Hi,
   I have create the PO account assigned to cost centre K and it has multiple account assignment.
The distribution is on the basis of quantity and in case of partial invoice it is to be distributed proportionally.
The pricing condition in PO are basic price and freight condition. When I am saving PO the sytem is giving following warning message:
No delivery costs can be posted in case of multiple account assignment
Message no. 06356.
I saved the PO and did GR.As it is multiple account assignment so GR will be non valuated hence no accounting document is generated.
When I am doing MIRO, I selected option goods/service+planned delivery cost.
System is not showing the delivery cost. My basic price was 100 and freight cost was 10 say as an example. In MIRO it is showing only 100 not the freight cost 10 though I have selected the goods/service+planned delivery cost.
When I am simulating the system is showing following warning message:
No delivery costs selected for invoice document
Message no. M8599
Diagnosis
No delivery costs were selected for the invoice document.
Procedure
If delivery costs are contained in the invoice, check that the allocation criteria and invoice type are correct.
Just to check further , in MIRO I selected only the planned delivery cost , then system is giving the following error message:
No delivery costs exist for purchase order 4500000596 00000
Message no. M8014
Diagnosis
You have chosen Delivery costs -> Planned -> By purchase order. This function allows you to process delivery costs which were planned in the puchase order. The purchase order which you are currently processing does not contain any planned delivery costs.
Procedure
Check the purchase order number. If it is correct, you can only post the delivery costs as unplanned delivery costs.
Please help how in the case of multiple account assigned PO we can post the delivery cost in MIRO?

Hello, Anju,
the systems does (well, in this case does not) exactly what is says: "No delivery costs can be posted in case of multiple account assignment".
So either you have to split the one items with multiple account assignment into more items with single account assignment, or you have to use unplanned delivery cost in invoice verification.
If you decide to use the unplanned cost, it can be helpful to activate the "Edit PO Supplement Text in Invoice Verification" function in customizing for LIV, so the buyer can write into defined text in PO "message" for invoicing clerk, that he/she agrees with certain amount of unplanned cost. I know, it's such lousy workaround...
Kind Regards
TomT

Similar Messages

  • Tax code error while posting Planned delivery costs in Import Scenario

    Hi!!!!!
    I am getting on error while posting Planned delivery costs in MIRO for Import Purchase Order with zero value tax code v0. The error is
    "Tax code V0 country IN does not exist in procedure ZAXINN"
    For Import I defined a pricing procedure which contains all condition types for CVD, Ecess, SEcess, Additional Customs Duty and Others.
    While making Import PO im putting V0 tax code. I assigned the Tax Codes to the Company code.
    Please let me know what config is missing.
    Regards,
    Durga

    Is you ZAXINN assigned to the country India
    and is your taxcode (created in FTXP) created for country India?
    kr
    hakan

  • Handling delivery costs conditions in PO

    Hi,
    I need the suggestion and help on one of the issues related with the delivery cost type of conditions in PO.
    We have couple of header conditions which have been defined as delivery cost conditions in m/06.
    We enter these conditions at the time of PO creation.Then GR is done wrt to the PO.The idea is that all these conditions are to be loaded on material at the time of GR(Vendor GR is ticked as 2)
    Somtimes it happens that user realizes that he has made mistake in PO in delivery costs and want to change them.Thus he cancels the GR.
    However, once GR is cancelled he is not able to make any changes in the PO conditions being delivery costs.
    SAP does not allow it.
    But I want to make changes in the header conditions since they were wrongly entered.
    What is the way out for this.I have not found any solution for this.
    I can make these conditions as freight conditions(checking the freight tick for the conditions instead of delivery cost)and it allows me to change them even after GR is done or cancelled.
    However at the time of MIRO I can not have them so that becomes problem.
    Request you to suggest me the solution for this.
    Thanks in advance
    Regards,
    manOO

    Hi Rajesh,
    Thanks for the valuable feedback.
    I went through the notes but as usual I found them confusing.
    Anyways,what is the alternative in this case because I need to add the conditions as delivery costs while creation of PO as header condition and it's likely that rarely I may require to delete/change /add them after GR/Cancellation before Invoice posting.
    Why can not I change the delivery costs after GR or cancellation is not yet understood by me.
    One side of the coin I could understand that that it may lead to imbalance if invoice is also posted but what if invoice is not posted and user wants to correct his mistake which he realizes after GR has done.
    Any suggesttionyou would like to make her to solve the issue ?
    Thanks in advance
    Regards,
    manOO

  • Delivery Cost for Free Goods

    Dear SAP Guru,
    I need some advice how to do the following scenario.
    In My Purchase Order there will be 2 material A dan B. And B is a free goods (no invoice receipt).
    And in this Purchase Order there will be added some type of Delivery Cost.
    How can I make this Delivery Cost to be distributed propotional to material A and B since in line item B no condition type are allowed to be added.
    Please help.
    Thanks in Advanced
    Best Regards,
    Sugiharto

    Hi ,
    free goods Delivery charge
    If it is imported free goods..please go through the following link
    PO for goods free of charge
    Regards,
    Nani.

  • Report for delivery costs

    Hi,
    1.
    I need to have a report for the paid delivey costs(planned and unplanned) for the given pos.
    2.
    Is there any std transaction which can give the list of fast moving items based on movement types?
    Please help me, it is very urgent.
    Your help is appreciated.
    Regards,
    Subbu.

    Hi,
    For Delivery Cost look in Table EKBZ ,EKBZH.For Fast moving item use the T Code MCBE (also MCBA,MCBC)in which you can find the fields like number of valuated stock receipts and issue and also number of movements .Selecting a given period range if the number of movemnets is sorted in descending order the maximum moved material can be found.
    Dhruba
    Message was edited by:
            Dhruba Charan Behera

  • Report for Planned Delivery Costs

    Hi,
    Is there any Report for Planned delivery costs per month/day.One of our client needs separate report for frieght charges so that he can be able to pay service tax (GTA) for the same.
    Thanks
    Prasad

    Hai,
    Did you check thro' Tcode MIR5.

  • Question on uplanned delivery costs need to go to GL account

    Hello
    I have a question regarding unplanned deliver costs. I am a FI analyst  Can you please explain my how I can solve my problem . My user wants unplanned delivery costs to go in to the GL account .
    In MM account determination GL account is set up but when I am doing MIRO
    . I am putting  total amount in amount field and freight costs in unplanned field under ‘detail ‘ section.
    When I simulate it gives me ‘tax code ‘ related warning when I hit enter it credit vendor and debits  GR/IR clearing and some debit  to inventory  account but not  to freight account,
    What’s  the problem. Can someone explain me :
    1)     What do I need to do to make it go to GL account ( account is set up but what is tax code related error . how do I fix that,
    2)     How does unplanned delivery costs work if I have tax, discount and freight.
    3)     Is tax calculated off total amount (inventory + freight) and discount too. How can I prevent that so that my tax is calculated just on inventory amount?
    4)     DO I have to put total in amount field (meaning inventory amount + fright ) or not .
    I will be grateful if someone can guide me towards right direction. Please give me a detailed answer. How does it work???
    Thanks
    Kavita Reddy

    Hi,
    1. If you eant ot post to a differnet GL account the GL tab is there.. there you have to mention the Gl account.. like Fb50.
    2. When you put some amount in unplanend delivery cost ..
    a. If material is Moving average price then the amount will be debited to inventory account
    b. If material is in standard price then it eill go to price differnece account.
    3. frieght vendor , discount why not u calculate through pricing schema in PO and after that in MIRP for firght vendor u will have different option..Just check with MM guys..
    4.answered in point 1.
    Hope it will helps ..
    Assign point if helpful
    regards
    PK

  • Question on unplanned delivery costs need to go to GL account ????

    Hello
    I have a question regarding unplanned deliver costs. I am a FI analyst  Can you please explain my how I can solve my problem . My user wants unplanned delivery costs to go in to the GL account .
    In MM account determination GL account is set up but when I am doing MIRO
    . I am putting  total amount in amount field and freight costs in unplanned field under ‘detail ‘ section.
    When I simulate it gives me ‘tax code ‘ related warning when I hit enter it credit vendor and debits  GR/IR clearing and some debit  to inventory  account but not  to freight account,
    What’s  the problem. Can someone explain me :
    1)     What do I need to do to make it go to GL account ( account is set up but what is tax code related error . how do I fix that,
    2)     How does unplanned delivery costs work if I have tax, discount and freight.
    3)     Is tax calculated off total amount (inventory + freight) and discount too. How can I prevent that so that my tax is calculated just on inventory amount?
    4)     DO I have to put total in amount field (meaning inventory amount + fright ) or not .
    I will be grateful if someone can guide me towards right direction. Please give me a detailed answer. How does it work???
    Thanks
    Kavita Reddy

    in standard setting the freight amount gets debit in the stock or inventoy account and gets credit in the fright accoutn at the time fo gr so it means the amount of frieght is gettting invenotrised
    now at the time of IV IN MIRO SYSTEM CREDITS THE VENDOR ACCOUNT AND DEBITS THE GR/IR account
    if u want to settele the planned delivery cost then select the laout variant for the planned delivery at item level
    or in case if u want to make use of the unplanned delivery cost then u r doing the right step
    but as u simulate the g/l accounts sytem will debit the inventory or stock account for it  rather then frieght account (i belive so )
    as the uplanned delivery cost may be getting inventorised that is added to the material price
    and as u said u dont want to have tax calulated on the unplanned delivery cost then i suggest u to post it as subsequent debit and there do not make use of the claulate tax option or do the direct posting for the g/l account option

  • Planned delivery cost for the scheduling agreement

    Hi Experts
    1. I have an requirement to post Invoice ver. for the Planned delivery cost (freight,customs duty,CVD etc) against the Scheduling Agreement just like Import Purchases with checking off the GR Based IV Indicator before doing the GR
    I tried it but its giving me that no delivery costs are Planned in the Scheduling agreements it runs fine in case of the PO because PO is a time independent.  Please inform how to post the same for schedule agreement with time dependent indicator on. I tried switching off the time dependent indicator and the system allowed, but my requirement is to Post I.V for the delivery cost with the time dependent indicator on.
    Appreciate if you can suggest something in this case Urgently .
    2. Aother issue is we have some uploaded Scheduling agreement from legacy system with Time dependent conditions. For this we need to post planned delivery cost in Miro. Since the system is not allowing to post, how to about for this. Shall we enter the delivery cost in unplanned delivery cost in Miro and post.  Please suggest if any alternate solution is available.
    Regards
    Arvind

    Hi,
    As you know if the delivery cost document is not posted during GR the
    delivery cost is not proposed during invoice (MIRO). Planned delivery
    cost will be proposed in invoice only when there are records in EKBZ
    table. The EKBZ table will be updated when delivery cost is posted
    during GR itself.
    Please ensure in the PO itself thatr the conditions have been defined
    properly with the relevant amounts and values.
    During GR when planned delivery cost conditions are present in PO,
    system checks for values in amount field. Then only appropriate
    calculations will be done for delivery cost and planned delivery cost
    document will posted during GR and hence updates EKBZ table.
    Solution to this issue is described in below steps,
    1) reverse the invoice document
    2) reverse GR document.
    3) You have to give values in amount field in relevant conditions ZGDS
       in the PO.
       If you face any issues changing the values, delete above conditions
       and put it again manually and give values in amount field also.
    4) Post GR once again, delivery cost document will also be posted.
       You can check it in PO history.
    5) During invoice select Item + planned delivery cost and post the
       invoice. If you need planned delivery cost to be posted separately,
       then you can post individual invoice for item and delivery cost.
    Please note it is not possible to post delivery costs for documents with
    multiple accountassignments. 
    For your second question, I am afraid I can not answer. Please open a new ntry in the forum, so that someone else can answer it.
    Best Regards,
    Arminda Jack

  • How to get rid of "Delivery costs have not been cleared" status = MM_EKKO

    Hi dear experts,
    During pretreatment of MM_EKKO archiving object (TA: SARA), I get an amazing huge amount of PO position which can not be archived due to "*Delivery costs have not been cleared*".
    I tried several ways to find out how to solve this issue but without any success.
    Point is that we do not clear delivery cost regarding those PO positions, but delivery cost are transfered directly to a global account.
    It means that those PO's won't never be cleared.
    Any ideas about how I can fix this issue?
    Best regards,
    Daniel

    Yep,
    no idea why, but when I uncheck the "Final Invoice" box save and went back into the same PO and check again the same "Final Invoice" box, then, as a miracle, SARA=>MM_EKKO=> Pretreatment knows that this document is cleared and can be archived.
    It is just that for now, really old PO's are located in the present residence time
    I hope this slyness will help someone else one day.
    Regards,
    Daniel
    Edited by: Daniel Putzschler on Jul 28, 2009 2:02 PM

  • ERS and delivery costs

    Hi guys,
    We have following two problems in case of ERS vendors.
    1) We have certain delivery costs also in purchase order.  The same vendor will receive material payment and freight related payments.  In MRRL transaction, we select "Selected goods items + Planned del costs"  and run MRRL.  But after this also, amount excluding freight amount is posted in the invoice and delivery cost is not being picked for invoice.  How to get material cost + delivery cost also in one invoice
    2) In another scenario, we have different freight vendor.  For this we are configuring ERS for delivery costs also.  But the problem is in configuration we have to mention the vendor code in "Specify Automatic Settlement of Planned Delivery Costs".  Can we give vendor code as "  *  " here?  Or is there any other way of doing configuration without mentioning vendor code and it is applicable for all vendors ?
    Please suggest the solution for the above two problems.

    Hi Pankaj,
    Thanks for ur reply.  This will work.  But my problem is with this, we have to include all the freight vendors in configuration.  But we do not know how many vendors are there for the company.  If any new vendor is created, who has to enter this in the configuration..
    Is there any other way of making this functionality applicable for all vendors.
    Other problem is in our PO we have basic rate and 3 to 4 delivery costs,.  We have made 103 and then 105 and run ERS run and arranged payment to material vendor (it is same for both material and freight)
    But for some reason we are making return delivery against material document with 105 movement.  When we run MRRL for this, it will generate credit memo for the quantity returned to vendor.  But delivery costs are also added.  We want to avoid delivery costs in credit memo and it should only take material cost
    How to acheive this?  Please help me out

  • Goods and delivery cost processing at one instance through MIRO

    Hello,
    Is there any possibility of doing bill wise MIRO for both goods and planned delivery cost in a single screen apart from refering PO and option goods+planned delivery cost?
    The scenario is; vendor is common for both goods and delivery cost,organization want to pass MIRO bill wise for goods and delivery cost at same instance.
    Regards

    Hi
    The scenario is; vendor is common for both goods and delivery cost,organization want to pass MIRO bill wise for goods and delivery cost at same instance.
    If vendor is same we can do it for multiple Po at same instance in MIRO,what Mr, Bijay Kumar said ,follow this
    Regards
    Kailas ugale

  • How can I order more than one project to save on delivery costs?

    Is it possible to order more than one project (book) in iPhoto at the same time to save on delivery costs? I have several to order and I dont want to get hit for £5.99 three time if possible. I cant see how to do it or even if this is possible. Any guidance would be much appreciated.
    Regards,
    Andy

    You can only order identical projects on one order. If they are different then a seperate order is required
    LN

  • Planned delivery cost at PO header

    Hello,
    I have the following requirement:-
    1. There should be a freight condition at PO header level for delivery costs. Freight vendor is different from PO vendor.
    2. Even if there is partial GR, delievry cost must be paid in full.
           Say PO is for 100 PC and delivery cost is 100 INR. Now at MIGO if the delivered quantity is 75, the freight vendor must still be paid 100 INR.
    Issue 1 can be resolved easily by copying FRB* condtiton type and marking it for header level.
    I am stuck with how to resolve issue 2. I am unable to make the system post full freight condtion at MIGO for partial GR.
    I have thought of the following approach:-
    User does normal MIGO for partial GR and at MIRO posts the difference freight invoice amount as unplanned delivery cost. Also how best to treat subsequent delivery cost for 25 PC - as a unplanned delivery cost?.
    Material vendor gets invoiced in the normal way.
    Is there any setting to make the system post full freight condition (header or item) amount even for partial GR? If not how best to treat this scenario and for subsequent invoice for remaining PO amount.
    Waiting for your valuable suggestions.
    Thanks,
    Saurav.

    Hi
    If you are aware of the no of goods receipts and the cost of freight per Gr then you can enter this amount at the Po header before the GR. The advantage is that the total freight cost will be divided across all complete Po quantity.
    Thanks
    Ganapathy Subramanian.N

  • How to enter a specific vendor for  the delivery costs in purchasing order?

    Now I want to create a purchasing order including planned deliver costs such as Freight, Coustoms ect, as the vendor of such planned deliver costs is different from the goods supplier, then How to enter a specific vendor for  the delivery costs in purchasing order? That means the partner for invoice partner will be two vendors at least in one purchasing order. thanks very much.
    <i>
    <b>No one would like to answer this question?</b></i>
    Message was edited by:
            King Qi

    hi, 
    You can have vendor at each condition record level.
    try it out.
    cheers
    Rav

  • Message no. V1631-You cannot enter new delivery costs

    Hi All,
    before posting this issue i have searched and could not found the correct thread.
    system: ECC: 6.0
    Scenario1: Inter company STO with import process
    PO created and delivery created and TO created and confirmed and PGI done.and SD invoice done
    After this foreign trade module process starts and creating shipment and entering delivery import costs and releasing import costs from the custom transaction which will update the delivery costs into PO through BAPI_PO_CHNAGE
    here i am getting the above error Message no. V1631-You cannot enter new delivery costs
    but when i am adding delivery conditions manually in ME22N system accepting
    scenario2:
    PO created and delivery created and TO created and confirmed
    foreign trade module process starts and creating shipment and entering delivery import costs and releasing import costs from the custom transaction
    successfully updating delivery conditions  in PO
    scenario 3:
    PO created and delivery created and TO created and confirmed
    Foreign trade module process starts and creating shipment and entering delivery import costs and releasing import costs from the custom transaction
    successfully updating delivery conditions  in PO
    PGI done and SD invoce done and GR completed
    After that trying to add delivery conditions and getting the same error
    Question: why i am not able to update the conditions through BAPI and i am able to update conditions in ME22N manually in scenario1??
    Thanks
    Kiran

    Hi ajit,
    Getting issue after PGI. no GR done.

Maybe you are looking for

  • Game Center mixes up scores of multiple users (apple IDs)

    (New iPad, iOS6 - all apps are up to date) My son and I both have our own Apple ID. When we play games in Game Center, we use our OWN ACCOUNT. Still we get each other's scores & achievements. Example: Subway Surfers: I log on to GC using my credentia

  • PO Conditions(Urgent)

    Dear All, i applied some conditions for LC and in the calculation schema i assigned acckey and in obyc i assigned a gl account for that acckey but when i am doing GR its updating all other conditions are updating except this one i assigned all others

  • ISE, Active directory and OUs

    Hello Everyone I have an ISE with an AD integration, i am trying to limit the access to the wireless users, i only added one OU "wireless users", but all the users can access to the wireless network, i just want to allow the access to the users in th

  • Problem Submit command

    Hi All, I am calling the standard report in the fumctiom module using submitt command. After that one i am using LIST_FROM_MEMORY  after that i am using below function module CALL FUNCTION 'LIST_TO_ASCI' TABLES listobject = list_tab listasci = txtlin

  • IPad Air stuck in recovery screen after update. No reset possible

      Hello everyone, I have searched the community for an answer but nothing fits really. There are some threads regarding problems with the update to iOS 8.1 and screens stuck in recovery mode, but none of the suggested solutions work for me and I am r