight accounts.
    Menu Path: Logistics Execution > Transport > Shipment Costs > Settlement > Automatic G/L Account Determination
    From the Transaction u201CWRXu201D and value of valuation class as u201C u201C the G/L account is picked for GR/IR accounts.

  • Error in Shipment Cost document(Delivery date is in past)

    Dear All,
    While iam trying to save the shipment cost document, i am getting error like Delivery Date is in past. Due to this error iam unable to generate the P.O in back ground. We are creating the shipment Cost for the S.T.O process.
      I want to know system is considering which delivery date in shipment cost.
    Regards
    Sunil

    Hi
    Can you provide few details like.....
    what are all preceeding steps you completed before shipment cost Processing
    whether you restricted only backward scheduling?
    Generally backward scheduling checks whether the delivery date  is in past or not?
    Thanks & Regards
    Bhaskar

  • Freight capitalization for STO process using shipment cost document

    Dear MM experts
    I have been testing and trying to charge freight to material using transportation module. I know how to do it in simple STO process without SCD (shipment cost document) but I am not able to do it with SCD.
    I have searched and tried every link I found on SCN. Unfortunately there are many open threads and non of them is answered or giving complete solution. For example I have tried this link where Ajit Kumar has explained the scenario in detail I am but unable to achieve my result. I have also tried other links and SAP note 427944 as well.
    Now what thing confusing me is accounting entries and documents/steps where these accounting entries will be posted.
    My current process is like this in plant to plant transfer under same company code
    STO > OBD > Shipment Document > PGI > Accouting Entry with 641 movement type. Material account debit and same account credit. > Shipment Cost document > GR with 101 without any accounting entry > Transfer freight cost to FI using Freight Service PO determination > Accounting Entry Freight Outward Expense Debit and Freight Clearing Account Credit > MIRO > Accounting Entry Freight Clearing Debit and Vendor Credit
    As you can see we are booking freight as an expense and not charging to material. Now what I want is that freight should be charged to material. If I am sending material from plant P000 to plant P201 under same comapny code then freight charges should be added in material cost in plant P201.
    I have done FRB1 condition type with accrual and copy shipment cost tick mark and other stuff suggested in all those threads but it is not working.
    My requirement is to understand the points where and what accounting entries will be created as per my new scenario which is same as old one except one difference which is to charge freight to material instead of booking expense in freight service PO.
    Lets take an example that material cost price is 100 and freight charges is 50. Now as per old threads at the time of GR against OBD system will create accounting document with 150 debiting the stock in plant P201. What about credit? If we have added freight here then what about 2nd accounting entry in my first scenario in which freight expense is debited and clearing account is credited? Could anyone please explain accounting entries and points where these entries will be posted?
    Another thing is that is it only possible with moving average price to charge freight to material or can we do this with standard price as well using some standard or customized solution?
    Detailed and easy to understand answer will be highly appreciated.
    Thank$

    Hi Moazzam ;
    Firstly, you can benefit Badi/s in package VTRA which is given belowed.
    Secondly , i think that  shipping method --> create sto with delivery --> create shipment document and shipment cost document (problem is starting so system will be create PO and service entry sheet automatically , can you try shipment document is non-related with cost document.
    Thirdly , you can post invoices charge to material with miro , if you success to direct freight costs to stock account (BSX).
    Also , you can benefit doc. sap behaviours for Std price/ Map --> Planned & unplanned delivery costs in mm
    I hope , you can manage your process ; for me standart way is the best.
    Regards.
    M.Ozgur Unal

  • Document date of Shipment cost document in a transfer document

    Hi Gurus,
    I have created a new shipment document and a new shipment cost document. I have created the news document with the settlement date to 30.06.2008. Then, I have transferred the shipment cost document.
    The problem is the document date of the new account document that is 16.07.2008, while the posting date is 30.06.2008.
    Is it possible to change or to assign the document date before to transfer the shipment cost document?
    Thanks in advance.
    XeviG.

    Dear Karan,
    My problem is not the settlement date, it is correct to 30.06.2008 because I need settlement in a period before (period 06). My problem is the document date in the account document that I need the same than settlement date, 30.06.2008, when I transfer the shipment cost document.
    I need modify or introduce the document date before to transfer shipment cost documents.
    XeviG.

  • Tax code for service tax in shipment Cost document

    Hi,
    Can someone pls. tell me that do we need to create Tax Codes for Service tax, edu Cess and secondary & higher edu cess for Shipment cost doc?
    If yes pls. explain the config in detail.
    Regards
    Abhilash

    Dear Abhilash
    Tax codes can be classified into two types, viz. Output Tax and Input Tax.
    Output tax can be assigned to all sales related activities whereas, input tax can be assigned to all MM related activities.
    To maintain these tax codes, go to <b>FTXP</b> and maintain tax codes for the combination of country and tax code.
    Thanks
    G. Lakshmipathi

  • How to update sales order number (KAUFN) characteristic in the profitability segment of the PA document created at the time of service entry sheet confirmation, as a result of shipment cost document

    Hi,
    We have a scenario wherein we create shipment cost documents against delivery. As a result of shipments fully transferred, a PO for freight vendor is automatically created and a service entry sheet confirmation happens. As a result of service entry sheet confirmation, we have Financial accounting, Controlling and profitability analysis documents created. We have a requirement wherein we need to have the characteristic “sales order number (KAUFN)” populated in the profitability analysis document created as a result of service entry sheet confirmation.
    Could someone please advice how could this be attained in COPA. Thanks for your help in advance.
    Regards,
    Sandeep

    Hi Ajay,
    Thank you for the quick update.
    The document is updated to COPA through OKB9 settings. The profitability segment is updated with fields like customer, product, company code, plant, sales area data, profit center, etc; however the sales order number is missing.
    Could you please elaborate further how could FI substitution be implemented to call for the FM COPA_PROFITABILITY_SEGMENT through user exit? Are you recommending the substitution through GGB1? What could be the possible validation to call for the user exit to be implemented?
    Regards,
    Sandeep Kulkarni

  • Auto creation of Shipment cost document

    Hi Folks,
    Is anyone aware of how to create a shipment cost document using a function module?
    I need to create shipment cost document as well as update the condition values. But all this needs to be done via a BAPI or something in the background.
    Thanks,
    Mihir

    Seen an abaperr and check out the program "RV56TRSL" for your requirement. Through this program, you can Schedule the creation of Shipment cost document.
    If you're talking about automatic PO creation then you need to do the following:
    1. Assignment with relevant Purchasing org & group will be done at SPRO->LE->Transportation->Shipment cost->settlement->Assign Purchasing data
    2. To create the PO automatic you need to do these settings :-
    By selecting the shipment cost & item category for automatic PO (T_56) and selected the default PO type for the transaction.
    Path :- IMG > Material Mgt. >Purchasing >Define default Values for Document Type.
    Path :- IMG >Logixtic Execution >transportation -> Shipment Cost >Ship Cost Document >Shipment Cost Type & Item Category (T_56).
    3. Remember to check EKKN which is the table for account assignment in PO.
    Good luck

  • Split a Shipment costs document into several MM document by carrier

    Hi gurus,
    I am trying to split a Shipment costs document into several MM document by carrier. We need the system to search for an existing MM order if not found create a new one (the system is set to do it by V_TVFT-BESER value “A”).
    I have a route with different stages. These stages/steps have associated different carriers (or partners).
    When these data is transferred to MM purchase order the system gives an error with the message no. M7107:
    Enter goods receipts for vendor 103962 only
    Message no. M7107
    The system does the purchase orders but not the 101 movement.
    Does someone met this problem before?
    I am in 700 SAP version with package 12
    Regards.
    Mikel

    Hi,
    Check out BADI BADI_SCD_PO_SELECT. This allows you to control which purchase order is used for shipment costing.

  • Business Area not flowing automatically in Shipment Cost document

    Hi there,
    In transportation module, while creating shipment cost document, business area is not flowing automatically. Upon more exploration we found that plant is also not flowing, and may be because of that business area is not flowing. What can the posible reasons for plnt not flowing? Suggest solution.
    Thanks and Regards,
    Deepshikha

    Dear Deepshikha,
    Please check the Assign purchasing data settings in T_53 transaction with the combination of the plant.
    Through this setting plant will flow in the shipment cost document.
    I don't have idea about where the businees area field avail in the shipment cost document.
    If so please chek the settings related to business area through this IMG path.
    SPRO>IMG>Enterprise structure>Assignment>Business Area Account Assignment.
    Define Rules By Sales Area
    If Rule 1 is assigned then
    Assign Business Area To Plant And Division
    If Rule 2 is assigned then
    Assign Business Area by Sales Area.
    I hope it will help you,
    Regards,
    Murali.

  • Grouping transport documents in one shipment cost document???

    Hello!
    I need to create one shipment costs document for several shipment, grouping by carrier and range of shipment end date. Does anyone know if it´s possible?
    Thanks in advance
    Manuel

    Hi Ramky,
    I know that VI04 allows to create shipment cost documents massively, but at this moment the system generates one shipment cost document per each shipment document. I want to group by service agent and date
    Anyway, thank you!

Maybe you are looking for

  • Download Movies from Music Store but will not show up in ITunes Library

    I purchased a Movie from the iTunes Music Store. After downloading the movie the movie disappears. It's not in the itunes libaray or anywhere on my hard drive. I looked at my purchases account info for the store and it has a record of my purchase. Is

  • How to print a word document using java?

    Hi All, is it possible to write a java program that takes input and directs it to printer. I specifically want it for word document. i already have a program that works for images but not for word document. Plz guide me where i am wrong or help me wi

  • Flash Alternative for developing app with lots of 2D Animation

    First let me say, I know Flash does not run on iPad. And I'm not looking for an alternative to Flash Video. I want to create an app for the iPad, with a lot of full screen, 24 frames-per-second animation. Basically an interactive Animated Movie, like

  • Messages not sending in Outlook

    Hi I hope someone can help, I have a talk21.com account that I use via Outlook 2010. I now cannot send messages from this account and is returning error 421 too many messages. I have tried to set up a new account but that does exactly the same. Does

  • Can somoene please help me get all my pannels back?

    I was clicking on remove panels for one screen now all of them are gone. I just want it to go back to the original view  so that I can see everything like it was when I first started my project. Can someone please help me with that? How do I get back