Define Measurement Method as Default in Progress Analysis

Hi All,
I have defined Measurement Method 0000000003(Milestone) in progress analysis for my company code.
But while running CNE1 for my project it is not picking the measurement method i have defined for my company code but it is picking the 0-100 Method .
Please advice.
Muzamil

Hello All,
I have read all the posts on the subject, we are facing the same problem as reported by Muzamil. I have done the follwing
1. Creat Progress Version
2. Define Measurement Method as Default Values
     2.1. Define measurement methods for WEBE
     2.2. Ddfine measurement methods for all activity types
3. Assign progress versions to the WBS Elements and Activities in their progress tabs.
But, wen I run CNE1, SAP does not pic the default methods while analyzing progress. SAP uses 0-100 method, which is not right.
Please propose some solution
Regards,
Murtaza

Similar Messages

  • PROGRESS ANALYSIS: what does COST PROPORTIONAL measurement method use for?

    Hi Experts,
    When I tried to use the COST PROPORTIONAL measurement method, I found 1 thing:
    + actual POC = actual cost / overall value
    + BCWP = actual POC x overall value
    It means that BCWP = ACWP (actual cost) --> Cost Variance (CV) = BCWP - ACWP = 0
    Hence we cannot see the cost variance when we apply the COST PROPORTIONAL method.
    Could you please help me to explain the use of COST PROPORTIONAL method?
    Thanks and best regards,
    Khoa Huynh

    Hi Abdul Khader,
    Thanks for your answer. I got your point.
    But can you explain more about "Cost proportional measurement method is suitable for work packages where costs and services have a constant relationship"
    Thanks a lot,
    Khoa Huynh

  • Estimation method of progress Analysis

    Hi,
    We are having following scenario.
    We are creating the project in PS. Then creating the PM order & assigning
    the order to WBS element.
    We want to use the Estimation method of progress analysis. Hence we havedefined Estimation method as default measurement method (both plan &
    actual )for following objects,
    1. WBS element
    2. Internal processed activity
    3. External processed activity
    4. General cost activity
    5. Order (Other than Network)
    For WBS element & all activities we are able to manually maintain planned
    POC & actual POC in CJ20n.
    But for PM order we are not able to manually maintain planned POC &
    Actual POC.
    Can you please let me know where we can manually maintain the planned &
    actual POC for PM Order.
    regards,
    Pradip Shelke

    /@#$%%%%@ wrote:
    > Can you please let me know where we can manually maintain the planned &
    > actual POC for PM Order.
    I do not think it is possible for order to use estimation method..
    Please go for Cost / Time / Work proportional

  • Default report display for Project Info System: Progress Analysis Report

    T-Code: CNE5
    At the Progress Analysis Initial Screen, I chose the fields from the menu Views > Choose Fields, Then I saved the Variants as Test_Variant ( GoTo > Variants > Save Variants )
    Every time I run the report, it will run the Test_variant but once I logout and login again to run CNE5  Test_variant will not be used.
    Can I set the default variant, so that every time I logout and login and run the Progress Analysis(cne5), Test_variant will be used as default.
    Appreciate advise
    Thanks.

    If you want the same variant should default to all the users then you can assign the variant in SE93 to transaction CNE5. write your variant there-->save.
    Other option is to look at possibility of creating screen variant using transaction SHD0 for CNE5. Take help of ABAP in this case.
    Regards
    Nitin

  • Progess Measurement method determination error.

    Hi Experts
    I have maintained default measurement method for project object types (WBS, NWA) in customizing.
    But still, the method 0-100 is defaulted.
    Is it essential to maintain the project version for all the project objects manually?
    Is there any setting to default the project version for project objects?
    warm regards
    ramSiva

    Hi,
    Create a Template(Std project) and default the Progress version and Measurement Method  and create operative projects from this template so that Progress version and Measurement Methods will come automatically.
    Also you can create your new operative projects with reference to some other operative project where you have maintained the version and the measurement methods.
    Muzamil

  • Progress analysis scenario

    Can some one help me with a sample scnario for Progress Analysis which can help in understanding what events will lead to Cost Variance or schedule Variance and will give me EAC, ETC etc.
    I have all the settings done for progress analysis, but I am getting same values for BCWP & ACWP.
    Also, how is Plan POC related to schedule/duration/period of the activity?
    Regards,
    VDS

    Dear Rupesh,
    please have a look at the SAP online documentation following this link:
    http://help.sap.com/saphelp_erp60/helpdata/en/b4/ba853488601e33e10000009b38f83b/frameset.htm
    Project Progress -> Progress Analysis:
    There you can find a list with the relevant KPI's, formulas and questions they will help to answer.
    Project Progress -> Progress Analysis Progress:
    There you can find a short scenario with a diagramm which explains the cost variance and schedule variance.
    The relation of the POC calculation to values like schedule/duration/period is depending on the measurement method which is used, as every measurement method uses different values as basis for the calculation. So a general answer can't be given on that.
    Kind regards,
    Dirk

  • Comparing Progress analysis data saved in past periods

    Hi forum team,
    We are using PS in SAP R3 ECC 6.0 system
    With the intention to reviwe at later stage, we had saved 'Progress
    Analysis' report data (CNSE5)in 'Other selected version' in past periods
    i.e.in July, August etc.When we open these reports in November all its
    fields (Adj/Nonadj/Agg/Non Agg/PlanPOC/ActualPOC....) except actual
    cost shows current period (November) values.
    We thought this version copy would be a sort of screen shot but now it appears as a dynamic report.
    How can we save this report (cnse5) in ERP database as we save project version for comparision in future?
    Please suggest.
    Thanks,
    Mohan Parab

    Hi
    The standard method is KKA8. But you need to reverse the settlement.
    Or you should be able to delete  the data from RPSCO with Value type 32.
    But once you delete, you will be running the RA again for the last 10 Years? If so will you be settling it again? In that case how do you reconcile this with FI-CO and PA?
    Thanks
    psconsultant

  • SKF for Progress Analysis

    Hi,
    I have successfully run progress analysis using Estimate method .  As my understanding after I run CNE1, system will record POC that I maintained in Estimate table into SKF.   Which report I can use to see this SKF value ?
    I have checked all SKF report in PS and even in Cost Center Accounting,  but the report has no data.

    Hi,
    Did you check the report CNE5???
    Once you run CNE1 accordingly reports on CNE5 will update.
    Regards,
    SL

  • WebDynpro method tab - defining a method

    Hi all ,
    I 'am trying to define a method in Method's  tab . but I can't do correctly the type "returning"
    I define parameter , type = returning asociate type I and default = 1.
    When I try to change the state of the parameter.  Syntax error throws " The field x  cannot be changed"
    anybody can help me ?? with this ?
    thanks in advance,

    >
    nishant patel wrote:
    > Hi,
    > I want to create my own method in Web dynpro with importingand exporting  parameter as a table is it possible to do?
    > If yes how can it be done.
    >
    >
    > Thanks,
    > Nishant
    Most certainly.  Just go to the methods tab of the component controller or the View.  You can create a method there.  Double click on the method to bring up the method editor. Above the ABAP editor is a table where you can input exporting or importing parameters.  Supply a parameter type that is a table type ( data dictionary table type) as you can use the "TABLE OF" statement within the Associated Type column.

  • How to view the results of progress analysis

    Dear Experts,
    I executed progress analysis for my project analysis in CNE1 for my project.
    After execution, PA has been completed for two WBS elements. But iam not able to see any POC values or costs.
    Where should I check and confirm that Progress analysis has been carried out successfully.
    Pls suggest.

    Hi,
    Run the transactio CNE5 for the project progress analysis ,you will get the following reports.
    The standard reports offer various values we can use to assess the progress of our project. The following fields are defined in the standard progress analysis reports:
    - Planned POC in percent
    - Actual POC in percent
    - Budget Cost of Work Schedule, BCWS
    - Budget Cost of Work Performed, BCWP
    - Cost variance (CV)
    - Schedule variance (SV)
    - Value index (CPI)
    - Estimated costs at completion (EAC)
    Regards,
    Raj

  • Syntax error in Define entitytype method in MPC class.

    Hi,
    I am trying to create Odata service by creating new entity type and entity set at service level creation itself (Data model-->Create). Now at the time of generation of classes I am getting syntax error fields are not defined in method, Define Entitytype of MPC class. Could you guide me on how I can generate classes here.
    Br,
    Venkat Konanki.

    Hi,
    I am trying to create Odata service by creating new entity type and entity set at service level creation itself (Data model-->Create). Now at the time of generation of classes I am getting syntax error fields are not defined in method, Define Entitytype of MPC class. Could you guide me on how I can generate classes here.
    Br,
    Venkat Konanki.

  • ICR Contact persons details- Communication method  by default set as Remote

    While maintaining  Contact person  details through FBRC010. The communication method  by default it is picking up as
    Remote mail, it is same in user profile also,  with this setting when we tried to send the mail using template   through
    FBICR3 or FBICR1. mails are not going to the  intended user.
    When we changed the user profile from Remote mail to  Email,  mails are going,   But i understood that from ECC6 onwards
    the mail type in user profile should be kept as Remote mail. if we change it to  Email, our concern is  users might not get
    mails from other source.
    Is there any way to come out this situation please.
    Thanks
    Ganapathi.

    Hello Ganapathi,
    ICR simply uses SAPOffice standard functionality. Details about sending options would have to be answered by a basis communication expert. I'm glad you were able to find a workaround but if you would like to have a different solution you may want to ask somewhere else...
    Ralph

  • Exception '1250' is not defined for method 'CREATE' object type 'MESSAGE'

    Dear experts,
    I set up the document distribution (SWU3, backgroundjob SMTP, activated the workflows, flagged the linkages, etc). Now, I have still a error:
    Exception '1250' is not defined for method 'CREATE' object type 'MESSAGE'
    Does anyone know what the cause of exception 1250 could be?
    Thanks in advance and kind regards,
    Samuel

    hi,
    SAP ITS is SAP Internet Transaction Server which provides connection between SAP ERP system and html client.
    Check with bassis, i think TCP/IP or work station application not configured yet. i guess?
    Benakaraja
    ??P

  • Exception '1003' is not defined for method 'SENDTASKDESCRIPTION' object type 'SELFITEM'

    Hi All,
    Please help me in this. I am trying to send a mail when user rejected the item in his inbox. I am getting error like
    Exception '1003' is not defined for method 'SENDTASKDESCRIPTION' object type 'SELFITEM'. I tried so  many ways like no attachments,send express ,siganture,encryption all disabled but still the same error from user outbox who ever rejects it.
    Regards,
    Madhu.

    Hi Madhu,
    This exception is raised means you have checked the Signature check-box  and encrypt check box.
    Now you have unchecked that the issue should be solved , but if it is still giving the same exception synchronize your run time buffer using the t-code SWU_OBUF .
    Let me know if the issue is still there.
    Regards
    Bikas

  • PS Progress Analysis -

    Dear Guru's,
    I am facing problem while executing the Progress Analysis report in SAP PS for one of our client. I am getting only the Schedule plan value and actual... rest of the column like BCWS, ACWS are comming blank which is important for client.
    If any body work on customer project pls suggest..
    Regards,
    Rupesh Kumar Singh

    Hi Shashank,
    Right now I'm facing the same problem, I've already implement the user exit but I would like to know if you have an example of the implementation, I still don't know where to find the info of the structures to calculate the POC.
    Thanks,
    Héctor

Maybe you are looking for

  • How can I make Acrobat save the scale (e.g. 1:50) when I save a document?

    Hello, I have a document (a house plan) whose scale is 1:50. I regularly need to load up this document and take measurements off it, using the Measuring Tool. But each time I load it up, the scale is reset to 1:1, so I have to right-click and reset i

  • Phone number appearing in Favorites list but does not exist in Contacts

    I have an iPhone 4S, running iOS 5.1.1 (9B206). About two weeks ago (not really sure when I noticed) a phone number appeared at the bottom of my Favorites list. The number is for a person that I deleted from Contacts some months ago. The number is no

  • Screen Saver Built in Pictures are Low Res

    I just purchased this 30" Cinema Display. Really like it a lot. I wanted to use the Beach or Forest screen saver. All the pictures are low res. Is there a way to get HD picts to replace those for a great looking screen saver. The originals are very g

  • Different number of document impact

    Dear All, when running check document numbering --> sales order, I've got missing list of some numbers of the sales order documents in the document serial numbering lists window. What would be the effect of this result ? Edu

  • Typing French Accents

    How do I type french accents? Do you use some sort of code like with a windows computer? Any help would be greatly apprectiated. Thanks