Delivery from the project stock

Dear experts,
Kindly suggent me for the below scenario...
My client wants to procure the goods from the project stock. The goods must be issued from the Project stock.
I am creating sales order and assigning the WBS element in the account assignment key.. i wann know that how should i deliver the goods from the project stock,,,, wat is the configurations needs to be done.
i had checked in requirement class.. ther i could not find any Delivery with project stock.. where in Schedule lines there is LP : Dlv. from project. in this shedule line there is no Movement type nuthin.. could anyone suggest me how to deliver the goods from the project stock.
Regards
abhi

Hi
You can try 221 movement type which is goods issue for a project.
Regards
Subhasish

Similar Messages

  • Delivery from the project stock not happening

    Dear experts,
    after doing a Post goods issue, system is not picking project stock but it is picking storage location stock (normal stock)
    (in MB1B this project stock is created with a movement type 561Q)
    (in sales order WBS is put at the item level.)
    please give solution
    atul

    Hi
    This is because of the simple reason that when the sales order is created your item category (which is getting determined in sales order) has not been marked with special stock indicator as Q while order creation
    This is first mistake
    (in MB1B this project stock is created with a movement type 561Q) As per my knowledge MB1B is transfer postings and movement type 561Q cannot be used here
    This is Second mistake
    Pls mark your sales  order  your item category with special stock indicator as Q  and then create sales order
    Make proper reservatation with proper t code movent types (take the help of MM people)
    Stocks should show as Project stocks separately in your plant in MMBE
    Then create delivery and do PGI
    That Project stock in MMBE will be consumed for this PGI so general unrestricted will remain same
    Regards
    Raja
    Edited by: ramanathan raja on Aug 8, 2009 11:38 PM

  • Delivery from the Project

    Hi Experts
    I am trying to do delivery from the Project in CNS0, but everytime i try to do the delivery the message occurs that "There are no deliveries for the chosen project".
    i checked the sales order in whcih the Finished good is account assigned the very WBS through which i am trying to do the delivery.
    Please let me know if i need to do any configuration or the steps to do the delivery from the Project. As in my current Project is a SAP PS-PP integration in which the raw material is procurred in PS and then it flows to PP for Planned orders and Production orders and all the Production activity is taken careoff in PP itself.
    I attached the Finished good in one of my internal activity and created a reservation for the same and i wanted to do the delivery from there.
    Experts i look forward for your advice

    Hi Mahendra
    I checked the points -
    1) Carry out availability for check components to be delivered - how do i "Carry out availability for check components to be delivered". i checked the stock availability and it was available in mmbe as unrestricted use
    2) ENsure that materials linked to network activity do not have backflush indicator., -  i checked and it dose not have a backflush indicator
    3) WBS/Network is released - It is released.
    When i press the delivery tab on CNS0 it say the same message
    anything else i need to see

  • Return to vendor from Blocked Project stock - Line rejection

    hi
    I have a problem in doing line rejection for return delivery from a blocked project stock.
    we had modified F5 notification for Project related senario to FQ and using the same for doing line rejection return delivery directly from project stock with the help of action box.
    While the include is accessing MSPR table for picking up the project stock.
    the steps involved are as below.
    1. create FQ notification (Similar to F5) by giving inputs as Material to be rejected,Plant, Defect code from existing code group and assign the purchase order.
    2. Tranfer the project stock to blocked projection stock ie.rejection stores using 344 movement type. while doing this 344 we give input of WBS element, storage location and Batch.Stocks against this WBS are picked from MSPR table and trasnferd to rejection stores.
    3.After this while doing return to vendor we give the reason code and post 122 document.
    the problem is if the material is having two WBS elements it and both have stock in rejection stores this follow up action is unable to pick the Exact stock for which the WBS element is assigned to notification while 344 movement.
    please suggest me as how the WBS element can be retrived from a notification which was used for earlier actions in action BOX.
    regards
    NVB

    Hi
    If u want to return the material to the vendor. In MIGO itself select return delivery against the material document with movement type 122 u can send it.
    This is irrespective of material lying in quality or blocked. From quality or from blocked status u can send the material back to vendor.
    No need for quality to Un restricted or Blocked to Un restricted.
    Regards,
    Raman

  • MIGO:How to post GR with Location induced from PO (Project Stock)

    Hi experts,
    I want to post GR with Location induced from PO (Project Stock).
    But SAP doesn't allow this induction.
    Please show me how to resolve it.
    thanx.
    Torao

    Hi,
    In PS if the account assignment is "P", then the material is treated for directed consumption to the Project or WBSe.
    If you want to track the Project Stock based upon of Storage Location (Here, the Storage Location is used as Project Stock location) then, please select Account Category as "Q".
    Create a PO using Account assignment Category Q will give you Tracking of Quantity based upon Project WBS and Storage Location. At the time of GR the Stock will be shown under Project WBS. (Physically maintained at Storage Location used)
    e. g. :  Create PO using Acct Assignment Q , give WBS and save.
    MIGO : GR will be done 101 Q (Project Stock)
    Quantities are shown : Mat # 100XXXXX  Qty : 100 Storage Location : XXX  Project Stock : 100 ( WBS )
    Special Stock : Q
    GI : 221 Q using the Project Stock for Consumption.
    The Project Stock can be tracked using T-Code MBBS.
    Hope it helps,
    Best regards
    Amit Bakshi

  • Help! how to create an outbound delivery from a project using a FM/BAPI?

    Hi,
    I need help to find a BAPI or FM which can be used to create an outbound delivery from a project similar to tcode CNS0?
    The following data will be used in creating the outbound delivery from a project:
      Project definition
      WBS Element
      Network
      Shipping Point
      Ship_To_Party
      Plant
      Storage Location
      Planned Goods Movement Date
      Delivery Type  : LP
      Sales Organization
      Distribution Channel
      Division
      Item Number
    Please help me find the appropriate BAPI or FM to create the delivery from project.
    Any help on this would be greatly appreciated.
    Thank you.
    with regards,
    Muthu Ganapathy.

    Hi Ferry Lianto,
    Thank you for your response.  Do you have a sample code to call this FM? Or can you please provide me what all parameters I need to pass to create delivery from project?    My input parameters are as given below:
    Project definition
    WBS Element
    Network
    Shipping Point
    Ship_To_Party
    Plant
    Storage Location
    Planned Goods Movement Date
    Delivery Type : LP
    Sales Organization
    Distribution Channel
    Division
    Item Number
    Please help me on this.
    Thank you.
    with regards,
    Muthu Ganapathy.

  • After "Replace with clip" the original clip can not be deleted from the project - why?

    After using "replace with clip" to replace clip A in the timeline with a new clip B , clip A can not be deleted from the project anymore.
    If you try to delete clip A, you get a warning, that it still has references in one or more sequences.
    If you continue and delete clip A, it seems to be deleted - at first!
    Unfortunately if you save and reopen the project, clip A is restored to folder "Recovered clips".
    It's not possible to really delete it.
    I also did not find a way to unlink clip B from A .
    The only thing you can do, is to revert the change by "Restore Unrendered" in the clip context menu. But that's obviously not helping
    I dont know if this is a bug or a feature. I understand, that it can be useful to undo the "replace clip" function, but why would anyone not want to be able to delete the original clip at all?
    help how to fix this problem is greatly appreciated!
    I use Premiere Pro CC 2014.2 (Win7 64bit)

    I'm sure it has nothing to to with other sequences.
    You can easily reproduce this behaviour:
    1. create a new project
    2. import 2 clips and name them "A" and "B"
    3. put "A" in the timeline
    4. ALT-drag "B" over "A" in the timeline (or right-click "A" in the timeline while selecting "B" in the project files and select "replace with clip ... from bin")
    5. delete "A" from the project files
    6. save and close project
    7. reopen project
    => "A" reappears in "Recovered clips" and can not be deleted.

  • The package file is missing from the project directory

    Today after working in SSIS all day with no problems, I re-opened one of my projects and got the message:
    The package file ‘package_name.dtsx’ is missing from the project directory. This package has been skipped, and project will continue to load.
    So two of my packages loaded and all remaining packages where skipped, one pop-up dialog for each “missing” package. I then looked in my project directory and all my packages are still there.
    1. Has anyone experienced this and found why this happens?
    2. Can I just import my packages again and be good to go?
    Update:
    I discovered that this had to do with renaming my packages in SSDT. For some reason the name changes did not get saved into the project .dtproj file. I was able to correct by renaming the .dtsx files in the project directory to their original name. Then
    I re-opened the project, renamed the packages to the new names, saved and closed all packages. At this point you need to save the project, which actually wasn't really straight forward. You need to highlight the project name in Solution Explorer
    and then from the File menu select 'Save Selected Items'. This updates the .dtproj file.
    Upon closing SSDT, a dialog SOMETIMES appears asking you to save the project, after selecting Yes, the .dtproj file also updates. However, I've realized that upon closing the project, that the dialog asking to save the project does not always appear,
    depending on what has changed in the project. To be safe, use method previously described, especially after renaming packages. Also, if SSDT happens to crash after you have renamed a package, the project will not re-open properly.

    I remember one such occurrence when I used Source Control (if I recall right it was TFS), and yes, you can simply right-click on the packages folder and choose 'add existing package'.
    But check for project file perhaps it has a wrong reference. E.g. something from the outside manipulated on the package files.
    Arthur
    MyBlog
    Twitter

  • Open multiple images from the project bin

    In Elements 9 I can only seem to open 1 image from the project bin at a time! What am I doing wrong?
    Bob Dunkerley.

      You need to double click on your main image and then drag your second image up from the project bin. That creates separate images on separate layers.
     

  • Saving Edited pics from the project bin

    I am a little rusty as I havent used my PSE 9 for quite some time and I cant remember how to save the files that have been edited in the project bin.  I click on File - Save As........But it will only allow me to save one pic at a time.  Thats it.  Can someone please refresh my memory on this.  I may be doing it all wrong..

      You need to double click on your main image and then drag your second image up from the project bin. That creates separate images on separate layers.
     

  • AE CS4 Crashes when I drag media from the project panel to the timeline

    Hello,
    I have a problem dragging media from the project pannel to the timeline.  Several times a day AE will crash when I do this.  Currently I'm using the latest MAC Pro with 11 gig of Ram and Duel 27 inch monitors.   Everything worked fine in CS3, but when I upgraded to CS4 I started having this issue. I have AE spread over both monitors.  Could that be a problem?  Are there any know issue with dragging?  Any ideas?
    Thanks

    Magiebabel:
    Since there are millions of context-specific reasons why this could happen -and also considering it's not happening to the majority of users out there-, it would be really helpful if you could fill out the Adobe Crash Reporter dialog that pops up when AE crashes (it just asks for what you were doing when the app crashed, and your e-mail info). When you send that, it includes a report about the crash that can be very useful to help the engineers figure out why it crashed.
    Here's a blog post on what kind of data is sent through the Crash Reporter and why is it so important that you fill it and send it, if at all possible.

  • Media Encoder export a different font from the project file

    HI
    Media Encoder export a different font from the project file when I use a installed font
    The problem doesn't occur when exporting directly from Premiere 
    Any ides why?
    Thanks

    Hi! This also happened to me quite a few times with different fonts. Your fix worked, thank you. I don't think it's the font since, like I said, it happened with a few fonts, but just in case I was using Mf Young & Beautiful in TTF format.
    Are there any side effects to turning off "import sequences natively"?

  • Select a range from the Project window in iMovie 10.0.3

    In iMovie 10.0.3, I can no longer select a range of frames from the Project window; when I left click, the whole clip highlights yellow.  I can still shorten the clip from the ends, but not select any range within the clip.  What gives? Thank you.

    GOOD GRIEF!  That did it, THANK YOU!  I wonder why they added this 2 second delay in the current version... regardless, THANK YOU SO MUCH!

  • Aperture, why when I delete from an album it deletes it from the project folder

    Aperture, why when I delete from an album it deletes it from the project folder also.
    I thought that it was the other way round, in that the library was not the main entry.
    I have 10 project folders and 6 albums and I want to remove the albums and keep the projects "as is"
    I am unsure as to how I wound up with albums in the Aperture program.
    thanks
    Greg
    Lamont

    Never used the Trash icon either (and generally don't show the Toolbar).  But at least the Tooltip is correct:
    Now that I think on it, clicking "Trash" _should_ put the item in the Aperture Trash.  The confusion comes from the use of "Delete" -- specifically using a key with that label to execute a command that changes based on not only what kind of item is selected, but where the item is located.  So in this case (let me parenthetically add I have yet to take part in my morning caffeine ritual) "Delete" in the Tooltip does not equal "press and release the 'delete' key", but rather is used as a verb (rightly, imho).
    Not sure what a better design might be, but perhaps at least popping up a window saying, "The selected items are Images in an Album.  Would you like to remove them from the Album, or move them to the Aperture Trash (which will delete them from the Project they are in)?".
    Greg -- I suggest using the context-sensitive menu (a/k/a "right-click") to select the command you want:
    Message was edited by: Kirby Krieger - formatting and clean-up.

  • How can I see the history of Team Members added & removed from the Project

    Dear Folks,
       Would like to know,  if there is a  report / change document report, on the History of Team members
    being added / removed from an active project.
    Regards,
    Owais...

    Hi Owais,
    Try using CN60 report to see added & removed team members from the project.
    Regards,
    Sandeep