hi
we have 2 companies A, B. Company A receive order and give Company B to production, then Company B directly ship to customer. We are using deliviery plant for this scenario. However, sometimes the production will via Company A, then Company A delivery the product to customer. In this case, using delivery plant is not a good way. As the product require to stay in Company A for few days. any suggestion in this case? thanks

Looks like its a stright forward Inter company transactions.
in the first case it is a intercompany sale where company A receives the order and you change the Delivering plant to company B's Plant so that the delivery is triggered from company B.
in the second case, you trigger a  Inter company Plant to Plant  stock transfer requistion from Company A to company B , and there by the stock comes to A and from comp A you can ship to to the customer.

Similar Messages

  • Purchase and sales flow resulting from 'production in other plant'.

    Dear all,
    When using the procurement type 'P' (production in other plant), materials are consumed in plant A and goods receipts from production order happens in plant B.
    When plants A and B belong to different company codes, SAP generates a cross-company document. Within the receiving company, the offsetting account for the stock account is the cross-company clearing account.
    This posting is generally not sufficient as legal and tax requirements ask for a sales and purchasing flow between the 2 company codes. Therefore many companies need to 'develop a solution' to complete this posting 'after the facts'.
    Does anybody know whether this additional posting exists under the form of an 'add-on' or additional solution to the standard made available by one or another partner of SAP ? Note that the starting point for this question is important : our company wants to use the 'production in other plant' flow because the native purchase and sales flows are too much time consuming.
    Thanks for your help.
    José Beghein

    Hi all,
    I want to be a bit more accurate here :
    The produced material in plant B has a special procurement type code (MARC-SOBSL) which in its definition contains procurement type E (BESKZ) and special procurement P (ESOBS). It is special procurement P that triggers the 'production in other plant' behaviour. The production plant (WRK02) is also specified in the definition of the special procurement type code.
    Kind regards.
    José Beghein

  • Production at other plant

    I have created sales order for material X. In Material BOm of X there is material y with special procurement 80 ( production from other plant ) in line item of Bom.
    When I do MRP MD01 in first plant  then system does not create planned order for material y in other plant.
    But when i do MD50 then system creates planned order in other plant.
    Also when production is completed in other plant for material Y then it does not built stock in First plant but it creates sales order stock in other plant.

    Mayuresh,
    Sorry for the very late reply. I do not think you need to built stock of Y in the first plant. You can just do good issue of Y (in stock in 2nd plant) to the production order of X (the first plant). 
    If you need to have stock of Y in first plant then you will need to manually do a plant to plant transfer posting goods movement.
    Hope this helps. If you have additional questions please come back.
    Thanks,
    Ram

  • MM - Daily Report of the materials received from other plants

    Hello
    I want  the daily report of all the materials received from other plants i,e by stock transfer. Is there any way to get this information from the standard reports
    regards
    Ravi Pal

    Dear Prashant
    i checked with this transaction but the problem is that this gived the report for only the GR taken against STO with SD Delivery i,e with or with out billing. the system is not picking the STO with MM delivery whan we enter the supplyiny plant as u said
    pl check this
    thnaks
    regards
    ravi pal

  • Production in other plant for finish and semifinish

    Hi Friends,
    We have following scenario:
    i)    Finish Product FP1 and Semifinish Product SF1 exist in both Plant X and Y.
    ii)   BOM for FP1 consists of SF1.
    iii)  SF1 is produced in Plant X and FP1 in Plant Y.
    iv)  Planning plant for FP1 is X.
    v)   I have tried with special procurement key 'production in other plant'.
    vi)  SF1 is produced in Plant X and GR done directly to plant Y for consumpton to FP1.
    vii) FP1 is produced in plant Y and GR done directly to plant X.
    Here instead of doing GR  directlyto the consuming plant the client wants to do Stock Transport for both SF1 and FP1.Please suggest any method to achieve this.
    Thanks in advance
    Shiva
    Edited by: Shiva Sharanappa on Apr 24, 2009 3:37 PM

    Hi,
    For Halb: DepReq in receiving plant and no receipt elements in prouducing plant.
    I am expecting also for Halb: Purchase Requisition in recieving plant(Y) and a planned order in producing plant(X) just like Fert.
    You stated you have DepReq for SFG in PlantY (receiving plant), nut MRP did not generate prourement proposal (PurReq) for it.
    In this case you should check the planning situation (e.g. whether you have sufficient stock to cover the requirement). If the procurement proposal is missing and this do not originate from the planning situation (e.g. stock level, stock like elements(STO, existing PurReq, etc.)), you should check your master data settings (e.g. MRP type) - if your master data settings are proper, MRP should generate procurement proposal (please be aware that in case of "VB" MRP type system watches the so called reorder point!).
    So, second MRP run should generate the mentioned PurReq for SFG (in PlantY) and at this moment you should get requierement in PlantX (that produces SFG). Third MRP run would generate procurement proposal (PldOrd) in PlantX.
    Please check master data (BOM, material master) settings of SFG.
    Regards,
    Csaba
    Edited by: Csaba Szommer on Apr 26, 2009 8:50 AM
    Edited by: Csaba Szommer on Apr 26, 2009 8:50 AM

  • Withdrawal from other plant- sales

    Hi dudes,
    suppose if i am using 70  special proc. key for semifinished materials and are planned in other plant gets consumed for FERT materials order in the main plant.
    suppose if i maintain the sales views for these semifinshed materilas in the main plant and can i do the PGI for sales order from other plant to main plant where the sales procesing is happening.
    thanks in advance
    Robert

    Special procurment key 70 is reservation from FERT plant to the supplyiong plant.
    Against this reservation you need to issue the material? Is it your scenario?
    As I know the material will be withdrawn duting backflush from the supplying plant directly
    If you want to sell the raw material from supplying plant to production plant, then you need to set up STO, in OMGN.
    Since usually we use it for inter company tranfer and billing, I am not sure whether you can do it for the plants with in the same company code.

  • MM01 -- Update Was terminated while copying the material from one plant

    Hi Experts,
    While I am trying to copy the material from one plant like ETPE to another plant ETPZ , its telling that material created.
    But when we try to display the created material in MM02 for plant ETPZ , it says that material does not exist.
    Note : After creating the material , if we try to move any transaction code it shows the error message box and  says that Update was terminated .
    Kindly help us to resolve this.
    Regards,
    Vijay

    Hi rob,
    we have put the debugging , if there is any badi , enhancement the debugger would have gone to exit or enhancement line but its not going to any where.
    and I have checked in sm13 ..
    its giving the error like update was terminated
    from funtion module : MATERIAL_UPDATE_DB
    Report name :      LGRAPU37
    row : 360.
    ABAP/4 processor: POSTING_ILLEGAL_STATEMENT
    but if we go and see in the row 360 ...
    CALL SCREEN 100 line only
    is there , even if we put the breakpoint in this line , while we are debugging , debugger is not going to that line .
    Note : if we see the screen 100 it shows the empty screen.

  • Transfer the material from one plant(non valuated) to another plant valuat

    Hi All,
    How to transfer the material from one plant(non valuated) to another plant valuated.
    Which Goods Movement type we required to use.
    Regards,
    Amit Shah

    Hello,
    Please refer the link below. hope it could be a help.
    stock transfer plant to plant
    split valuation
    Regards,
    Jana

  • Good receipt for job work from other plant

    Dear Experts:
    1.Material Received from Other Plant for job work with challan and how to bring the Material into Stock at receiving plant.
    The same material stock number available in this plant also.
    Regards,
    Sridhar.N

    Hi,
    You could use serial number concept or bacth managment here to separate within the material code.
    Regards

  • Production in other plant, Sloc determination for prod. order

    Experts,
    we are using production in other plant. Demand in plant A, Router & BOM in plant B. Mfg. should be done in plant B. The components in plant B are Prod.stor.location 0003 (MRP 2 View).
    If I create a production order the system always uses Stor.Loc 0001 in component overview and for with draw material.
    My expectation was that system uses Sloc out of MM of plant B. What might be the reason for that behaviour ?
    Thanks in Advance
    Jörg
    Even if I put Stor.loc 0003 in BOM line Item system goes with 0001 in prod.order.

    JORG,
    I am assuming you have raw materials in plant B. In the BOM of material in plant B, maintain storage location as 0003 for all line items and do read PP master data for the production order on current date so that correct storage location is picked up.
    Also check if production versions are maintained and what is the issue storage lcoation maintained in production version?
    check and revert,
    Santosh Sarda

  • I cant enter the serial number i received when i bought the product from softwareking

    i cant enter the serial number i received when i bought the product from softwareking

    May I ask
    1. What they charged?
    2. What exact product and version?
    3. What message you get?
    Please don't post the serial number!

  • PR should generated from only centralized plant not from other plants

    Hi Friends ,
    I am having 5 plants.
    Plant- A , B, C, D, E, F
    A is the centralized purchasing plant.
    Others are manufacturing and sales plant.
    So all my Purchase requisitions should be generated by plant A only. (Not from other plants) How can I make this?
    Regards,
    Mahesh.

    You can restrict PR creation in other plants by using authorisation object M_BANF_WRK.
    Activate this object via SU24 for transactions ME51 or ME51N and then create a role in PFCG with this object or add this object in your existing roles and then assign users to this role.
    Keep in mind do not link plants to this role which you dont want to used for PR.
    Hope this clears you.
    Njoy SAP...

  • Is there any way to get the files from other computer ?

    Hai all,
    I have 2 computers connected. I know the IP address of other computer. Is there any way to get the files from other computer. (for e.g. I want to get the files from specific folder. In Java netwroking is it possible? (Any programs)
    regards,
    Namanc

    Bro Take it easy.
    Think you need to send a Image file named ("abc.gif")
    now develop a server using ServerSocket and connect it in local IP and any PORT
    For example i think ur server is connected in "localhost" and 9000 port.
    Now make ur server educated using some commands.
    For example:
    FileName: <File Name String>
    [Means new file is sending by connected client]
    FileSize: <File size long or int value>
    [ So that ur server can determind about the total length of sender file]
    DataModeOpen
    [Now your client will send its image data, this command means your client software is sending data]
    fjadlkfjaofaijojfwoeiurfodkjflsajlfksa
    l23j4lj23lkjlasjfoq23j4rokjelfkjasldkf
    2o3j4lk2j3ljslakdjf2l3j4 l23kjlk23k4j
    DataModeClose
    [Means file sending finished]
    Close
    [Means your client connection is closed]
    Now develop a client supporting this command.
    For example(Server):
    String getFileName=null;
    long getFileSize=0;
    public handleCommand(String getCmd) {
        if(getCmd.startsWith("FileName")) {
                String[] splitData=getCmd.split(":");
                this.getFileName=   splitData[1];
                outPutStream.writeBytes("+OK");
        } else if(getCmd.startsWith("FileSize")) {
                String[] splitData=getCmd.split(":");
                this.getFileSize=Long.parseLong(splitData[1]);
                outPutStream.writeBytes("+OK");
        } else if(getCmd.startsWith("DataModeOpen")) {
               //data mode open so receive data
              receiveData();
              outPutStream.writeBytes("+OK");
        } else if(getCmd.startsWith("DataModeClose")) {
              //close client socket
             getClientSocket.close();
    }For client:
    DataInputStream dataIn=null;
    BufferedOutputStream bout=null;
    public sendFile(bytes[] getBytes) {
            //if ok found then do other or show error message
        if(sendCmd("FileName:"+getFileName)) {
            if(sendCmd("FileSize:"+getFileSize)) {
                if(sendCmd("DataModeOpen")) {
                   bout.write(getBytes);
                } else {
                   showError(3);
            } else {
                   showError(2);
       } else {
            showError(1);
    }i think it will help u

  • How to read and store the documents from other system to own system.

    Hi Experts,
    i need to read the document from other system (Say from other connected R/3 system) and then i need to save it in my system.
                     Please suggest how would i proceed?
    Any helpful suggestion will be rewarded with points.
    thanks
    Snehasish

    Hi Abaper
    I think I havent explained my problem well. Here I am explaining it again..
    I want to pull an  *.excel/ *.csv file through ABAP code.The target file that I want to access in my ABAP code is stored into another PC in the same Local area network under some directory say 'c:\temp\credit.csv'.
    I have the logon information of the target file's  PC.
    Please help me with code if anyone of you having.
    Thanks in advance.
    Rgds,
    Snehasish
    Edited by: Snehasish Das on Apr 29, 2008 2:18 PM
    Edited by: Snehasish Das on Apr 29, 2008 2:33 PM

  • Please, I'm in Brazil. I can buy items in the store the USA from other countries?

    Please, I'm in Brazil. I can buy items in the store the USA from other countries?

    No.
    (65965)

Maybe you are looking for