Day wise production order

Hi Gurus,
Can any one please help me down??
Do we have standard SAP report to track on day wise production order status other than COOIS,CO26,CO28 and MD4C.
Regards,
VINODH

Prasobh,
My client needs to track the production order daywise...
1.The operation wise which it has passed during the day.
2.The confirmation quantity on the particular day.
3.WIP in certain workcenters.
He dont want to go for "Z report".He want the standard functionality.
I tried with given transaction and business what not satisfied.
Please help.
Regards,
VINODH

Similar Messages

  • Day wise Production stock

    Hi, I am a SD consultant and looking for the following details,
    I need to develop a report in which I need to show the
    1. daily opening stock,
    2. day wise production stock,
    3. Available stock for the day (this will be step 1 plus step 2)
    4. open order Quantity for the day
    5. Invoice Quantity for the day.
    Please guide me in getting the day wise production stock
    Thanks & Regards,
    AK

    Hi anand,
                 1. daily opening stock,
    2. day wise production stock,
    3. Available stock for the day (this will be step 1 plus step 2)
    4. open order Quantity for the day
    5. Invoice Quantity for the day.
    except the 5th one you can get every thin from stoke overview(MMBE) by changing the layouts.
    Correct me if i am wrong or reward.
    Thank U
    krishna
    Edited by: dr.krishna on Jan 10, 2012 4:13 PM

  • Work center wise production order infomation report

    Hi all,
    i have a requirement that workcenter wise (with date) production order information with quantity details (plan and actual).
    Eg: My production order quantity - 40 nos. (it takes 4 days to finish).
          i have three operation in production order.
          my order scheduled start date - todays date.
    In standard, when enter my first operation work center, system showing production order and its quantity (40 nos) . but i need to split that order quantity in report.. means on todays date for particular production order - order quantity = 10 nos.
    Clent want like that (with quantity break) report..
    Any standard report ???
    If customization.... How it can be mapped in SAP.??
    Thanks in advance

    Hi,
    You can use the FM COIS_SELECT_ORDER_DATA_READ.
    CALL FUNCTION 'COIS_SELECT_ORDER_DATA_READ'
          EXPORTING
            iv_prod_order_sel       = lv_prod_order_sel
            iv_proc_order_sel       = lv_proc_order_sel
            iv_planned_order_sel    = lv_planned_order_sel
            iv_rem_objects_only_sel = lv_rem_objects_only_sel
            is_objects_to_read      = ls_objects_to_read
            it_parameter            = lt_parameter  "General Structure for PARAMETERS and SELECT-OPTIONS
            it_status_hdr           = lt_status_hdr
            it_status_opr           = lt_status_opr
            it_status_cmp           = lt_status_cmp
          TABLES
            ct_ioheader             = lt_ioheader
            ct_ioitem               = lt_ioitem
            ct_iodocl               = lt_iodocl
            ct_ioopdocl             = lt_ioopdocl
            ct_iomamo               = lt_iomamo
            ct_ioconf               = lt_ioconf
            ct_ioopconf             = lt_ioopconf
            ct_iosoconf             = lt_iosoconf
            ct_iogomo               = lt_iogomo
            ct_ioopgomo             = lt_ioopgomo
            ct_iosogomo             = lt_iosogomo
            ct_iogmer               = lt_iogmer
            ct_ioopgmer             = lt_ioopgmer
            ct_iosogmer             = lt_iosogmer
            ct_iosequen             = lt_iosequen
            ct_iooper               = lt_iooper
            ct_iosoper              = lt_iosoper
            ct_ioopcomp             = lt_ioopcomp
            ct_iooppreq             = lt_iooppreq
            ct_iosopreq             = lt_iosopreq
            ct_iooppord             = lt_iooppord
            ct_iosopord             = lt_iosopord
            ct_ioopmst              = lt_ioopmst
            ct_ioopprt              = lt_ioopprt
            ct_ioopcap              = lt_ioopcap
            ct_ioopscap             = lt_ioopscap
            ct_iosocap              = lt_iosocap
            ct_iososcap             = lt_iososcap
            ct_ioopsccf             = lt_ioopsccf
            ct_iososccf             = lt_iososccf
            ct_ioprodlist           = lt_ioprodlist
            ct_iomatver             = lt_iomatver.
    This FM get data from the report used by transaction COOIS. If you needed the header data then you can use lt_ioheader table and seperate the data with the date. If you need at operation basis the you can use lt_iosoper table. You can use this FM to create custom report even with the checks like material availability, PRT availability, capacity requirement etc.
    Thanks and regards,
    Pradip
    Edited by: Pradip Ray on Aug 26, 2009 8:26 AM
    Edited by: Pradip Ray on Aug 26, 2009 8:26 AM
    Edited by: Pradip Ray on Aug 26, 2009 8:26 AM
    Edited by: Pradip Ray on Aug 26, 2009 8:27 AM

  • Branch Wise Production Order

    Hi all,
    If the production is done in 2 units let delhi and Noida....(Production of Item A)
    So Item A is in 2 warehouses Noida and Delhi.
    When we are running MRP wizard and creating Production Orders from MRP wizard ,how we can get that wchich production order is for which Branch.
    We are using Project Code to define Branch but while running MRP there is No option To select Project Code.
    How to solve this problem??
    Thanks,
    Neetu

    Hi Neetu,
    You need to track through ware house.
    In Production Order there  is provision to mention ware house below planned qty.
    Hope this helps...
    BR
    Samir Gandhi

  • Day wise sales Vs Production report - Urgent

    Dear Guru's
    My client require a new report, Material A is producing in plant 1000 and they want to know day wise production Vs day wise sales, week wise production, week wise sales and month wise prodution and month wise sales.. all these in one format so that they take necessary steps.. please provide me some inputs which i need to give to ABAPers, and is there any standard report for these...
    Thanks
    Ramki

    I am sorry Ram Ki, these are client restricted documents and i am not haing authorization to email you.
    Sorry again...I think this is not big job just sit with abaper and search the fields requires for your report from the said tables. You have to design the format in excel and explain the same to abaper... if your abaper is good then he will do this without any problem.
    Regards
    TAJUDDIN

  • CO Profitability report day wise

    Hi Gurus,
    My client wants to see the Profitability report at company code level day wise, Sale order and Product, is it possible.
    If its possible, then how the data will flow day wise and what are the pre-requisits to get this done.
    Does SAP has any standard report to get the required.
    Day wise i mean, if i take the COPA report on 2nd Feb, it should display only the amounts which were posted on 2nd Feb and activites confirmed etc.
    Thanks & Regards,
    Praveen

    Hi All,
    Can you tell me what is Line item report, and how is it different from KE30 summarised report.
    What i understand from your saying is, Line item report will give us the particular dates information when the report is executed, leaving out the info till previous date.
    Even if the line item report is created, can u tell me how the data will flow into it. Because we have Sale order cost estimate for the client. If i create a seperate value field for the cost component then it will give me the Sale order cost estimate info which is again standard. How is it possible to get actual data.
    What about the other cost centers amount. How this data is passed onto it.
    If i have to get this data into the reports then each day I should do Assessment cycles, settlements of the order and reverse the same the next day. But even if i do that i wont be able to get the day wise report as the data will get posted on month end date and again will be summarized one.
    Pls clarify me on this. My clients expectation is to bring out the daily report to see the progress of each day and wats the cost he is incurring so that he can compare it with sterdays and also the plan data.
    Thanks & Regards,
    Praveen

  • Automatic creation of production order form demand

    Dear Gurus,
    In my cycle,
    I want to copy monthly plan from EXCEL sheet through BDC to SAP System.please tell me on which screen it will upload(in md61 or some other).
    After uploading is there any option according to date wise production order should create automatically for each date separate wise.
    Thanks
    Alok

    It will come day wise only if you [split the demand|Re: Automatic splitting of MRP requirements for components] or give the demand in days. Or else while creating the Z program for upload write program in such a way that it will
    1. take the monthly requirement divide the value with no. of working days.
    2. The value got after dividing will be enter evenly for all working days.
    Regards
    Abhijit Gautam

  • Automatic production order creation and confirmation

    Dear all,
    I am in a situation where i have to configure the SAP system in the following ways:
    1. From the planned orders automatically production order should be created today for the next day production and the end user will re-declare the quantity if there are any changes in the production order.
    2. If there are no re declarations to be done SAP should automatically release production order and save it.
    3. After the goods are produced the confirmation of the order should happen automatically from the measuring points.
    4. In the order confirmation, the storage location for goods issue should be automatically captured from the goods issue slip.
    5.After the confirmation of the order the goods receipt should happen automatically.
    Please suggest me whether these are possible in SAP or not.  If yes please tell me the procedure.

    HI,
    I hope this will give you the clear picture
    actually my scenario is:
    Finished good= x
    work centers involved = WC1, WC2.
    HERE BOTH THE WORK CENTERS ARE IDENTICAL, INPUTS ARE SAME AND OUTPUT IS THE FINISHED GOOD "X"  FOR BOTH THE WORK CENTERS.
    I HAVE A ROUTING FOR THE FINISHED GOOD "X" WITH TWO GROUP COUNTERS AS (1)WC1 AND (2) WC2
    When i create plan in md61 for 1 month and when i do mrp run in md02 it will create the planned orders and we can see the stock requirements in md04 and when we double click on the planned order we can convert them into production orders.
    But my users requirement is, he want to run the mrp in md01 and after that automatically each day the production order should be created.
    example with the above work centers and materials:-
    i have done the mrp run for "x" for November and December months
    i want to produce "x" of 200 kg on 30.11.2011.
    so SAP should generate production order for WC1 AS 100KG AND WC2 AS 100KG on 29.11.2011 at 5 pm automatically  and the user will release the order.
    similar example:-
    i have done the mrp run for "x" for November and December months
    i want to produce "x" of 400 kg on 03.12.2011.
    so SAP should generate production order FOR WC1 AS 200KG AND WC2 AS 200KG on 02.12.2011 at 5 pm automatically and the user will release the order.
    Please suggest me how to do the configure settings for my users requirement.
    Thanks,
    Aravind.C

  • Mtl Availability Problem @ Production Order Release

    Hello All,
    For production order creation and order release we have different types of availability checks:
    1: Order creation: check all purchase orders (ZP02)
    2: Order release: do not take purchase orders into account (ZV02)
    In the material master the field "availability check" is always set to 02.
    The problem with this is that as soon as we want to release a production order, the future purchase orders are not taken into account, but the corresponding production orders (created ones) are. This yields missing parts at release, even though there is enough in stock.
    The following options are now selected for ZV02:
    [ ] incl. purchase orders
    [ ] incl. purchase reqs
    [V] incl. dependent reqs
    [V] incl. reservations
    [V] incl. sales reqmts
    [V] incl. deliveries
    [ ] incl. ship notific.
    incl depend reservat [x] all
    incl rel order reqs [ ] do not check
    incl planned orders [ ] do not check
    incl production orders [x] all
    I tried changing OPPJ. Things that do not work or are unwanted are:
    changing ZP02 identical to ZV02, since purchase orders should be included for orders in the future
    changing ZV02 identical to ZP02, since purchase orders confirmed to today might be delivered tomorrow, which would yield missing parts.
    changing ZV02, incl. Production orders from [x] to [F]. Still missing parts @ release.
    Thanks in advance.
    Regards,
    Marc

    Hello
    I assume here that 02 is for the component in the production order, am I right ?
    All components have the material availability at 02, so you are right.
    Now in 02-ZV02 , the you are considering all the reqmts coming from planned or production orders, is that right ?
    Yes, both planned and production orders are checked in ZV02 and ZP02.
    Is ZP02 working according to what you need ?
    ZP02 is used @ order creation. This works fine, because it takes purchase orders into account that are confirmed in the future. This is correct at order creation.
    Cna you check the differences between both rules ?
    Purchase orders are not taken into account for ZV02
    Purchase orders are taken into account for ZP02.
    The rest is identical to the previous list
    An example:
    Day 0 (current stock): 200 of material X
    Day 1: Production order requires 200 material X
    Day 2: Purchase order is confirmed for 200 material X
    Day 3: Production order requires 200 material X
    Result of ZP02: in stock: 200, required 200 + 200, confirmed @ day 2: 200 --> No missing Part
    Result of ZV02: in stock: 200, required 200 + 200 --> Missing Part
    The best solution would be for the system not to look at the requirements of the orders in the future which are not released yet. Therefore I changed the key ZV02: incl. Production orders from [x] to [F]. However, this did not have any effect!
    Regards,
    marc.

  • Reg :Production order cost  report day wise.

    Dear Expert,
    1.We want a report for a particular Production order cost  day wise.
    The scenario is like this Production order is Released for 100 Qty.
    Today they confirmed only 50 Qty.
    Tomorrow they will confirm 50 qty.
    Now they want to see the cost for today confirmation and tomorrows confirmation.
    Reason being daily the Raw Material cost is changed and they want to track the variance.
    Is there any standard report we can achieve this or do we have go for development
    2. And also i need to know daily how many production orders have been released.
    Thank u in advance.

    A day is not a controlled cost object. You could write a report to look at costs gathered in a day (by reporting date), but I strongly suggest that if you need to analyze costs per day you switch to daily orders.
    You'll find then that all the standard processes work for you.

  • Production order wise report  of  all component.

    dear all
    I want production order wise report  of  all component.
    1) quantity required 2)issue quantity3)currect stock
    I got  quantity required and issue quantity field in co24 but i didnt get currect stock field(unrestricted stock) in that t-code
    Is any t-code is available ?
    rgds
    Surendra

    Hy Surendra,
    In any of the standard SAP reports you will not find the Goods Movements of Particular order along with available Component stock.
    Goods movements report of the Production / Process order is static report once the order is close.While Stock report is variable report and may be change Time to Time.
    I think if you wish such kind of report then you have to go for Z reorts.
    You can find all the Goods Movements of Order in COOISPI/COOIS/IW3M but there is not available stock report.
    Regards,
    Dhaval

  • How to get Operation wise Time for a list of Production Orders

    Dear Sir,
    We have a list of Production Orders numbers and need to know the operation wise time duration for these production orers (off course the desired time is same as mentioned in the routing for the relevant component)
    Kindly guide us as how can we get these timing details .
    Rgds
    Sonia agarwal

    Sonia,
    I hope your are refering to setup time, process time, teardown time in the production order.
    use report COOIS for it.
    In the 'List choose operation.
    Give input for the production orders in the slection scren. Execute.
    In the report select the columns as per your requirement.
    Hope this helps you.
    SmanS

  • How to get open production orders by plant wise

    Hi,
    How to get open production orders by plant wise.
    i know from tcode COOIS, is it possible to get from this. if so what are the parameters we have to give to get open production orders by plant wise.
    is there any tcode or tables available , please provide details .
    regards,
    Hari priya

    Hi,
    What is your definition of Open Production Orders?
    Definetly you will get the report from COOIS for Plant wise.
    Whther you want to consider all the Orders having the Status REL but not DLV?
    Then there is a chance of having the Orders, still with PDLV status but GR is done for the full Qty. May be you don't want to consider the TECO status, eventhough the Order is short closed??
    Better to ommit the Orders with CRTD status also..
    So, based on this which status to consider and which status not to consider..
    You can define the "Selection profile status" in BS42.
    Use this selection profile in COOIS, so that the rsults will be accurate..
    Best Regards,
    Siva

  • Report to view Production order wise atcual cost when PO is assigned to PCC

    Hi All,
    Can anyone help me to get the report for production order wise actual cost incurred when that Production order is assigned to PCC (Product cost collector).
    Is it possible through Summarization hierarchy or Product drilldown?
    If yes, can u explain the steps.
    Regards,
    Durga.

    Hi Bhaskar
    You are in Alaska and you wanna eat vegetarian food
    You cant get values at Prod order level if you have chosen PCC as cost object.... You will only get Qty at Prod order level
    To get a bird's eye view of costs incurred in PCC, execute report MCRY with PCC as the input...  MCRX shows only Qty info for components
    br, Ajay M

  • How to get Production Order wise Actual Values

    Dear CO Experts,
    How to get Actual Values (Raw Material Issue, Activity Confirmations & OH Calculations & Goods Receipts from Production) each Production Order wise ?
    My Scenario is Product Cost Collectors (PCC)  with Production Orders.
    If we select above scenario Production Order is Statistical and PCC is real cost object.
    For PCC is Period wise we can track the cost Periodically in individual Material.
    But my client is asking how to see the each Production Order wise Actual values. Is there any T.Code ??
    In Production Order I am able to see only Plan values (CO03).
    Waiting for your favorable reply.
    Regards,
    KBR.

    Hi Bhaskar
    You are in Alaska and you wanna eat vegetarian food
    You cant get values at Prod order level if you have chosen PCC as cost object.... You will only get Qty at Prod order level
    To get a bird's eye view of costs incurred in PCC, execute report MCRY with PCC as the input...  MCRX shows only Qty info for components
    br, Ajay M

Maybe you are looking for

  • Cannot select the calendar in a Oracle application. See detail section for error message

    Getting the following error TMGeckoAgent.prototype.getElementPosition=function(_586){ var _587=_586.ownerDocument; var _588=_587.getBoxObjectFor(_586); var _589=_588.screenY; var _58a=_588.screenX; _588=_587.getBoxObjectFor(_587.documentElement); _58

  • Third party softsynths with LE8

    Hello I thinking about purchasing native instrument's Absynth 4 to work with LE8 but I've heard that it causes a lot of crashes and is a big cpu eater? Anyone used it with logic express 8? if so how does it fair up? Does it take up a lot of space as

  • Lightroom 2 and Windows 7 Home Premium 64 bit Compatibility

    I just got a new laptop with Vista Home Premium 64 and a free upgrade to Win 7 Home Premium 64 bit, coming soon. Is LR 2 compatible with Win 7 64 bit?

  • Adobe interactive forms for VA01

    I'm looking for a list of all Adobe interactive forms that are available for ECC Enh4... we are looking to create an adobe template for SAP transaction VA01 (Create Sales Order). I've looked at table FPLAYOUT but the form names are very cryptic. Than

  • My 4th Generation Ipod keeps shutting down

    THe ipod will play about 6 songs and then stops. I have to shut it off for a day before it will work again. THen it will only again play about 6-7 songs and then shut down. Has anyone else had this problem and how did you fix it????