Deliveries through project

Hi,
We have a customer project where we have hunderds of BOMs to be delivered through project. We will be using results analysis for calculating WIP and project profitability.
What are the options that I have,  to do the deliveries through the project.
1. Can I use the networks alone to manage the BOMs and deliver them?
2. Should I use production orders and bring the sub-assemblies as project stock and then deliver from the project ?
I appreciate some discussion on to how to go about this requirement.
Thanks,
Manohar

Hi Rakesh,
Thank you for your reply.
I need one clarification , though.
1. We want to generate material requirements for purchasing raw materials by creating reservations in one of the wbss and then run MRP to generate PRs. The PRs will be procured to plant stock and then issued for production orders as generated below.
2. We will be doing PS BOM transfer or some other means of uploading BOM assemblies to network activities in some other wbss.( for production and not for purchasing). These reservations should be created with negative quantity so that they will be produced and not procured.  (When we run PP-MRP , these reservations will be converted to production orders via planned orders).
When the sub-assemblies are delivered to project stock via production orders , we want to deliver them through the project.
Please review and comment whether the above processes will work as outlined above.
The reservations which are created in poitn 1 above , will remain as such. I am not sure about how to get rid of them ? Please comment.
Thanks,
Manohar

Similar Messages

  • Automatic Asset creation through Project settlement

    Dear All,
    We have one issues where in AS02 AUC Asset quantity is in display mode still we can find the quantity there.
    Can any body help me about the Process of Auto Asset creation through Project settlement.
    I need to know how system calculate the Quantity from the Project settlement. if such type of Process exist in SAP
    Thanks
    Abhijeet
    Edited by: Abhijeet  Patil on Oct 5, 2011 3:05 PM
    Edited by: Abhijeet  Patil on Oct 5, 2011 3:05 PM

    Hi,
    There is process in SAP where we can create AuC from Projects. We need to have an investement profile set up and the same needs to be used in the project. You will have the details in SAP Help documnetation for this.
    Regards
    Sreekanth

  • Creation of maintenance order directly through project.

    Hi,
    Is it possible to create maintenance order directly through project while creating network activity?
    Please let me know if it is possible and how.
    Thanks,
    Nilesh

    Hi Abdul,
    Thanks for your reply.
    Can you please elaborate few details on DIPM.
    Thanks,
    Nilesh.

  • Stock transfer purchase requisition through project builder

    Hi Friend's,
    For transfering material from one plant to another plant we have to create stock transfer purchase requisition through project builder.
    Can is it possible to create stock transfer purchase requisition through project builder which will have account assignment category as Q & item category U.
    Thanks & Regards,
    Sandeep

    Hi Sam,
    Thanx for your input.
    We are dealing with project specific stocks & customer project scenario.
    My requirement is that we having 2 plants. Projects are created in 1001 plant, same plant does the mfg. of FG items required for projects & 1002 plant manufactures MTS items which are required to mfg. project FG items as well as same items will bring into 1001 plant and then delivered to customer.
    Here my clients want to create stock transfer pr through project builder to bring MTS items from 1002 plant to 1001 plant & then delivered to customer.
    I think as you said this is not possible in std. sap to create stock transfer pr through project builder.
    Thanx & Regards,
    Sandeep
    Edited by: Sandeep Theurkar on Mar 23, 2011 7:11 PM

  • Can we change budget status through project setup system status window?

    Hi Experts,
    Can we change budget status through project statuses window?
    Thanks

    Hi
    Project statuses window will only deal with the status of the project, not the status of the budget.
    Dina

  • PS - GR of finished product through project

    Dear all,
    How to do GR of finished product through project, pl. tell movement type also.
    Regards,
    Ravi

    Hi,
    For FG through MB1A with movement type 221 you can do the GI from plant stock to project stock. Project stock FG will get updated.
    Regards,

  • DElivery through Project

    hi all
    at the time creating delivery through project tcode : CNS0, i am getting following error please help to resove this 
    Document is incomplete: You cannot save the delivery
    Message no. VU013
    Diagnosis
    When the system checked whether saving delivery was permitted, it determined that the requirements stored in Define Incompletion Procedures for this document do not allow this subsequent function.
    System Response
    The system does not permit this subsequent function.
    Procedure
    If this message appears during online processing, you can edit the document by choosing Edit -> Log of incomplete items.
    If the message appeared during background processing, you can analyze the problem by regenerating the delivery

    closing thread

  • Hi, when trimming a project through project manager I get blue lines and the video is missing. I'm using PP CC 2014. Why is this?

    I have tried through Project manager to save a "Trimmed Project" but when I open up the trimmed project some video is missing or is the wrong video and on the timeline these missing videos have a diagonal blue line. Any idea on why this is happening would be greatly appreciated.

    Is this a Mac?  If so what version of OSX?

  • AUC through Project System

    Dear memebers,
    Could you give the details how to configure Asset Under Construction through Project System Module.
    Looking forward for an reply and positive reply.
    Thanks & Regards
    Kumar

    Hi,
    You have to link an asset to WBS.
    Set settlement profile for the WBS to allow to settle the costs to assets.
    Define settlement rule for the WBS.
    Post costs on WBS.
    Execute settlement of the costs.
    Regards,
    Eli

  • Generating a production order through projects, without MRP run?

    Hi to all
    Is it possible to generate planned orders and further proceed to production order through projects  WITHOUT MRP run?
    Regards
    surya

    create the production order in CO01 and assign WBS element in the assignment tab of the order.
    whether it ll solve ur purpose....
    ashis

  • Creation of  Inbound Deliveries through IDOC

    Hello All,
    I have a scenario wherein through SPRO the configuration has been set to throw an error message in case a new delivery is getting created through VL31N and the total quantity of the inbound deliveries created till now(including the one getting created now) exceeds the PO quantity , but the same is not applicable for deliveries created through IDOC.
    For example : I have a PO with order quantity of 2pc's
    I create 2 inbound deliveries each of quantity 1 . Now if i try to create a new inbound delivery through VL31N system throws a error message.
    But through an IDOC i am able to create any number of deliveries though the total of all the inbound deliveries exceeds the order quantity in PO.
    Is there any way that the same SPRO setting can be made active for Inbound deliveries created through IDOC also.
    Helpful answers would definitely be rewarded.
    Thanks in Advance,
    Sowmya.

    IDocs and BAPIs sometimes behave differently than transactions. You might need to add a user exit specifically for IDoc processing. Otherwise send a message to SAP and have them look at it.

  • Creation of Production order for FInished Product through Project

    Hi,
    Pls clear me on how we can create a Production Order for finished product.  
    If we confirm the production orders in PP, cant the same be confirmed in PS.. Should we consider the same activity types in both PS and PP
    Pls clarify

    hi srikanth,
    your answer has been very helpful... but could u clarify  why MRP is run in MD51 for WBS element and in MD02 for network..
    Pls clarify...  My scenario is like this ...                                                                               
    A
                            B                                                                                C
                    D  E F G H I                                                                                J K L M N O
    I have  a Assemblies B and C which are always delivered in sets.. under assemblies B and C,  we have 6 sub assemblies which has its own components.  I am assigning sub assemblies to differenet WBS elements 01 and 02. so, initially these sub-assemblies are produced to stock. this should happen in PP i.e., through production orders generated in MRP run ( MD51 ). In the next phase i will assign Assemblies B and C to another WBS element.  Again system should generate two Production orders thru MRP for this. Here the 6 sub-assemblies produced earlier will be consumed in confirmation of the production order...
    What i am doing is this correct...
    and the procurement for the components is happening thru the purchase requisition generated via MRP. the components themselves are not directly assigned to the project..
    Pls advise and clarify?

  • Sub-contracting through Project system.

    Hi
    Can some one please help me in understanding how Project system (PS) is supporting sub-contracting scenarios.
    I am looking for activity sub-contracting and also sub-contracting with Project stock materials.
    I am aware of normal sub-contracting through production order and also sub-contracting through MM. I am specifically looking for sub-contracting in PS.
    Thanks and warm regards,
    Jagadeesh

    Hi,
    If requirements for subcontract items (or services) are generated automatically from PS just make sure that the right document category is used (subcontract) then any requisitions or planned orders etc. will have the right category.
    There is no difference between PP, PS and PM effectively, they all use subcontracting in the same way it is just how the requirement is triggered that is slightly different.
    If you need details on how to trigger the right type of requirement through PS then you may need to use one of teh financial forums that cover PS? (is there one?)
    Steve B

  • Raise the PR through project with unknown item category "U"

    HI,
    In my business process, i have raised the PR's through the projects. at the time of material assignment we need to give the item category N or L  .But at the time of material assignment to the activity,whether third party sale or local sale is not decide .it's only  decide at the time of PO creation .is there any options or configuration process to assign the unknown item category at the material assignment the PROJECT?
    Regards
    Bhavani

    Item category available is either N or L. I don't think there is any U available.
    If you are referring account assignment in PR. for project it should Q, P or N. U is not for project.
    What is the purpose of assigning / planning materials in your project during the initial stage?, is it for cost planning? if it is only for cost planning then follow what Virendra has recommended.
    Please also read sap help on Material in Projects.

  • Changing project settings mid way through project?

    Hi guys, I've just created some plain text (with black background) for the credits in my film, however when played back on a dvd player, the text is broken and has vertical lines running through it (best way I can explain it - hope it makes sense).
    I read on the forums that my current projects compression (DV PAL) is probably causing this and if I "change your sequence settings to Uncompressed 10bit and do an export of the final show for delivery. The text and any graphics should look much better"
    Is this true? Will this not mess up my project i.e. editing points etc? Will this also improve overall project quality?
    Thanks. T
    p.s. I don't want to use BORIS as this is not an option

    Is this a title crawl? If so, you might do better by creating a separate sequence with just the crawl and set the field dominance for this sequence to none, export this sequence with sequence settings and edit this clip into your complete show.
    If it's not a title crawl and you're doing any vertical repositioning, make sure that the vertical coordinate is an even number (2, 4, 6 not 1, 3, or 5, and so on).
    Although you may have a slight improvement in quality changing your sequence settings, I doubt you'll see much of a difference. To be sure you're not screwing anything up, duplicate your sequence before changing the sequence settings.

Maybe you are looking for

  • I can´t get @ to work at my new Mac mini

    Hi I just bought and installed everything on my new Mac Mini 2012 from my old iMac and I chose Swedish as my language. My OS is Mavericks I also connected my apple keyboard and everything works OK. Except that when I try to write a e-mail. I can´t wr

  • Why does my webcam transmit fine in html5 in Chrome, but not in Firefox?

    On every website I try, Firefox does not support getusermedia, so I cannot transmit audio and video data from my Windows 8.1 tablet in html5. Thus, I cannot use Firefox Hello. I have tried tinkering with numerous settings in about:config, but nothing

  • Number of decimals in the stock, availability tab.

    Hi, Dose anybody know if it is possible to change the number of decimals that appear in the availability tab, in the stock. It appears 3 decimals (as is defined in the data type). any clue??? thanks for your attention best regards. Jorge Vigo

  • Start screen tile

    Hi all, I am running out of idea about a problem I have. I am migrating a computer from Windows 7 SP1 to Windows 8.1 Update using ConfigMgr 2012 R2 and USMT 6.3. During the deployment of any Windows 8.1 Update image I am forcing the Start Screen disp

  • Help: Resizing an image in camera raw

    I'm trying to resize a raw photo to 8.5 x 11 inches (2550x3300px) at 300 ppi in camera raw.  After I resize it changes itself to 2186x3300px at 300ppi.  Is there a way to make it 2550px?