Dependent demand flow from SCM to ECC

Hi ,
Can any one explain, how the scm dependent demand can flow form scm to ECC.
scenerio-
I have 5 level of BOM , i need to plan up to 3 level in SCM and other needs to plan MRP in ECC.
Is it possible to transfer the dependent demand of 4rth level in ECC form SCM and run the MRP?
BOM are PDS explosion not RPM matrix.
Regards
Lav Mishra

Yes it is very much possible. MRP type should be X0 for material planned in APO and PD for not planned in APO.
X0- Means without MRP with BOM explosion so if you are transfering publishing planning results of APO planned material in ECC it will explode bom to plan ECC planned product in MRP.
Regards,
Santosh

Similar Messages

  • Need to control demand flow from APO system in the R/3

    HI Gurus,
    Kindly help me control the demand flow from APO system in the R/3.
    We want to change the timeline where demands coming from APO are given back to APW. The idea is to have a control table in APW where we can set a number of days or weeks by sales org / customer number. Within this number of days / weeks, no demand should be created / updated from APO system.
    Kindly advise the possible solutions to control Demand in R/3 flowing from APO.
    Thanks in advance.
    Naveen.

    Check user exit CIFPIR01 (inbound from APO to SAP).
    Rgrds,

  • Data Flow from SAP Source (ECC) system to SAP BI system

    Hi All,
    I wanted to know how data will be flown from SAP Source system to SAP BI system.Data flow should include
    1) Data will be flown by using the IDOCs?
    2) What all are the interfaces involved while data is transferring?
    3) What will happen exactly, if you execute the PSA?.
    If you have any info on this, could you please post here....I
    Regards,
    K.Krishna Chaitanya.

    Hi Krishna,
    Please go through  this article :
    "http://www.trinay.com/C6747810-561C-4ED6-B85C-8F32CF901602/FinalDownload/DownloadId-C2EB7035A229BFC0BB16C09174241DC8/C6747810-561C-4ED6-B85C-8F32CF901602/SAP%20BW%20Extraction.pdf".
    Hope this answers all the mentioned questions.
    Regards,
    Sarika

  • Replication Of Z Partner Functions from CRM to ECC

    HI All,
    We are creating the " Z Partner Functions " in SAP CRM & ECC.in our scenario partner functions flows from CRM to ECC and we want to replicate these partner functions from CRM to ECC.
    So can some onle please tell me how to do this?.
    Thanks in Advance,
    Arun

    1. Create the partner function in ECC
    2.  Assign the partner function to the relevant partner procedure in ECC
    3. Create a partner function in CRM
    4. Map the partner function as follows:
    Customer Relationship Management
    --> Basic Functions
    --> Partner Processing
    --> Data Transfer
    --> Distribution of Partner Functions from R/3 into CRM
    Create the following entry:
    Partner function in R/3         Function
    and also the below:
    Create a mapping entry for data transfer from CRM to R/3 via the
    following IMG activity in CRM:
    Customer Relationship Management
    --> Basic Functions
    --> Partner Processing
    --> Data Transfer
    --> Distribution of Partner Functions from CRM into R/3
    Create the following entry:
    Function     R/3 function    Type in R/3

  • CRM BP Identification number entries (Identification tab) from CRM to ECC

    Hi,
    I have a requirement to map the CRM BP Identification number entries (under Identification tab) from CRM to ECC alongwith BP flow from CRM to ECC.
    1. Is it mapped by standard framework and do we have any view in ECC customer master to display the identification numbers?
    2. If not, Is it stored in some table in ECC?
    Please suggest,
    Thanks.

    Hi,
    Were you able to resolve this as I am looking to do the same thing? From my investigation, I can't see anything standard that would transfer this data, although it does look like the Identification number is held within the BDoc.
    I assume the solution would be to map the field into an XD01 field (either a bespoke field or standard - we are planning to use Corporate Group) but i'm not sure how to progress this... I have found some FM's in table CRMSUBTAB which look like the right sort of thing so that is my next area to investigate.
    Please let me know if you have managed to solve this some other way!
    Cara

  • Planning Dependent Demand with Phantom Strategy (59)

    Hi
    We would like to maintain forecasts at a Phantom material level and consume this forecast based on dependent demand (Planning Strategy 59 in ECC and an equivalent custom strategy in APO). This works in ECC MRP, but does not appear to work in APO CTM.
    For example - Phantom Material P1 has a forecast. MRP and CTM behave the same, exploding this demand and planning for components. Now, a Sales Order comes in for A1 which is a parent of P1. MRP creates planned order for A1 and dependent demand for P1 which is set to consume forecast (based on the planning strategy 59). CTM also creates a planned order for A1and directly creates dependent demand for components of P1 but does not create dependent demand for P1 itself. Due to this, there is no forecast consumption of P1 leading to doubling of demand.
    Any suggestions how to get Dependent Demand to be created for Phantom materials (so that CTM behaves similar to strategy 59 in ECC MRP) ?
    Thanks
    Rishi Menon

    Hello Rishi,
    Hope you are doing well.
    Have you check the atp check mode. What value are you maintaining on check mode? What requirement type and requirement class are configured in ECC? There should be a class in ECC for Phentom Assembly and see if that is configured.
    Hope this helps.
    regards,
    Najam

  • Demand transfer from ECC to SNC using RSMIPROACT Programme

    Hi,
    Presently we are using RSMIPROACT to transfer demand (Planned independent Requirements-T-code MD61)from ECC to SNC.
    It transfers the demand always from version 02 and not from the active version 00.
    I want to know whether there is config to change this.We want to send through 00 verison also.
    Thanks and Regards
    Raghavendra Pai

    Hi Raghavendra Pai
    In ERP system, transaction OMPD. Each transaction has been assigned to active version.
    I believe in your case it is version 02 as active.(Guess)
    If you want both active version and other version data to be sent, then try to enhance the code in includes available in RSMIPROACT program.
    Kindly seek help of PP guy and ABAPER.
    Hope this helps, As per my knowledge we have different versions, so that we can simulate long term PIR and differentiate between various planning approaches.
    Best Regards
    Vinod

  • Block Credit Card information flow from ECC to CRM

    Hi All,
    Need help!!
    How to block Credit Card information flow from ECC to CRM? Can any filter be applied in any adapter objects for doing so?
    If so which is the adapter object and corresponding Table name. The ECC tables are VCNUM and VCKUN. But no adapter objects can be found for them in SMOFTABLES.
    many thanks

    Hi Bhasker,
    We had the same requirement. We implemented custom logic in the middleware user-exit to remove the Banking/Credit Card data from the Bdoc.
    Thanks,
    Munish

  • Background job not automatically poopulating Dependant Demand

    Hi Users,
    We've recently set up a POS & PA using the DP-BOM selection and characteristics, manually created PPM's and generated CVC's using the BOMS. All of this is set up fine in our SCM 7.0.
    The background job has created the forecasts for the ouptput products but NOT the input product.
    Now if I call up the parent material, and then choose to show the input products the dependant demand is generated. If I now return to the material with the dependant demand, it now shows the demand from the parent.
    Or, if the forecast is genereated interactively, then the dependant demand is poopulated.
    Is there an automated method to populate the dependant demand when using background jobs? I would like to think that we don't have to query every sales BOM parent in DP and drill into the input products to load the dependant demand?
    Please let me know if there is an easier way to do this as part of the background processing.
    Thanks
    Edited by: Paul_111 on Mar 31, 2011 4:20 PM

    Hi Andand,
    Thanks for your reply and sorry if my post is confusing.
    As far as the PPM with imputs A & B, output C - I have this relationship working and calcuclating demand in DP no problems.
    If I now add a new PPM combination inpput X, Y and output Z. Create the BOM CVC and TSO so its all set to go. Add to selection profiles and background jobs.
    Now, if I run the background job to create the forecast and this runs successfully. Now I check my products.
    Z has the forecast generated, X & Z have no dependant demand showing.
    The only way I've found that pushes the demand to X & Z is:
    - open product Z in demand planning and then choose the option to show input products from the header
    OR - from demand planning, select the univariate forecast to run interactively.
    My issue:
    The background job (if run alone) does not push the forecast on Z to X & Y.
    And if I show the input products or create forecast (as bove) the dependat demand is shown on X & Y.
    This is going to be a slow process if we have to do this everytime we run the backgound job.
    What am I missing when running the background job?

  • Dependent Demand not genarated

    Hi Experts,
    My client product structure starts from 1*****, 2***** and so on to 7****** that is we have 6 level BOM. Final FG is 1*** and 7*** is raw material. 1 will be procured from vendor1 by providing component 2 to vendor1. 2 will be procured from vendor 2 by providing component3 to vendor2 and so on. 7*** material is a standard procurement. So we are implementing sub-con scenario in SNP using SCM 7.0. So we created work centers and PPMs at sub-con locations (location type 1011 as only one product from one plant will procure from sub-con locations).  
    Could any one confirm the following master data settings I made
    1) Both FG and Components procurement type will be 'F' (External procurement) at plant. Where as at sub-con locations FG will be 'E' (In-house) and component will be 'F'.
    2) Transportation lane with sub-contracting defined for finished good between sub-con location to plant. Transportation lane between plant to the same sub-con location defined for the component with sub-contracting (not sure whether it should sub-contracting or standard procurement in the transportation lane) as we are using PPM
    With those settings I ran CTM and no PRs are generated. Where as when I ran SNP01 I got PRs only one 1 series and I didnt seen any dependent demand. I ran low-level code before running SNP01.
    Could any one guide me to get the PRs through CTM.
    Thanks,
    Naveen

    Hi Experts,
    For the master-data set-up in SNP, I got the following low level codes.
    SNP Low Level Code     Material     Location
    0          100057     Plant1
    1          100057     Sub-Con1
    2          201079     Sub-Con1
    3          201079     Plant1
    4          201079     Sub-Con2
    5          306574     Sub-Con2
    6          306574     Plant1
    7          306574     Sub-Con3
    8          506083     Sub-Con3
    9          506083     Plant1
    10          506083     Plant2
    11          506083     Sub-Con4
    12          600004     Sub-Con4
    13          600004     Plant2
    14          600004     Sub-Con5
    15          700002     Sub-Con5
    16          700002     Plant2
    Still I am not able to genarate the dependent demand. My Integration models for Storage Location stock and vendor stock active and no issues with those material ids.
    Could any one give some in-sight.
    Thanks,
    Naveen

  • Dependent Demand Planning of commponents

    Hi
    Following is the BOM structure -
    F (Finished Good) -
    > S1 (1st Intermediate) -
    > S2 (2st Intermediate) -
    > R (Raw Material)
    I am trying to plan the finished good (F) in an external system (like say xLPO / ECC) and transfer the dependent demand of the S1 thus created to APO and plan the balance materials S1, S2 and R in APO. Can this be done. I have tried it but it does not seem to work.
    Dependent demand of S1 is net getting transferred.
    Regards
    Deepak Joshi

    How have you tried to plan for S1 in APO? Moreover standard APO design says F to be planned in APO. If F is planned in APO then S1 / S2 and R are NOT to be planned in APO as you plan for Header product (and the important components) in APO not the other way round.
    Having said that you can get demand of S1 from the external system (not ECC) to APO BW and load that data in Demand keyfigure. If you are using Planning with BOM (DP-BOM functionality) then assig this keyfigure suitably to the dependent demand keyfigure.
    Otherwise this demand of S1 when released to SNP/PPDS should explode to S2 dependent requirements based on the SNP or PPDS PDS.
    Hope this helps,
    somnath

  • How to get the forecast data from SCM into BW

    Hello,
    Is there a table or Function module in SCM F&R  that can be used  to transfer the forecast data from SCM F&R into BW? I dont see any Business content datasources that has the forecast data.
    I would like to get the future forecast data. For ex, if there is a forecast for a material and Site for the next 52 weeks, I would like to retrieve
    the same from SCM. I dont see any business content. The closest would be 0FRE_ANA_WEEKLY_1. But it has only the past data, not the future data.
    Thanks,
    SBS.

    Hi,
    You would follow the same process as you would for getting data from a R3 system to BW, i.e generate datsources on the APO side and then set the extraction to flow from APO to BW. On the BW side, you'll need a source system for the APO, replicate datsources, set up update and transfer rules in the infosource and then load data to the data targets.
    Cheers,
    Kedar

  • BAPI_MOSRVAPS_SAVEMULTI3 creating unwanted Dependent Demand

    We are using the BAPI function BAPI_MOSRVAPS_SAVEMULTI3
    to create Production Orders to integrate WIP from a
    legacy system. The presence of PDS for the product on which the production order is created, makes the PDS assignment to the production order. But, it is also creating a depenedent demand for the component in PDS, which inturn pegs to the supply on the component. We dont want the dependent demand to be created and peg to the supply, as the supply is already reduced in the external system.
    We tried using PLANNING_MODE_USAGE parameter, but was not able to stop the creation of dependent demand.
    Any way around this?

    Hi,
    Do you need the PDS in the planning system (APO) at all in case you don't want to see the dependant demand. The BAPI
    BAPI_MOSRVAPS_SAVEMULTI3 documentation says:
    For you to be able to create an order, a valid source of supply must exist for in-house production. This can be a production process model (PPM) of the type PP/DS or a production data structure (PDS). The source of supply is then used to generate the order. The order structure (components, operations, durations, capacity requirements, and so on) is determined based on the explosion. If a valid source of supply does not exist, a 'dummy' activity is generated and the order is created without structure and with only a main component.
    We create production orders with dummy activities and only the output component using the BAPI without having the PPMs at the supply plant.
    Regards
    Vinod
    NB: Also try 'Deactivate Dynamic Pegging' option in the product-supply location master data in  the 'Demands' tab to ensure  the dependant demand does not peg to available supplies of the component.

  • CTM and Dependent Demand purchase Requisitions

    Hello Gurus,
    We have a business situation where there are 2 plants which can produce a finished product from a single input product.  It is much less expensive for us to transport the finished product than the input product.  We want CTM to force the plant with the supply of input product to produce the product and send it if that plant has capacity - only transporting the input product to the demand plant if there is no capacity at the supply plant.
    Plant A   Demand 100 units of Product X
    Plant B  Supply of 100 units of Product Y which can be used to create Product O
    PPMs for creation of Product at both plants.
    Desired outcome:
    If Plant B has open capacity to create Product X prior to due date, Plant B creates Supply of Product X from Product Y and transports Product X.
    If Plant B does not have open capacity to create Product X prior to due date, Plant B sends Product Y to Plant A which creates Product X.
    The supply may be at Plant A or Plant B so the scenario must be able to work in either direction.
    Currently, when CTM runs, it see the demand at Plant B and creates a planned order there, creating a purchase Requisition for the dependent demand.
    Is there a solution for this?
    Many thanks in advance,
    Sarah

    I have done some further testing of the system and have found that I can further clarify my question.
    consider 3 production plants situated roughly in a line with PLANTA located 1000 KM east of PLANTB and PLANTB located 500 KM east of PLANTC.  Because PLANTC is nearer to PLANTB, the transportation lane procurement priority for PLANTC to PLANTB is lower than PLANTA to PLANTB (making PLANTC the first to be considered at a procurement source for PLANTB)
    We have demand for a finished product at PLANTB.  We can create the finished material at PLANTA or PLANTC.  PLANTA has the input material in stock for creating the finished material.
    When CTM makes its planning run, it looks at the PLANTB demand and determines that PLANTC is the correct procurement source for the finished material.  It looks for the finished material at PLANTC and can't find it, so it creates a Planned Order to create the finished material.  In order to do that, it pulls dependent demand from PLANTA. 
    The result is that we are moving input material west 1500 KM to PLANTC and then moving the finished material east 500 KM to PLANTB.
    We have set our priority for moving input material very high, so it should be the last resort to move.
    It appears that CTM is looking at the priority of the finished material only when determining procurement source.  Is there any setting I can make to the system so that it will look at both the dependent demand priority and the finished material priority when determining procurement source?
    Alternately, is there a way to mark the ATP group EB as not being available during a specific CTM run (without removing the dependent material from the TLANE)?
    Ideallly, we'd like to be able to move the dependent material to another plant if the capacity at the plant it is currently in is too full.
    thanks in advance for any advice,
    Sarah

  • How it is possible to debug the transfer of an order from CRM to ECC

    Hello,
    how is it possible to debug the coding when a CRM sales order is replicated to R/3?
    The outbound of SCM APO and/or the inbound of SAP R/3?
    Thank you in advance.

    Hello,
    Data flow from CRM to R/3 is like below:
    - Write the data to outbound queue of CRM
    - Wrtie data to Inbound queue of R/3
    - Validation and Save in R/3
    So you can debug from CRM outbound queue, by de-registering the queue in txn:SMQR
    R3AI_<OBJECT-NAME> In case of Initial Load
    R3AR_<Request-Name> In case of Request Load
    R3AD_*                           In case of Delta load
    Similarly you can de-register the queue in R/3 as well to debug the R/3 inbound queue.
    As you might be aware that MW generic module CRM_UPLOAD_TO_OLTP, would be called for any data transfer
    between CRM to R/3. You can start debugging from this point.
    Hope this helps!
    Best Regards,
    Shanthala Kudva.

Maybe you are looking for

  • Itunes playlistless music won't go away

    Hello, Recently I switched the itunes I used to sync from Windows (Bootcamp) to OSX. I noticed in my library there was two of each song on my iphone (and my wife's ipod) So, I deleted all the music (by syncing no playlists) and looked at my phone and

  • Printing to pdf when running Windows in Boot Camp

    I have reluctantly installed Windows 7 on my Macbook Air (1.7 GHz, Core i5, 4 GB, OS 10.8.2). I run a simulation program which produces a report for printout. I would like to have the option of printing to pdf so that I can select pages for printing,

  • 9 beeps HP DC7700

    Hi all, I have HP DC7700 desktop, whenever I switched on the machine, it gives me 9 beeps with two second gap it starts again beeping. What I do is take out bios batteries from motherboard and place it back, after a while i switch it on again and it

  • Create accounting error :APP-SQLAP-100000,  ora-00000

    afer validate the AP credit memo. create accounting occured the error as below the first form 'NOTE :create accounting successfully' the secone form 'ERROR APP-SQLAP-10000:.........(x_rowid=AAAAHTUAAXAABIDYAA,X_invoice_id= 34345 ,ap_in:normal, succes

  • Workbench request released

    Hi, I accidentally released a workbench request for Asset Accounting in R/3.  I have tried numorously to delete the request even in R/3.  I now have an error when I try to change a query.  Is there any way that a request can be deleted/changed after