We are planning for SAP upgrade in our Production environment and we are facing the below listed constraints and need your advice on the options to peform ECC Upgrade.
1) Present HW resource is already facing bottleneck and so no additional load can be added.
2) We have a completely new HW environment due to which we are unable to perform the test upgrade.
Also, is there anyway to perform the Prepare Activities on new hardware (copy of Production system) first and then do the delta data migration for update of transactional data from present production system to new system (Prepare Activities done on this system) without affecting the Prepare Activities data.
Thanks & Regards,
Pratap

Hi Pratap,
You can first make a copy of you production system on new hardware by homogeneous system copy. Then do the test upgrade if everything will be fine. Then as suggested earlier migrate your production to new hardware and then do the upgrade.
Thanks
Sunny

Similar Messages

  • DATA Migration Strategy of Inventory from one SAP system to another

    Hi,
    We are migrating data from one sap system to another due to business split . I would like to know what are the considerations, dos and donts for inventory/stock balance  migration.
    Appreciate your responses on the same.
    Kind regards,
    Tanuja

    Hi
    Here are some of the links for Data migration in SAP which may be really helpful for you..Please have a look at them.
    http://www.packtpub.com/article/data-migration-sap-business-one-part1
    http://www.sap-press.de/download/dateien/1468/sappress_migrating_your_sap_data.pdf
    http://sceisqaweb.sc.gov/documents/Agencies-Approach-and-Plan-for-Data-Conversion.pdf
    Thanks.

  • Data migration for SAP E-Recruiting

    Hi all,
    We are looking for a standard way to migrate data from a nun sap system into SAP E- Recruiting.
    Is there any way for doing so?
    Thanks,
    Sharon

    There is no standard way available for data migration in SAP for E-recruiting.
    As it believes in the concept of creating new data and a new talent pool.
    Regards,
    Divya

  • How to make data available in SAP PI from SAP BI

    Hello All,
    I have certain data in a INFOCUBE ie in SAP BI and as per my requirement i want to push that data to SAP PI
    Can I get to know the process to make data available to SAP PI from SAP BI..?.
    It would really helpful if i get the step by step procedure for the same.
    Thanks in Advance.
    Regards,
    Foram

    Hi,
    SAP PI is the interface to move file from one system to other system like BI, R/3 etc.,
    Create open hub on top of Info cube based on your requirement. Create logical path and assign physical path to logical path using T-code FILE. Provide that logical path in Open hub destination where the file will be placed. Then SAP PI team will pick that file and process that file as per requirement.
    Thanks & Regards,
    Chandra Sekhar.

  • Full and delta Data loads in SAP BI 7.0

    Hi,
    Kindly explain me the difference between full and delta data loads in cube and DSO.
    When do we select change log or active table(with or without archive) with full/delta in DTP for DSO.
    Please explain the differences in data load for above different combinations.
    With thanks and regards,
    Mukul

    Please search the forums. This topic has already been discussed a lot of times.

  • SAP Upgrade from 4.7 to ECC 6.0 connected to BW 7.0 Best Practices

    We are upgrading SAP R/3 4.7 to ECC 6.0.  We have been running live in a BW 7.0 environment. We have done some enhancements for 2LIS_11_VAITM -  Sales Document Item Data  and 2LIS_13_VDITM - Billing Document Item Data datasources.   We currently have a test instance that has been upgraded to ECC6.0.
    What are the best business practices for testing BW to insure data transfer and enhancements are working correctly?
    Eg. Should we connect the ECC6 instance to BWD and test there OR upgrade R/3 TST that is connected BWD  and test there OR Upgrade QAS and test in BWQ.
    Thanks in advance . . .
    Edited by: RWC on May 4, 2011 6:26 PM

    Hi RWC,
    the plug-in will change slightly, you may notice differences in the screens of RSA2 and others after the upgrade.
    Regarding best practices: In a recent upgrade our project team decided to create a parallel landscape with a new, additional Dev and QA on the R/3 side.
    We connected these new systems to a BW Sandbox and the BW QA.
    We identified all datasources, transfer rules and infopackages in use in production and recorded them with related objects onto transports in BW Dev. Before the import into BW Sandbox and BW QA we adjusted the system name conversion table to convert from old R/3 Dev to new R/3 Dev in order set up all the required connections for testing with the upgraded R/3 systems.
    After the go LIVE of the upgrade we renamed the old R/3 Dev system in BW Dev and ran BDLS to convert everything (speak to your Basis team). That way we made sure not to lose any Development and we got rid of the old R/3 Dev system.
    Take a look at this post for issues we encountered during this project and test everything you load in production.
    Re: Impact on BI 7.0 due to ECC 5.0 to ECC 6.0 Upgrade
    Best,
    Ralf

  • SAP Upgradation from 4.5B to ECC 6.0

    Hi all,
    We need to upgrade from 4.5B to ECC 6.0. Gathered all the information abt. the 4.5 B system...Its on AIX using ORACLE.
    I want to know few more info. with your help. i have access to the system through GUI, but didnt have OS level access..
    1.) How to know whether  the system is CLUSTER configured, any transaction?
    2.) I didnt find any Upgradation Guide particular to AIX, can u pls. guide me the path for that in SMP?
    3.) How to check whether its using any third party tools(Like Fire Fighter...etc) and any usage types configured(Like PI, BI...)
    please guide me in knowing the above through GUI?
    Thanks,
    Subbu

    Hi,
    Roadmap is the recomended way to manage the Upgrade project, but this will not make anything automatic. If you don´t have the knowledge and time to configure the project in Solman then just follow the Upgrade Guide. In this Roadmap is included Technical and Funtional processes and it is an excellent starting point for the project but as already said, if don´t have the knowledge or any other person from the team either, then don´t worry much about it althoug it is imperative that a good Project is designed before starting the process either using MS Project or any other software, after the first tests you will have to adjust times for next upgrades.
    Buy the way in the upgrade guide there are some sections specially dedicated to AIX but most parts of the process are the same for any OS/DB combo. Basically check prerequisites, do prepare, fix what ever is necesary and then run upgrade process.
    Read the Upgrade Guide 2 or 3 times to get a clear Idea on what should be done before, during and after the upgrade process, read all related notes and have them printed in case of any problem.
    AND you should have access to OS level, if you don´t then when doing Prepare or Upgrade then you won´t be able to look at the logs and that is Vital during the process. Also need to have access to SAP directories to check and change files like copying upgrade DVD's, upgrading R3trans, TP, etc so explain that to them or make one of them to be next to you.
    Good Luck

  • Delta data changes are not reflecting from ODS to another infocube

    ODS1 --->Infocube1  - Field1,field2,field3
    ODS2 -
    > Infocube 2  -
    Field 2-1,2-2,2-3,field2-4
    Both datasource information are totally different.
    Delta changes are captured in the field3 in ODS1 and Infocube 1 also.
    Field3 and Field 2-3 is the same field .Infocube 2 - I have included infoobject and populating the value from ODS1-Field3.
    The question is
    Whenever I capture the changes from ODS1-field3 -the similar changes also needs to be updated here in infocube2 -field2- 3.
    Start routine : I have created code like ,
    SELECT field1 field2 field3
      INTO CORRESPONDING FIELDS OF TABLE IT_field
      FROM /BIC/aods1.
    Update rule routine : Select the field2-3 in the characteristic- routine
      READ TABLE IT_field INTO LS_field
      WITH TABLE KEY
      field1 = COMM_STRUCTURE-field2-1
    Field 2 = COMM_STRUCTURE-field2-2.
    Result = LS_field -field2-3.
    If I load the full load to infocube 2  -no problem.
    Is their any other way Can I capture the transactional data changes in infocube 2.
    Advance thanks

    Thanks for quick update. You are right.
    There is no problem from  ODS1 --->Infocube1 - Delta is working properly.
    My question is ,
    ODS1 has a field 3. Whenever new changes happen for this field3 - I have to capture the simialr changes in the Infocube 2 and the fieldis 2-3.
    field3 and field 2-3 is the same field infoobject .
    Whenever the changes occurs inthe tranasation - ODS1-field 3 will capture the changes. How can I capture the similar changes in Infocube 2 and the field 2-3.

  • Data extraction into sap table  from legacy oracle database

    Hello All,
        I have a scenario where I have two different software systems (SAP and xyz systems), where a intermediate table will be created in between the two systems that is shared. Data will be updated by the xyz systems into this shared table. Now, my questions regarding this shared table.
       1) Can we write some program or something to get the data from shared table to update the SAP?
       2) If possible send me the suggestions
       3) Please also send me the sample code to get the data from the shared table
    Thanks in advance,
      SDN powered

    this shared table should be compatiable to sap fields...write code to fetch data from this table and assign data to appropriate fields in SAP and insert the data into sap.
    1. Push mechanism
    Write a RFC on SAP side to insert entries into the table.
    Call the RFC from xyz application passing the data you want to insert.
    2. Pull mechanism
    Write a ABAP Program, where you can somehow read the data of the xyz application and insert data into the table.
    3. Flat file
    Dump the data from xyz application into the file.
    Write a ABAP program to read the file and update the table.

  • SAP Upgradev from 4.7E to ECC 6.0

    Hi,
    We are doing SAP ecc 6. 0 upgradation from SAP 4.7EE.( database is 10.2.0.2 & WIN 2003 server)
    After ran prepare we are getting the error message as mentioned below:
    INFO> The following values may be preliminary because of
          free space consumption during productive operation and
          additional free space requests derived in a later stage.
          Conversions of modified tables can require additional space.
          Please use the largest free space request printed,
          which are the values at the very end of this file.
    ERROR> Insufficient free space in the database as follows:
    Create TABLESPACE PSAPDIMD             with 127 MB
    Create TABLESPACE PSAPDIMI             with 127 MB
    Create TABLESPACE PSAPODSD             with 139 MB
    Create TABLESPACE PSAPODSI             with 139 MB
    Create TABLESPACE PSAPFACTD            with 127 MB
    Create TABLESPACE PSAPFACTI            with 127 MB
    Create TABLESPACE PSAPPTU700           with 33772 MB
    INFO> To adjust the size of your tablespaces, you may use the commands
          in file 'D:\usr\sap\put\log\ORATBSXT.LST' using the 'brspace' utility.
          Please copy the file before making changes, as it may be
          overwritten in subsequent upgrade phases.
    INFO> During the upgrade, the new SAP kernel
          will be installed. All files and subdirectories
          in directory D:\usr\sap\PTU\SYS\exe\run which are not used
          in Release 700 will be removed.
          The files from "dbclient.lst" in the kernel directory are kept.
          Files and subdirectories can be protected from deletion
          if they appear in a file "protect.lst" in the same directory
          (each protected name in a separate line).
          For security reasons, directory D:\usr\sap\PTU\SYS\exe\run
          should be saved in a backup.
    INFO> It is possible to upgrade the frontend software before
          you start SAPup!
       #===========================================================#
    PREPARE module General checks finished with status failed #
       #===========================================================#
       #=======================================================#
    Requests and information for module Activation checks #
       #=======================================================#
       #=================================================================#
    PREPARE module Activation checks finished with status succeeded #
       #=================================================================#
       #======================================================================#
    Requests and information for module Necessary checks for conversions #
       #======================================================================#
       #================================================================================#
    PREPARE module Necessary checks for conversions finished with status succeeded #
       #================================================================================#
       #=====================================================================#
    Requests and information for module Optional checks for conversions #
       #=====================================================================#
    Information:
    In file D:\usr\sap\put\log\TABCONV.LST you can see a list of tables
    which will be converted in your SAP System during the upgrade.
    The list of tables was determined at SAP and is not complete for
    your system. Other tables might have to be converted due to your
    modifications. The final list of tables can only be determined immediately
    before the conversion during downtime. The list contains the names and
    the size of the tables.
    INFO> The following values may be preliminary because of
          free space consumption during productive operation and
          additional free space requests derived in a later stage.
          Conversions of modified tables can require additional space.
          Please use the largest free space request printed,
          which are the values at the very end of this file.
    ERROR> Insufficient free space in the database as follows:
    Create TABLESPACE PSAPDIMD             with 127 MB
    Create TABLESPACE PSAPDIMI             with 127 MB
    Create TABLESPACE PSAPODSD             with 139 MB
    Create TABLESPACE PSAPODSI             with 139 MB
    Create TABLESPACE PSAPFACTD            with 127 MB
    Create TABLESPACE PSAPFACTI            with 127 MB
    Create TABLESPACE PSAPPTU700           with 33772 MB
    INFO> To adjust the size of your tablespaces, you may use the commands
          in file 'D:\usr\sap\put\log\ORATBSXT.LST' using the 'brspace' utility.
          Please copy the file before making changes, as it may be
          overwritten in subsequent upgrade phases.
       #============================================================================#
    PREPARE module Optional checks for conversions finished with status failed #
       #============================================================================#
       #==========================================================#
    Requests and information for module Modification support #
       #==========================================================#
    PLEASE SUGGEST HOW CAN WE REMOVE THIS ERROR.
    Thanks & Regards,
    Madhu

    Hi,
    >
    > ERROR> Insufficient free space in the database as follows:
    >
    >  Create TABLESPACE PSAPDIMD             with 127 MB
    >
    >  Create TABLESPACE PSAPDIMI             with 127 MB
    >
    >  Create TABLESPACE PSAPODSD             with 139 MB
    >
    >  Create TABLESPACE PSAPODSI             with 139 MB
    >
    >  Create TABLESPACE PSAPFACTD            with 127 MB
    >
    >  Create TABLESPACE PSAPFACTI            with 127 MB
    >
    >  Create TABLESPACE PSAPPTU700           with 33772 MB
    >
    >
    >  Create TABLESPACE PSAPDIMD             with 127 MB
    >
    >  Create TABLESPACE PSAPDIMI             with 127 MB
    >
    >  Create TABLESPACE PSAPODSD             with 139 MB
    >
    >  Create TABLESPACE PSAPODSI             with 139 MB
    >
    >  Create TABLESPACE PSAPFACTD            with 127 MB
    >
    >  Create TABLESPACE PSAPFACTI            with 127 MB
    >
    >  Create TABLESPACE PSAPPTU700           with 33772 MB
    >
    As you can see prepare is saying to create the tablespace. Please create above tablespace then prepare check will be successful.
    Thanks
    Sunny

  • HTML Page not appearing after SAP Upgrade from 4.6c to ECC 6.0

    Dear All,
    I am novice in ITS and IAC configuration stuff....
    Issue: We have a HTML page which shows a tree structure of Functional location and Equipments. A Z transaction is built to cater the requirement. User logs on to the HTML page navigates thru the Tree structure of Functional locations and equipments and the logs the workrequest or Break down details. In 4.6C every thing is working fine. But after Upgrade in Testing Server (We are not go live yet) we are facing a problem where the HTML page with tree structure is skipped off and directly the Z transaction is appearing on the web page.
    Did any one faced such issue? Any thoughts is highly appreciable?
    Thanks,
    Sanjay.

    Thanks Frank and Dhurairaj....and sorry for the delay in responding..
    I have checked my service in SICF and it is active. I also tried to create a new Service and now I am now getting "500 Connection timed out" error.
    Our Z transaction is ZW03 and Service name is ZW03_2.
    We are on Netweaver 7 (2004s)
    Steps I followed:
    1. Created a Service ZW03_2 in SICF (New Sub element) and then Activated.
    default host -> SAP -> bc -> gui -> sap -> its
    2. Created a folder ZW03_2 under SAP->Public->ITS (Transaction SE80, MIME Repository) and imported all MIME objects into that folder.
    3. Created a Internet Service ZW03_2 in SE80. Once I created a Service already there is blank folder Topic 99. Then I created two folders Mime Objects and HTML Templates. Imported all Mime objects into folder "Mime Objects" and Created templates in "HTML Templates" folder. Then I published ..
    After doing all the above setting then I tried to test the service and I am getting 500 Connection time out.
    Please let me know if I missed any step or if I have done any setting incorrectly.
    Thanks,
    Sanjay.

  • Data Migration(wm)

    hi..
    can anybody  explain me the steps involved in data migration.
    Especially storage  bin data migration into sap system from an excell sheet. If there is any documentation or screenshots related to the above topic can be very helpful.
    and also material master data migration....
    waiting sincerely for ur valuable resource.....
    thanks&regards

    hi,
    kindly maintain the wm1 and wm2 view in OMS2 transaction for all the material types that are to be created for the warehouse.
    Create a bdc with the help of abaper by maintaining the required fieds in wm1 and wm2 like stkremoval and stock placement storage section ,capacity in WM1
    In wm2 you maintain the LE qty and sut.
    ABAPER can create a recording for this if you give the requirements.
    Regards,
    velu

  • SAP Legacy data Migration Starategy/Process

    Hi Friends
    I would request you, if anybody let me knwo the process of legacy data migration into sap. What are steps I have to follow while doing legacy data migration. My questions are:
    1) How to upload GL balances from legacy to SAP
    2) How to upload Vendor and Customer open items into sap
    3) Asset balances How to upload
    4) what is the use of Migration clearing accounts.
    Kindly provide if any documents for legacy data migration into sap.
    Thanks in advance
    Rao

    Dear Rao,
    Just check the bwlow link you can understand easly to upload the balances.
    http://www.saptechies.com/sap-pdf-books-download/SAP_Go_live_strategy11248141773.pdf
    Check the bwlow procedure for the same way do it.
    First create 5 Dummy GL codes. These GL code should be zero at the end of uploading balances.
    1     GL Offset Account               Dr
              Asset Offset Account          Cr
              AP Offset Account          Cr
              Sales          Cr
              Other GL's          Cr
    2     Cash               Dr
         Consumption               Dr
         Asset Offset Account               Dr
         AR Offset Account               Dr
         Material Offset Account               Dr
         Other GL's               Dr
              GL Offset Account     x     Cr
    3     AP Offset Account               Dr
              Vendor 1          Cr
              Vendor 2          Cr
              Vendor 3          Cr
    4     Customer 1               Dr
         Customer 2               Dr
         Customer 3               Dr
              AR Offset Account          Cr
    5     Fixed Asset 1               Dr
         Fixed Asset 2               Dr
              Asset Offset Account          Cr
              Acc. Depreciation Account          Cr
    6     Stock Inventory Account               Dr
              Material Offset Account          Cr
    Regards,

  • Module for data migration from pdf(zip) to pdf(unzip)

    Hi all,
    I am Working on Data migration using SAP XI with out using IR.
    I want to Zip the pdf file in the Sender CC and unzip the same in Receiver CC.
    I am using PAYLOADZIPBEAN to zip the pdf.
    Did any one work on zipping and unzipping the PDF files?
    Kindly let me know the Module I need to use for the same.
    Thanks,
    Sree

    Hi Sree,
    Please go through this blog and follow the step by step procedure for configuring your scenario.
    /people/stefan.grube/blog/2007/02/20/working-with-the-payloadzipbean-module-of-the-xi-adapter-framework
    Its a nice blog and i have configured my scenario using the same already.
    Thanks and Regards,
    Sanjeev.

  • Data Migration - Data Models Dependency

    Hi,
    In major ERP data migration and transformation project from legacy to SAP or from SAP to SAP, one should finalize the sequence in which data should be migrated. e.g. Vendor data cannot be migrated before customer data, or tax data should be uploaded first then customer data .. etc. Is there available any best practice or reference for such dependencies ? Primary models and secondary models which depend on primary models ?
    Please share such content if you have, I'm sure it will be helpful to many.

    The best way is to use iTunes. Back up your old iPad. Unplug it, plug your new one in and go through the set up process. When you get the question 'set up as new or restore from backup' choose to restore from the backup you just made. Your app data and information will be put onto your new iPad.
    You may need to redownload apps, but since the app data is already there, you should not lose progress on games or the such.
    http://support.apple.com/en-us/HT2109
    has directions. You can also use iCloud backup, but I personally prefer iTunes since it takes the internet out of the equation and things are done locally (beyond redownloading apps if needed)

Maybe you are looking for

  • Problems upgrading from Dreamweaver 4 to CS3

    The website I manage is www.episcopal-dallas.org. Today, I upgraded from Dreamweaver 4 to CS3. In Design view, I can edit about half of the pages, but those of the other half (including the index/home page) have gray backgrounds (with a few exception

  • Filters used in a query

    Hi, Is there anyway we can know what filters are being used in a query. I am using 2 variables to filter my query.But the report gives me this warning "Invalid filter on ZCODE: Filter changed". This is a display hierarchy with no variables on this in

  • Cant update to 10.5.8 Keep getting "run preinstall script" b4 restart

    I dont know anything about scripts... I tried updating my mac mini and right before it restarts, it says that the install failed and says "run preinstall script for MacOSXUpdCombo 10.5.8" I cant even update my iTunes to 9.2 (it says the same thing ex

  • Get XML data into SAP

    Hi , Is there any function module to get XML data into SAP? If function module doesnt exist, suggest alternative to do it. Thanks, Shivaa...

  • Jive Software Lays Off 1/3 Of Staff

    In case you don't know that's software vendor of this forum site. And from last upgrade experience and this site performance, it's not hard to understand why http://www.techcrunch.com/2008/10/14/jive-software-lays-off-13-of-staff/ Kinda off topic, si