Dates problem in MRP Run

Hello
i m running mrp using zpp_md50 is the zprogramme for running the mrp for all the line items in one sales order,  after running the MRP, whatever the pur. req. generated we will convert it to PO, but client need one release statergy here so that  they can take the assurance from the suppling plant that whatever the date mrp run showing is that plant is really able to supply the goods on that date or not.
1) if suppling plant is not able to send the goods on the requested date in that case receving plant should be able do the amendment (change) in dates in their panning so that they can give the new delivery date to the customer?how to achive this?
2) They also want when we run the MRP, system has to consider the unrestricted stock present for the sales order line item,but without giving the sales order ref. using 412e to sales order.cause their r huge no of line item in sales order.
3) my client is not able to achive the customer date so it is very imp to do the amendment in mrp dates cause the dependacy is on the supplying plant & the suppling plant can produse only taking  material grades of the same item at a time & it is not possible for suppling plant to produce as per the delivery date of the order.so  the date in master ie. in house production date maintain is not really going to be follow, as the plant is critical, plz suggest some solutions for this also?
Regards
Nishj.

Nishj,
Wow.  Substantial requirements.  Let me see how many of these I can help you with.
i m running mrp using zpp_md50
Please understand that that program is custom to your system.   It will be hard for us to comment on it's workings.
they can take the assurance from the suppling plant
It seems that you are selling the product from one plant but manufacturing in another
if suppling plant is not able to send the goods on the requested date in that case receving plant should be able do the amendment (change) in dates in their panning so that they can give the new delivery date to the customer?
This is standard in SAP.  Basically, the suppying plant will create a supply element (production order, process order, perhaps in conjunction with a Stock Transport order) to move the parts to the selling plant.  Once this element is in place, someone from Sales or another appropriate functional group will re-ATP the sales order.  The sales order will then re-confirm against the new, more accurate dates.
They also want when we run the MRP, system has to consider the unrestricted stock present for the sales order line item,but without giving the sales order ref.
This can be achieved easily, by not using a MTO strategy.  If you use strategy 40, Sales orders ATP, and all MRP calculations, will make use of all unrestricted stock.  If there then is NO sales order stock, then this means that ALL stock is included.  Just avoid any MTO strategies throughout your BOM.
There is no standard SAP functionality that will include Sales order stock and unrestricted stock simultaneously for the same part for the same requirement.
my client is not able to achive the customer date so it is very imp to do the amendment in mrp dates....
I am not sure what you are asking for here.  You have stated the solution:  The supplying plant does their research, and they then create a supply element with the realistic dates.  The Sales order ATP check will then re-confirm to those dates.  MRP will also run using those modified dates.
Rgds,
DB49

Similar Messages

  • Alternative BOM problem in MRP run

    Hello Experts,
    We have two BOM for one material.Now I want to use BOM-1 for MRP run & BOM-2 for subcontracting.I have maintined following settings.
    1) Production version.
    2) BOM explosion selection method in MRP4 -2
    3) Assign PV in inforecord for subcontracting.
    4) Assign PV in MD61 in schedule line .
    But when I run MRP it still consider subcontracting BOM.Have I missed any setting?
    Kindly guide.Thanks you.

    Hi, Follow the below process,
    1.Enter the BOM selection method as 2 in the MRP4 view of the material master.
    2.In case if you have not assigned the production version in MD61 against the PIR's under schedule line
    tab key (in the top menu click on settings and prod version ,then you can assign the prod version which
    you need to pick during the MRP run),the system always picksup the first production version during
    MRP run even if all the prod versions contains the same validity dates and lot sizes.
    3.If you are not willing to assign the prod version in MD61 ,but the system should consider the second
    prod version for MRP run means,then set the locked status for the first prod.version.
    4.When run MRP via MD02 or MD50 in the simulation mode.(i.e w/o giving tick in simulation mode).
    Click on Save,You will get a pop screen,
    Now click on the continue icon, Then go to Plaining Results: Individual lines screen.where you will get Plan order on which when double click you will get pop screen below,where you have Planned order no,quantity,plant,storage location,and version.
    Now here you can select the required version,and it will become firmed. This BOM will be used in the order now. Try it.

  • Reschedulig Date Problem in Planning Run

    Hello All,
    Need Clarification..
    The Scenario:
    The Requirement date (OrdRes) is 13.02.2009, The planned Order generated is on 13.02.2009.
    Now the OrdRes Date Changed Manually to 27.01.2009.
    After Background MRP Run, in MD04 against the planned order, the Rescheduling date proposed is 27.01.2009 and exception message is 30 ( Plan process according to schedule).
    System is Proposing the date, but not actually shifting the planned order.
    If I re-run the MRP Manually, the Rescheduling is happening.
    What at first place the rescheduling not happened? after manual MRP run the rescheduling happening?
    P.N:
    1. The Planned Order is not Firmed
    2. The Planning Parameters are same for Background Run and Manual one.
    Your inputs are highly appreciated..
    Regards,
    Siva

    Hi Siva Kumar,
    Once u change the delivery date (order rervation of Header), system will create planning file entry for Child materail and set Exception message 30 of child planned order
    When u run the MRP  next, child material should be included in the Planning Run and rescheduling should be happened .
    This is what my finidings, Please check.
    Pradeep

  • Problem with MRP running

    Hello Gurus,
    i have a problem with my product. lets take an example. my semifinished product abc is made up of a, b and c.
    i have made them(abc, a, b and c) to use MRP type VB. i made palnning file entry and BOM and then i run the MRP.
    I run single item multilevel MRP for semi-finished product abc, it showed me result in MRP running only for abc but not for a, b and c.
    can u please tell me where i am making any mistake.
    regards

    Hi Maggi,
    If you have used mrp run for single item,single level  planning (ie) md03, it will plan only for that particular material & will not plan for the dependent material in the BOM.
    If you run with t.code md02, MRP run for single item,multi level, all the dependent requirements will be planned.
    Also VB is for reorder point planning. ie if you maint reorder level as 100 for a,b & c materials & if the stock goes below 100, say  50 Nos. for all the three material. Then procurement proposal(Pur req) will be created for 50 nos for all the material(a,b,c).
    If you use MRP type PD, there is no question of reorder level, during mrp run system check the stock of the dependent requirements. If there is a shortage procurement proposal are created.
    Regards,
    Senthilkumar SD

  • Problem during MRP RUN.

    HELLO, FRIENDS,
    if i select mixed MRP in the material master with indicator 2 i.e.gross reqirement
    for MRP run ,but after taking MRP run through md01 .its not exploding dependent requirement of its component.Is there any setting for this?
    lpease give solution
    regards,]mangesh

    Hi,
    Check with t.code CS11 & check the result whether BOM is exploding or not.
    Then check in t.code OS23, whether mrp exlosion is activated or not.
    Check the BOM usage used while creating the BOM.
    Regards,
    Senthilkumar

  • Problem in MRP RUN

    Hi,
       We are maintaining one field in suppose MRP field in MRP1view as "X".
    In  Enhancement, we develop logic like that if in material master MRP field value equal to "X", then while creating reservation,system automatically create a PR along with reservation.
    Now My Problem is -
    I created a material with MRP field as "X", MRP type as ND.
    i created a resrevation for this material,system will generate PR no. 10000002.
    Now i am changing MRP field as Blank, & MRP type as PD.
    if now i am running MRP,system will generate again a new PR.now i have two PR for the same reservation.
    i also tried in t-code MD03, planning parameter as 3 (delete & re-generate).
    so now i have two PR against a reservation,if i am checking in MD04.
    so how can we control this situation,so that only one PR can create against one reservation.
    OR can we exclude that reservation / storage location for MRP,then my problem will solve.
    Thanks
    Pavan

    When you make enhancements you are taking responsibility that all scenarios are covered, and should not expect a solution from standard SAP.
    Change the nhancement in such a way, that when you try to change from X to blank, system will issue a message saying that Preqs exist, and thus will not let change before those are deleted.
    This will prevent the double coverage issue.

  • Change Purchase Order date as per MRP Run

    Hi SAP Gurus,
    My scenario is like that, MRP for a Material is run last Month and Purchase Requisitions are converted into Purchase Order, but there is no Good receipt for this purchase order. So my requirement is that when i run MRP for current Month. It will change the Date of same Purchase Order. Is this thing is possible through any enhancement /standard SAP scenario. Please give me a solution

    Hi
    MRP will not change the Purchase order dates since it is a firmed receipt element.
    You can achieve your requirement like this,
    1. You run MRP for the current month, if the PO delivery dates are not matching with the required date, system will give exceptional message with rescheduling dates.
    2. You can make a custom program to change the PO delivery date as your rescheduling date or whatever logic you want.
    Regards
    Bala

  • Scedule lines data change after MRP run

    I generates a schedule lines when I run the MRP for certains articles. When I run again MRP, It modifies the data's of schedule line (quantity per ex) even thoough I have already transmetted the request (schedule lines) to the vendor.
    How to prevent to make changes in the schedule line once I sent the info to the vendor. Instead I would like that the MRP creates new schedule line.
    Than you for any help.
    Ahmed.

    Hi Ahmed,
    In MRP-4 view have you maintained 1 or 2 for Indv. / Coll indicator?
    Regards,
    Vivek

  • Problem in MRP run with Project/WBS Element

    Dear PP Gurus,
    I want to run MRP thro Project/WBS Element.
    I have created WBS Element & WBS BOM for Material. Then created sales order for that material and assign WBS element to sales order.
    Maintain Planning Strategy 21 ( Make to Order/Project) for Main Mtl.
    Now when I run MRP with MD51 then no requriements are generated for main material and its components.
    Is there any thing missing from PS-PP & SD point of view?
    Pl guide me for the same.
    Thanks in Advance.
    Umesh

    Dear Nagrajan,
    Thanks for your reply.
    There is no safety stock & un-restricted stock of that material.
    Also I don't want to assign this mtl to that wbs Network. If I assign the Material to WBS network then network req.is generated and thro Normal MD02 MRP generates the requirements.
    & in the plan order it will not show WBS Element
    But My req. is I want to run MRP with  MD51 & want WBS element as account asignment tab in plan order & production order too.
    IS there any config. missing from PP/ PS / SD ?
    Pl guide me for the same.
    Thanks ,
    Umesh

  • Problem in MRP Run (MD01)

    hi experts,
           There were some MRP controllers were assigned for User exit in SPRO for planning run (T code :- MD01 ). Now i have defined additional MRP controllers and also assigned them for user exit (in SPRO) for planning run.
           With old MRP controllers defined as user exits , Planning run is considering materials with only particular MRP controller.
            But for these newly defined MRP controllers , user exit is not restricting planning of materials with only particular MRP controller and materials planning is carried out for all materials with newly defined MRP controllers.
         please help me out
    thanks in advance
    rgds.
    jai

    hi experts,
       No one has answered my query yet. please reply
    rgds,
    jay

  • MRP Run - Planning file entry Issue

    Dear All,
    We are facing one problem in MRP Run. We run MRP in the background for a plant (MDBT) System is not creating planned order for few component. I have checked all relevant setting. I found that planning file entry is missing. I would like to know that how system can miss the material? How system creates & delete planning file entry ? I have some data related to this.
    Last MRP run date is 22-04-09
    PIR changed date on 30-04-09
    MDRE Run on the 30-.4-09 at night.
    MRP Run on 02-05-09 at night.
    Problem reported that no planned order for the material on 07-05-09.
    We have huge number of material so its difficult to check all material individually whether MRP run happend or not ?
    Please let me know the possible reason for this.
    Thanks & Regards
    Kundan Kumar

    Dear,
    If you carte materaial or uplod materail before activation plant for MRP this may be the cause for this.
    Planning File creates all the materials relevant for the planning run.
    The planning run and the scope of the planning run (which materials are planned in which planning run) are controlled by the planning file.
    For planning file entry use the following transactions,
    MD20 : Create planning file entry
    MD21 : Display planning file entry
    MDAB : Set up planning file entry in background
    MDRE : Check planning file entry Please run this in it will solve your problem
    All materials assigned with MRP are automatically entered in planning file entry.
    Depends on changes in material planning or in proposal , system will create planning file entry.
    When MRP run system will consider only which materials having entry in above contents of planning file entry. After MRP run system delete the planning file entry. And again material gone the changes like GI GR on any other demand  then system generate planning file enty again.
    Hope it will help you to understand basic concept.
    Regards,
    R.Brahmankar

  • BOM selection during MRP running

    Hi,
       I have a question about BOM selection during MRP running...
       I have three production version and all of them are valid at the same time..I get a problem "no BOM data seletion" during MRP
    running..I suspect it is due to that I have three production version and MRP didn't know take which one..Can anyone tell me
    where can i config it or what's wrong with it in my situation?
       btw,BOM usage and stats are correct .so is the router data..since MRP is running well if i only have one PV..thanks..

    Hi Monst,
    Looking at the screenshots you uploaded, it seems that the validity of each of the production version is from 7.12.2011 to 1.12.2012.
    Please check whether for Planned order no. 36659 alternative BOM no. 1 is getting selected (Since BOM selection ID is 2).
    For planned order nos. 36660, 36661 and 36662, the start date is perhaps before 7.12.2011 and end date as we can see lies in the validity period of production version. Hence, neither of the alternatives of the BOM is getting selected.
    For verifying the above logic, please make the BOM selection method as 3 (selection only by production version) and run the MRP. I think MRP will get terminated in this case since no BOM will be chosen for first planned order.
    Just in case u need to select the BOM for planned orders, you can manually enter the production version no. in the planned order change mode.
    Please tell if this helps and revert back.
    Regards,
    Chetan.

  • Planning File Entry Not Created For MRP Run

    We are running MRP in backgroung at MRP area level as per scheduled. One material is missing from MRP run. We are expecting that we should get the proposals because stock is zero ( below reorder level) on the date of sheduled MRP run. Earlier it is working.The material MRP relevant data is given below.
    MRP Type - VB
    Reorder Level - 6
    Lot Size - Fx
    Fixed Lot Size - 10
    Minimun Safety Level - 10
    Please help us to resolve this issue.
    Thanks in advance. For any clarofiaction, pls revert back.
    Regards,
    Chetan K

    Hi,
    Please check whether you have maintained the Availability check group 01 or 02 in MRP-3 View.
    Also check the Dependent requirement selection in MRP-4 view individual collective and Selection method in MRP-4 view for its assy material.
    Check the Plant specific material status whether it is blocked for any procurement or usage in Basic Data and Purchasing,MRP  views.
    thanks and regards
    muru

  • STO Not to be considered in MRP Run in MTS

    Dear All,
    We are facing the following problem in MRP run in MTS scenario when
    there are STOs in Plant.
    We have 2 Plants one is production Plant (Say A) and other is Non
    production Plant (Say B) from where only Deliveries will be made.
    Now after final material will be produced in Plant A it will be routed
    through Stock transport order (STO) to plant B.
    So there will be always STOs in Plant A which will be created in Plant B.
    Now we are using Strategy 11 (Gross req. Planning) for Final FERT material.
    In MRP if we have PIR of 100 Qty. and STO of 50 Qty. system is creating
    the Planned order of 150 quantity which is a normal system behavior.
    Now our requirement is that it should not include STO in Planning (MRP Run).
    Pls. Suggest.
    Regards,
    Vinayak.

    Hi,
    Go to OPJJ,
    In that select your requirement type, and click details...
    there is a tab,IN/OUTward movement.. In that deselect the box for incl.rel.order.reqs..
    If you dont want the deliveries to be taken into consideration, then uncheck thebox for include deliveries..
    hope this solves..
    karthick

  • Wrong Planned Order dates - MRP Run

    Dear Experts,
    Please guide to resolve the following problem:
    I have uploaded the PIRs for 3 months. When I take the MRP run, the system is scheduling the planned orders for first 2 months only. For the 3rd month's PIR the planned order are created for the PIR dates only. 
    For example, if the PIR (for 3rd month) is maintained on 25th of the month. The planned orders for FG & SFGs are being created for 25th only. While for 2 months the Planned orders are properly scheduled.
    What could be the reason for such behavior.
    The planning horizon is 90 days.
    Regards,
    Rohit.

    Dear Rohit,
    If you are running MRP with NETPL, then the Lead time scheduling will be carried out only for the planning harizon.
    Try executing MRP you can select NETCH key.
    or
    If you want to run MRP with NETPL key, then please give In-house production time in workscheduling view as per the routing values. For example 1 day is the processing time and give the quantity for for 24 hr production. Then the sceduling will be carried out as per this values.
    And change the planning harizon for detailed scheduling in OPU5 transaction.
    Thanks and regards
    Murugesan

Maybe you are looking for