Delivery date and goods issue date anomaly

I am seeing issue in client site where when an order is entered for customer with a delivery date in December 2010 the goods issue date and loading are all correct. Soon as I put a delivery date after Jan 6, 2011 all the dates become the same. For example I enter Jan 29, 2011 as delivery all the goods issue, loading etc become Jan 29, 2011. Is there some config issue somewhere causing this issue.

hi harvinder
this is all happening because
when you entered the customer and material in sales order the system automatically prompts the delivery date of the material.
because in SPRO there is a setting called - DELIVERY SCHEDULING AND TRANSPORTATION SCHEDULING. with the help of factory calendar or shipping point calendar.
in the same process it has shown these dates and these dates might be the tentative because material may not be available at that time & as soon as you changed the delivery date in the system manually again system will do RE ATP and would have given confirmed date as 14.01.2001 & basing on the confirmed date every date follows.
this is standard behaviour of the system.
balajia

Similar Messages

  • Want to change Del Date and Goods Issue date in Delivery scdl tab of PO

    Hi Gurus,
    I am in a situation wherein i need to change the Goods Issue date in Delivery schedule tab of Purchase Order and make it equivalent to Delivery date in the same tab.
    Currently the Goods issue date that is taken by default will always be one day after the Delivery date.
    Where is the control for this???
    Regards,
    Trishul

    Hi Jürgen,
    Thanks for your response. You are right. The Process is STO.
    The delivery has not been created as yet.  Everything is happening while creating the PO. The settings are such that the delivery date will be taken by the system automatically by doing the Availability check and simultaneously the goods issue date will be updated. But it will be one day later to the delivery date. But i want this to be same.
    Incase if i change the Goods Issue date manually, this is the message i get "Goods issue cannot be carried out in the past"
    Message no. V1062
    Please let me know if i am not clear.
    Regards,
    Trishul
    Edited by: Trishul Das on Mar 17, 2009 4:09 PM

  • Sales Order Loading Date and Goods Issue Date

    I am getting confused with specific sales orders in our system which have a loading date of 5.11.2008 00:00 and a goods issue of 6.11.2008 00:00, this would imply a loading time of 1 day, I would think. However in our system I look at the shipping point I see default from shipping point is 2 work days. Is there something I am missing or other setting I am not aware of?

    What is the delivery scheduling type you are using for the sales document type? If you are using A change it to X. Also check the loading times.
    Regards,
    GSL.

  • Goods issue date and goods receipt date

    Hi Guys,
                 i was asked to display STO list.They asked me add goods issue date and goods Report date in the o/p columns.So any body can tell me what are the fields for goods issue and goods Receipt date's.?can u guys tell me the Tr code for these fields .?
    Thanks,
    Gopi.

    Hi there,
    I already solve it by myself.
    Actually is i call the initialization twice:
    Company.GetBusinessObject(SAPbobsCOM.BoObjectTypes.oInventoryGenEntry)
    Thats what make this problem happened.
    Sorry.
    Best Regards,
    danny

  • Deliveries and goods issue date

    Hi,
    can any one tell me here the name of the table which can show the details of the deliveries against the goods issue date along with the sales order?
    Thanks,
    Ravi

    You can get these details in LIKP/LIPS and VBFA.

  • What to do if delivery-date exceeds goods issue date?

    Hi all,
    is there a way to adjust this date after trigger 'POST GOODS ISSUE' ? User-Exit...Function Module...
    Many TX for your help,
    Christian

    IM sorry this was such a mess.  It's not normal. 
    DId you sign up online?  I have had good service in Verizon stores and will not do business online.  Your experience confirms my concerns about lost phone, wrong computer entries and wrong billing.
    there are a few mobility CSR on this forum, you should seek them out and hopefully get this fixed.
    i Understand you can contact on Facebook and Twitter Also.

  • Collective Invoice - Actual Goods Issue date

    Hi Friends,
    Collective invoice topic has been discussed many times but I didn't find exact solution to solve my issue.
    From sap help and few other threads it is learnt that Billing type, Billing date, Payer, Billing unit, Terms of payment, Incoterms, Letter of credit should be same to have collective invoice. During my tests it is understood that apart from those Actual Goods Issue date (Post Goods Issue) date should be same to have collective invoice for different sales orders/deliveries. In my tests SAP didn't consider Billing date but it did consider Actual GI date. In other words, even the billing date and other requirements are same invoice split happend due to different Actual GI date. However collective invoice created even though the billing date is different but Actual GI date is same.
    My user creates one sales order and one delivery for a customer once in a week (so 4 orders/deliveries in a month) and creates Invoice by end of the month with collective invoice. So based on the above tests I can ask the user to create sales orders, deliveries every week but perform Post Goods Issue month end and then create invoice so that collective invoice can be done. But the issue is they want to do the Post Goods Issue every week because the stock levels should reduce on weekly basis. So how can we create collective invoice even though the Post Goods Issue is done weekly (so Actual GI date will be different)
    Any idea? Please let me know if further information required.
    Thank you

    Hi,
    You may consider writing a routine under copying requirements so that invoice is not split even if the Actual GI date is different.
    Consider the following [thread|Collective billing; for more info.
    Regards,
    Amit

  • In Stpo transport, load and goods issue line is not appear

    Hi MM Expert's
    I am creating the STPO's (Different company codes) in items details -> Del.sch-> transport, load date and goods issue is not appear. The Delivery date is 25.02.2008. next day the user as change the del.date from 25th to 26th. transport,load date and goods issue is appear.
    Anybody plz tell me how its happen like this, and tell the root cause.
    Regards
    chandru.

    hi
    shipping point calendar and route calendar must be equal here.
    but
    i dont know why these are different here.
    because it is overtaking or superseeding the shipping calendar here.
    make the shipping point and route calendar in sync with each other.
    test and confirm
    balajia

  • What is the difference between delivery date and actual goods issue date?

    Hi ,
    Can you please tell me the difference between Delivery date and Actual goods issue date ?
    Delivery data can be be greater than goods issue date?
    Thanks,
    Ajay

    Hi Ajay,
                  Delivery date means its the original date on which the delivery should be done.Actual goods Issue date is the date on which goods to be delivered according to the purchase order.There can be delay in the delivery so we maintain 2 objects.
    Yes delivery date can be greater than Goods Issue date.
    Hope this clears
    Regards
    Karthik

  • Change goods Issue date and delivery date

    while crating Sales document through VA01
    i want  to replace goods issue date (VBEP-WADAT ) with my Z calender date.
    so that delivery date(ETDAT) aslo should chaged automatically ( bcz iof the change in goods isuue date ).
    how to achive this ?
    i tryied in  Program    program of MV45AFZZ/ MV45AFZB in the User Exists mentioned below:
    1.     Form Userexit_Check_VBEP
    2.     Form userexit_move_field_to_vbep
    i was able to change goods issue date (VBEP-WADAT )  but  not refleting in output screen,..
    regards,
    ramesh

    Hi Venkat,
      Even it did not update in my user exit when I update from VBEP-WADAT.  So, I did back calculation (considering route lead time) and updated Delivery date field VBEP-EDATU.  It is simple.  I have given the sample code as below.
       if lines( xvbap[] ) = 1 and VBEP-ETENR = '0001' and            "Calculate RDD while the first line item entered
         vbap-route <> space and <<your GI date>> is not initial.    "Only when header RSD is filled
          select single TRAZTD into ws_traztd from tvro
                where route = vbap-route.
          ws_days = ws_traztd / 24 / 10000.
          if ws_days <> 0.    "Only when Transp. Lead time is maintained ( So, will not affect other entities )
             select single FABKL into ws_fabkl from T001W
                where WERKS = vbap-werks.
             CALL FUNCTION 'WDKAL_DATE_ADD_FKDAYS'       "Calculate as per Factory calender
                 EXPORTING
                   i_date        = <<your GI date>>
                   i_fkday       = ws_days
                   i_fabkl       = ws_fabkl
                 IMPORTING
                   E_DATE        = ws_date
                  E_FKDAY       =
                 EXCEPTIONS
                    ERROR         = 1
                    OTHERS        = 2
             IF sy-subrc = 0.
                VBEP-EDATU = vbak-vdatu.   "copy to the first line item
             ENDIF.
          endif.
        endif.    "Route days

  • How to fetch post goods issue date and sales order creation date

    Hi All,
    How to find out the difference between SD Sales Order Item Creation Date and final Post goods issue Date. I would like to know how to fetch those dates and what is the relationship between the tables from which i will get the dates.
    Please let me know the solution .
    Thanks in advance.

    Hi,
    Sales order creation date is when u raise a sales order in favor of the customer using VA01.......using ATP logic system purposes the material availability date....
    after saving ur sales order...when u raise the Delivery using VL01n  w.r.t to OR...than u have to perform picking ....In the picking Tab...specify the amount to be picked than press Post Good Issue....means the goods left the company premises ..
    You can the fetch the values using tables-  Use T code   SE12  or SE16
    Vbak-----order header
    Vbap-----order item
    Vbek-----order schedule line
    Likp-----Delivery header
    Lips----Delivery item

  • New planned goods issue date during delivery creation due to changed route

    Hello All,
    I have defined 2 routes with different values for transit time and transporation lead times. I have configured routes such that in order creation - route A is determined and while delivery creation due to weight group - delivery B is determined.
    Now for Route A i have maintained transit time of 3 days and Transportation lead time of 4 days and for Route B it is 1 day each.
    Delivery scheduling is active for the order type.
    Now when i create the order with a delivery date of say 05/24/2010 then (route A with transit time of 3 days) is determined and the planned goods issue date of 05/21/2010 is in the order.
    Now while creating delivery (Route B which has transit time 1 day) is determined due to the weight group. But the planned goods issue date is still the same 05/21/2010 as in order.
    I am assuming that since the route B has a route of 1 day so the planned goods issue date should be re-determined to 05/23/2010? IS there no scheduling done during delivery creation even though route and subsequently transit time has changed?
    Please let me know the answer to this...
    Thanks
    Shobhit

    Hi ,
    You can use TA - MASS . Enter object type - BUS2032(for sales orders) on initial screen and select sales item data.
    Next screen enter selection fields like sales order no and items. After giving order no and item range , execute and enter all new values for any item data fields. After pressing button "carry out mass change", don't forget to press save button.

  • Purchase order delivery shedule tabl , no Good issue date, loading date.?

    Hi Experts
      We found some Purchase order, in po item, it is without goods issue date, loading date and so on.
    Material has set ATP check on mrp3. what's possbile wrong? something wrong for matieral setup or others?
    Thanks
    Alice

    Hi
    Really thanks for your help. You mentioned " SD delivery of the sending plant is created and processed."
    Do you mean in material master , the sales view -delivery plant will impact this po GI date and Loading date? It maybe something wrong?
    Thanks
    Alice

  • Different Request Delivery Date & Goods Issue Date

    Hi SD Experts,
    Please find my queries as below:
    1. How do i configure the system to propose delivery date as today's date? Currently the system now always propose tomorrow's date but i want it to be today's date. Assuming today is 21st December but the system is always giving 22nd December. Anything that can be done inside SPRO? Inside VOV8 i just tick 'Propose Delivery Date' but i left the box empty for 'Lead time in days'
    2. Assuming today is 21st December, and i created a SO. The goods issue date is always tomorrow's date as well which is 22nd December. I want the goods issue date to follow 'Request Delivery Date'
    3. In conclusion, why is 'Request Delivery Date' is always tomorrow's date?
    Anything that can be done? Please help
    Thanks!
    Regards,
    LEE
    Edited by: YEOW LENG LEE on Dec 21, 2008 12:10 PM

    Hi lee
    A request delivery date comes if you maintain the lead time in days in VOV8 , GR time , In-house production time RLT in days in MMR , based on that the you will get the requested  delivery date If you keep the fields blank  then you will get the request delivery date as todays date only but if you have assigned factory calendar in shipping point and if you create sales order on Saturday (19/12/2008) then the delivery date will be on Monday i.e., 22/12/2008.
    Now if you want the goods issue date as different date then the delivery date should be different ,if you fill any one feild and check then you will get the different goods issue date
    Coming finally you are getting a request delivery date as tomorrow's date because of the factory calendar you have assigned to shipping point and to the CMR
    Regards
    Srinath

  • Goods issue dates are different in sales order & delivery

    Hi,
    We have a situation where in sales order schedule line tab goods issue date is 21.30.2011
    but in delivery the planned GI date is 28.03.2011.
    There are two line item in the sales order & in both the line items all the dates are same.
    Same route is there in sales order & delivery.
    In delivery Item category avalability check Off is Y(Do not check avail. when reporting results of pick.request)
    All the dates(delivery,loading,Transportation planning) are different .
    waiting for responce.
    Thanks In advence
    Susrikant

    goods issue date is 21.30.2011
    What was the Actual GI date in delivery??  This should be the same as schedule line date.
    thanks
    G. Lakshmipathi

Maybe you are looking for

  • Error message when installing Oracle 10g on Windows XP Professional

    Hello, I need help installing oracle 10g database. When I attempt to run the installation from the setup.exe icon, I get a message that says "Error in writing to directory C:\Documents and Settings\Owner\Local Settings\Temp\OraInstall2007-04-29_01-19

  • Screen capturing in Premiere Pro 2.0?

    I'm looking to create a video presentation of my company's proprietary web applications and would like to capture my screen as I navigate through the pages and narrate.  I have seen other recently released video editing software that enables users to

  • Help with HTML tags and web page creating

    I have a project that is supposed to use an HTML class we make. He has given us the basics but we have to fill it in. My question is: How do you code a value that has been passed to a method into an html tag. For instance we have one that is called m

  • IChat v Skype - 'fail to respond' etc

    I have been using Skype on my Mac for a long time, and recently decided to try out iChat AV with friends living overseas. They have Macs too. I find iChat has superior audio capabilities but it has serious problems with such issues as 'user failed to

  • Calling SAP transaction from WebDynpro

    HI, Could someone post a link as to how I may call a SAP transaction from a webdynpro. Will this be an external call to R/3 or can i get it embedded in my dynpro....... Tnks..