Delivery date to be replaced by Confirmation date automatically.
Hi All MM gurus,,
I want to do a setting in the Purchase order in such a way that if there is inbound delivery created or say buyer created a confirmation manually in the PO.
The confirmation tab delivery date should replace the delivery date in the Delivery schedule tab automatically.
The buyer should not go and change the dates in both the places.
Is there any standard setting for this or else what all configuration needs to be done.
Thanks in advance
Sagar
Hi,
Thanks for the reply.
No this issue is not MRP revalant,
When the confimation comes from vendor , we change the confirmation tab as well as the delivery date in the line item and We send the PO back to vendor again with the new delivery date.
Now here the buyer has to change the dates twice.
Is there a std setting by which we can get once the confirmation date is changed it will change the delivery date automatically.
Thanks again
Sagar007
Similar Messages
-
Schedle line confirmation date is changing to shorter confirmation date
Hi friends,
The confirmed date in the schedule line is not in line with the planned
delivery time maintained in MMR.
When sales order with free of charge document type is created, the
confirmed schedule line is in line with planned del time for a material
of item category ZPTN-free of charge Purchase to order. After coverting
PR to PO the confirmed schedule line had been changed to earlier date
which is not in line with the planned delivery time in MMR.
Please provide your expert views and suggestions..
With warm regards
Janahello, friend.
please check if your purchase requisition has been configured for processing time. then check if the purchase requisition was converted to purchase order within the processing time specified, if any.
regards. -
Vendor Evaluation- Confirmation date Adherence
Hi Team
In vendor evolution I am using Delivery as my main criteria and Confirmation date Adherence as sub criteria and assigned weighting 1 . I have also entered the % and scoring both positive and negative. But when I am using T code ME61 system is showing scoring 0 for Confirmation date Adherence.
I have tried all option Confirmation date change in PO and GR still I am not able to see scoring in Tcode ME63. All other criteria is showing correctly, please let me know if I am missing any important step.
Thanks
SanjaySanjay
Did you solve this issue? From what I have researched in SAP the confirmation date is only used on a advance ship notice, is this what you are measuring?
Our company would like to measure against the order confirmation type "AB" not the delivery conformation "LA"
Any suggestion on using the order confirmation in this measure would be appreciated. Is it possible?
Thanks
Brad -
Can GATP confimed date come from production order finishing date??
Hi Expert,
I have one question to ask.
in the GATP , I want to the APO system can consider the production ability , that is, when I create a sales order, the system will make a GATP check in APO, if there is no enough stock, the system will create a PPDS planned order and return the planner order finsihed date as the schedule line confirmed date.
I do not know this is possible or not??
I hope some expert can help me to solve this problem
thank you in advance!Hi Liu,
Why Planned order date.. It could be Production order date (planned order release date) + inhouse production time + Transporation lead time + GR processing time (at the original location where the order is placed) ..that should determine the material availability date. CTP exactly does this. Make sure that the "replenishment lead time is switched off" in the product-location master (in fact this is location independent)- as this take precedene over everything else.
Also ensure that that end of checking horizon is larger than the interval established above, else MAD could be much earlier. Also enure that transfer of requirements is set both at header and schudule line level for CTP to work.
Regards,
Loknath -
Sceduling as per the delivery confirmation date in sales order
Hi,
I am working with planning strategy 50 and using availabilty check as per ATP.
When I create the sales order and check the availabilty, system confirms the delivery after TRLT(current date+TRLT).But when I run MRP,system creates a planned order on the req delivery date date.
(Req date - GR Processing Time - In-House Production time) so that Planned Order is available on the req delivery date.
As the system confirms the delivery after TRLT,I want my planned order's availabilty on the same date.
to summarise,I don't want system to consider the Reqmt date as reqd delivery date of the sales order but the conformed delivery date of the sales order.
I appreciate your help in letting me know if there is any way we can do this.
Regards,
Sastry
Edited by: Sastry Krishna on Dec 13, 2008 4:45 PMHi,
Can you check what is the Variant (dates filed) specified by going to SM37 transaction.do as below,
Goto SM37 transaction and give job name and then execute then select check box against date you scheduled job and then CtrlShiftF9,now place cursor on program/command and from the menu Goto-->Variant,here you check if any date range there.
Regards,
Chandra -
PO Confirmation Date (OA) & Inbound Delivery Date Report
Dear All,
Please let me know SAP Standard Report
PO Confirmation Date (OA) & Inbound Delivery Date Report
Regards
AmeyHi,
I guess ME2A will give u unconfirmed orders that require a confirmation, but have not yet been confirmed according to the dates configured for your monitoring period. First, ensure that you have such an order
Also, ensure that your confirmation control (OMGZ) has BOTH a value in Monitoring period AND Reference date.
Pls chk note for more information. https://service.sap.com/sap/support/notes/500502
BR,
Krishna -
Delivery Confirmation date calculation
Dear All,
In the sales order the delivery confirmation date is achieved after running the Availability check.
In our case lead time calculation for TAB item category is from Planned delivery time in Material master or Purchase info record+GR processing time + Purchase processing time + Pick/Pack days
But our requirement is, Planned delivery time to be calculated from Material master not from Purchase info record.
In Plant parameter setting I have removed the check of Scheduling : Info Rec/Agreement still the planned delivery time is calculated from Purchase info record.
Please let me know any BADI to get the planned delivery time from material master.
Regards,
NirmalPlease check if you have selected the check box for replenishment lead time.
Regards
Vasim. -
Open Purchase Orders Report with Confirmation Dates
Hi Friends,
I have searched a lot for the following need and I have found nothing. I was wondering if there ia any report that I can show the scheduled delivery dates from a Purchase order. I have seen in ME2L that by placing EINT in scope of list I can see the schedule lines. However, if there is a new delivery date due to supplier confirmation that have been placed in PO with the indicator AB this is not appeared. At the same time if there is a partial quantity that has already been delivered then it does not appear as well. So, I need a report with all the scheduled delivery line plus the open quantity.
Many Thanks in advance,
IoannisIt is very strange. Because what I see is that in this report the confirmation date is not appeared although the schedule line is appeared. Then If I go to change the confirmation date in PO for second time then it is appeared. I have no idea why this is happening
-
Material Confirmation date in future though the material is in stock
Dear Gurus,
Please tell me why the system is giving the material confirmation date in future though the matl is available in stock.
System creating two schedule lines one for 15/10 (15 oct) and the second one with the confirmation of quantity on 22/11 (22 Nov) as I have enough stock than the required for this order. In MRP1 view of same matl Master of same material delivery planning time is 28 days. and in MRP3 view the Replenishment lead time is 20 days. please tell me what date system considering to shift the confirmation date in future. the factory calender has Sat-sunday off.
please tell me the possible reasons for confirmation date change.
regards,
SandeshHi ,
Please check the value at MM03-> Sales: General plant Tab ->Availability Check is '02'.
u201802u2019 will consider all the u2018Individual Requirementsu2019 done before and during the creation of Sales order for the combination of respective Material & Plant.
Even though Material stock will be visible for you at MMBe for respective plant double click on the Quantity, it will show you multiple Row with one of it will be " On Order Stock" these are the other orders for which Quantity is already confirmed but respective PGI is not yet done.
The next schedule line date always generated based on the Factory calendar (based on Holidays/Weekly Offs if any).
AT MD04 Tcode, based on the selection made at Material master for Availability Check you could see all the requirements related to Goods Issue Sales Orders , STO & Production Orders for Goods receipts.
Hope this will solve your query.
With Best Regards,
RB. -
Purchase order list display with confirmed date
Hi,
I know the ME2* transactions, but how can I get a list from SAP where I see for a list of purchase orders the initial requested delivery date next to the confirmed delivery date?
Thanks,
Peter
Helpfull feedback will be rewarded.Hi,
you need to customize on this requirement, use below purchase order tables
EKKO Purchase document
EKPO Purchase document (item level)
EKPV Shipping-Specific Data on Stock Tfr. for P Doc. Item
EKET Delivery schedule
VETVG Delivery Due Index for Stock Transfer
EKES Order Acceptance/Fulfillment Confirmations
EKKN Account assignment in purchasing
EKAN Vendor address purchasing
EKPA Partner functions
EIPO Item export / import data
EINA Purchase info record (main data)
EINE Purchase info record (organisational data)
EORD Source list
EBAN Purchase requisition
EBKN Purchase Requisition Account Assignment
Regards,
Sankaran -
Hi,
Iam looking for a report which shows the PO date , PO delivery date , confirmation date & GR date. I can find a report for all except for the confirmation date. Any update on this is highly appreciated.
Regards
SudhakarHi,
ME92F (Check SAP Note 500502 - FAQ: Order acknowledgments in the purchasing) for more details.
ME2A will give you unconfirmed orders that needs to be confirmed.
Hope this helps!
Reetesh -
Vendor evaluation - Confirmation Date
Dear all,
am trying to run vendor evaluation for - confirmation date..
i have create a new confirmation spro - MM -purchasing - confirmations - define external conf , setup conf control
i have included this confirmation in the PO ..delivery date in po item line is 23.06.2014.. delivery date in conf in item details 22.06.2014 GR date is 23.06
when i run vend evaluation, 4 Adher. to Conf. Date is coming zero ---
can you pls advise what could be the reason... is my understanding to this Subcriterion is correctHi,
As an example its not available, nor tried self. As a common rule - if a main criteria created and sub criteria exists, when you run evaluation for main - excluding a stage of sub is not possible.
Secondly try transaction code: ME6C
Help says: Set this indicator if you only want to display those vendors that do not have
an evaluation for certain main criteria. When you click on Execute, a screen allowing you to choose one or more main criteria appears. The missing evaluations for these criteria are then listed.
here you can selection option to include/exclude evaluation. -
Vendor Evaluation - calculating score for subcriteria Confirmation date
Hi,
I have configured vedor evaluation with subcriteria Confirmation date with B
But while maintaing vendor evaluation ,system is not calculating score.
As per my understanding system compares the date of inbound delivery and actual GR date.
Can somebody help me on this how system calculates score or what is missing.
Thanks & Regards,
CharudattaHi,
Look at this article, it explains how it is calculated.
[http://help.sap.com/saphelp_erp60_sp/helpdata/en/8d/b985b0414511d188fc0000e8322f96/frameset.htm]
Thanks. -
Confirmation date - Strategy grp 50
Hi, can anyone advise why when we use strategy grp 50 'Planning without final assembly' for MTO scenario, the confirmed date/lead time in the SO is based on the inhouse production time only?
When i use strategy group 20 'Make-to-order production', the confirmed date/lead time in SO is based on inhouse production time + GR processing time.
Can i know why the difference in th delivery scheduling?
Thanks
PeterHi PP,
The following links may help to clarify your doubt:
[Strategy type|http://help.sap.com/saphelp_46c/helpdata/en/e0/71bb169c9f11d191920000e8a5f6e6/frameset.htm]
[Availability check|http://help.sap.com/saphelp_46c/helpdata/en/cf/70124adf2d11d1b55e0000e82de178/content.htm]
Regards,
Abhee. -
POD confirmation date allow to give before goods issue date.
Hello ,
Would like to know that POD confirmation date process , system allows to input the pod date before the actual goods issue date in VLPOD screen as logically it should be wrong i guess as per my knowledge .i.e as soon as goods receipt by customer then only he will confirm pod , how system can allow before the actual goods issue date in VLPOD.
for eg:
1.sales order
2.delivery
3.goods issue with 23.12.2013
4.pod date can enter with 01.12.2013 and save it.
5.billing document
Please advisse your thoughts/suggestions.
Regards
venkathi venkat
system will take back also , there is no config control ,you have to user user exit and control it
include: MV50AFZ1
user exit: USEREXIT_SAVE_DOCUMENT_PREPARE.
IF likp-vkorg EQ '1000'. "
READ TABLE XLIKP INDEX 1.
IF XLIKP-PODAT IS NOT INITIAL AND XLIKP-WADAT_IST grater then or eq to XLIKP-PODAT
MESSAGE e001(Z1) with xlips-VBELN. "MESSAGE DOCUMENT DATE IS BACK DATE ( CHECK YOUR ENTRY)
ENDIF.
ENDIF.
check the ABAPER discuss with above logic
regards
sankar
Maybe you are looking for
-
Procedure and Functions from ADF View Layer
Hi, Before i ask my question ,I would like to mention that I have done lot of googling on this topic before asking this question. http://adfhowto.blogspot.in/2010/11/call-db-procedure-or-function-from-adf.html http://adf-tools.blogspot.ca/2010/03/adf
-
Song Library Management Question
I have a music library several times larger than my 32gb ipod. My computer recently had a hard drive failure. I reinstalled itunes with everything else. My ipod of course still works. I have about 2750 songs on it. The problem is everything in my lib
-
create table t1(id1 number,name varchar2(10)); create table t2(id1 number,id2 number,name_value varchar2(10)); create table t3(id2 number, name1 varchar2(10)); insert into t1 (ID1, NAME) values (1, 'dave'); insert into t1 (ID1, NAME) values (2, 'rob'
-
Migrating data from Oracle 9i to SQL Server 2005
I am new to both. I need to first migrate data from oracle to sql server. After this I need to create a daily nightly batch process to insert new records from oracle to sql server into that table. As my knowledge in SQL server is zero. Can somebody h
-
I normally have 3 user options upon log in.. ( A, B, C) I log in as the (A) admin. I went for a coffee and closed the macbook while some applications were still open in admin.. When I came back I opened the screen to be confronted with user B's start