Dependent Demand Planning of commponents

Hi
Following is the BOM structure -
F (Finished Good) -
> S1 (1st Intermediate) -
> S2 (2st Intermediate) -
> R (Raw Material)
I am trying to plan the finished good (F) in an external system (like say xLPO / ECC) and transfer the dependent demand of the S1 thus created to APO and plan the balance materials S1, S2 and R in APO. Can this be done. I have tried it but it does not seem to work.
Dependent demand of S1 is net getting transferred.
Regards
Deepak Joshi

How have you tried to plan for S1 in APO? Moreover standard APO design says F to be planned in APO. If F is planned in APO then S1 / S2 and R are NOT to be planned in APO as you plan for Header product (and the important components) in APO not the other way round.
Having said that you can get demand of S1 from the external system (not ECC) to APO BW and load that data in Demand keyfigure. If you are using Planning with BOM (DP-BOM functionality) then assig this keyfigure suitably to the dependent demand keyfigure.
Otherwise this demand of S1 when released to SNP/PPDS should explode to S2 dependent requirements based on the SNP or PPDS PDS.
Hope this helps,
somnath

Similar Messages

  • Planning Dependent Demand with Phantom Strategy (59)

    Hi
    We would like to maintain forecasts at a Phantom material level and consume this forecast based on dependent demand (Planning Strategy 59 in ECC and an equivalent custom strategy in APO). This works in ECC MRP, but does not appear to work in APO CTM.
    For example - Phantom Material P1 has a forecast. MRP and CTM behave the same, exploding this demand and planning for components. Now, a Sales Order comes in for A1 which is a parent of P1. MRP creates planned order for A1 and dependent demand for P1 which is set to consume forecast (based on the planning strategy 59). CTM also creates a planned order for A1and directly creates dependent demand for components of P1 but does not create dependent demand for P1 itself. Due to this, there is no forecast consumption of P1 leading to doubling of demand.
    Any suggestions how to get Dependent Demand to be created for Phantom materials (so that CTM behaves similar to strategy 59 in ECC MRP) ?
    Thanks
    Rishi Menon

    Hello Rishi,
    Hope you are doing well.
    Have you check the atp check mode. What value are you maintaining on check mode? What requirement type and requirement class are configured in ECC? There should be a class in ECC for Phentom Assembly and see if that is configured.
    Hope this helps.
    regards,
    Najam

  • What are the disadvantages of implementing APO- Demand Planning without improvements or cleaning up the MRP. in other words is DP implementation dependant on MRP process. Gurus please advise

    HI All. What are the disadvantages of implementing APO- Demand Planning without improvements or cleaning up the MRP. in other words is DP implementation dependant on MRP process. Gurus please advise

    Hi Amol,
    DP is the demand planning machine, here you estimate your forecast (future sales).
    The MRP is a supply planning machine, here you use estimate the replenishment.
    Both machines in a technical perspective are independent one each other. Now in a business perspective they are not: The problem that you will have if you don´t clean your MRP elements is not a problem in DP itself. I mean, you can have a very success implementation in DP, your forecast accuracy will be very good.. and you will get a very good forecast, but when the MRP run and estimate the replenishment, the effort that you made in DP will not be translated in good results and your planning situation will be still not good.
    Kind Regards,
    Mariano

  • DP BOM- How to Plan Dependent Demand with characteristic?

    Hi
    I am using DP BOM functionality.
    I have a following issue:
    Part A- 1 Lit  requires            -
    Demand Date:2014
    Part B -0.4 Lit    --- Age 4 years -
    Reqmt should be:2010
    Part C -0.6 Lit u2013 Age 3 years  -
    Reqmt should be :2011
    Can any one suggest me as to how will I get Dependent Demand with correct qty & correct month/year as per above example?
    Regards
    AR
    Edited by: Ashokan R on Jul 1, 2009 11:42 AM

    Hi,
    I think you can maintain planned delivery time (2 years) for your dependent demand in production location master data.
    -sapcrs

  • Background job not automatically poopulating Dependant Demand

    Hi Users,
    We've recently set up a POS & PA using the DP-BOM selection and characteristics, manually created PPM's and generated CVC's using the BOMS. All of this is set up fine in our SCM 7.0.
    The background job has created the forecasts for the ouptput products but NOT the input product.
    Now if I call up the parent material, and then choose to show the input products the dependant demand is generated. If I now return to the material with the dependant demand, it now shows the demand from the parent.
    Or, if the forecast is genereated interactively, then the dependant demand is poopulated.
    Is there an automated method to populate the dependant demand when using background jobs? I would like to think that we don't have to query every sales BOM parent in DP and drill into the input products to load the dependant demand?
    Please let me know if there is an easier way to do this as part of the background processing.
    Thanks
    Edited by: Paul_111 on Mar 31, 2011 4:20 PM

    Hi Andand,
    Thanks for your reply and sorry if my post is confusing.
    As far as the PPM with imputs A & B, output C - I have this relationship working and calcuclating demand in DP no problems.
    If I now add a new PPM combination inpput X, Y and output Z. Create the BOM CVC and TSO so its all set to go. Add to selection profiles and background jobs.
    Now, if I run the background job to create the forecast and this runs successfully. Now I check my products.
    Z has the forecast generated, X & Z have no dependant demand showing.
    The only way I've found that pushes the demand to X & Z is:
    - open product Z in demand planning and then choose the option to show input products from the header
    OR - from demand planning, select the univariate forecast to run interactively.
    My issue:
    The background job (if run alone) does not push the forecast on Z to X & Y.
    And if I show the input products or create forecast (as bove) the dependat demand is shown on X & Y.
    This is going to be a slow process if we have to do this everytime we run the backgound job.
    What am I missing when running the background job?

  • How to configure for the give senario where we from APO demand planning, we provide baseline forecast into TPM

    Hello Guru's,
    Request for information on smart documentation on the integration between Trade Promotion Management and SCM-Demand Planning from an architecture perspective how to configure for the give senario where we from APO demand planning, we provide baseline forecast into TPM and from TPM promotions values can be considered in to APO demand planning: can anybody give me some insight on it.
    Thanks in advance.
    Kumar

    Hi Praveen
    There are several ways you can connect a DP system to a TPM. How are your interfaces and systems setup?
    Option1:
    Extract the baseline from APO to a BW cube, extract the data out of BW, may be using infospokes/open hub and pass it on to TPM.
    2. Have a custom program written in APO-DP to extract the selected keyfigure data at the aggregation level into an interface or a .txt file into APO directory and use some data transfer service such as EDI to take this data and send to TPM.
    In my experience it is simple to define an integration process. The much larger and complicated aspects are the date adjustments and the aggregation levels.
    Date adjustments:
    Understand the basis of the data in APO and TPM. APO is usually at the requested delivery date or material availability date ( when the customer like a store wants the product). However TPMs are usually at the consumption date ( when an end customer like you and me but from store shelf). Depending on the product and business style this can mean several days difference. Let's say it is 25 days on average, you need to add 25 days to APO base line date to get the TPM consumption date.
    Aggregation level:
    This can be product or customer. If the planning in DP is at product sku level and the TPM is at packs or brand level, you need to aggregate the data up before loading to TPM. The same with customer.
    To me the most complex part of the integration is to understand and transform the data in a meaningful way and a strategy to sustain this integration by keeping both DP and TPM in sync in terms of master data. Also important to have a process for identifying exceptions and failures. you send baseline from DP to TPM and if it fails, how do you know? how do you trouble shoot?
    Hope these help.

  • How to generate Dependent Demand for aggregates in DP

    Dear All,
    I am in the midst of DP implementation at one of our client.
    Business Scenario: Plant A- Car and Plan B - Engine
    I would like to know :
    1) How do I generate Engine Demand Plan wrto Car Demand using DP only?
    2) Do I need to know 2 diffrent planning areas?
    Request you to suggest on ABAP deveopment reqd or DP BOM and its functionality or If I maintain Parent Child relationship in CVCs , then is it possible to use any macro functions which will copy the Final demand of Car in Engine Planning Book against 'ENGINE' as characteristic.
    Or else request you to suggest a new approach to this solution.
    Points will be rewarded.
    Thanks & Regards,
    Ashok

    Dear Ashok
    Your requirement can be met using DP BOM. I am not sure about parent child CVC's , but DP - BOM should work.
    You need to first create and activate PPM/ PDS for DP with usage D (BOM Demand Planning).
    Assign it to model and create a  planning object structure with DP BOM relevant.
    Create the master and CVC based on MPOS
    Create a PA with 2 different KF( one for finished product, another for dependent BOM). Initilize the PA and version.
    Config the forecast settings for PA.
    Pl see through the below link
    [http://help.sap.com/saphelp_scm50/helpdata/en/e8/d47139f5a04c61e10000000a114084/frameset.htm]
    Rewards points if it helps
    Regards
    Nav

  • BAPI_MOSRVAPS_SAVEMULTI3 creating unwanted Dependent Demand

    We are using the BAPI function BAPI_MOSRVAPS_SAVEMULTI3
    to create Production Orders to integrate WIP from a
    legacy system. The presence of PDS for the product on which the production order is created, makes the PDS assignment to the production order. But, it is also creating a depenedent demand for the component in PDS, which inturn pegs to the supply on the component. We dont want the dependent demand to be created and peg to the supply, as the supply is already reduced in the external system.
    We tried using PLANNING_MODE_USAGE parameter, but was not able to stop the creation of dependent demand.
    Any way around this?

    Hi,
    Do you need the PDS in the planning system (APO) at all in case you don't want to see the dependant demand. The BAPI
    BAPI_MOSRVAPS_SAVEMULTI3 documentation says:
    For you to be able to create an order, a valid source of supply must exist for in-house production. This can be a production process model (PPM) of the type PP/DS or a production data structure (PDS). The source of supply is then used to generate the order. The order structure (components, operations, durations, capacity requirements, and so on) is determined based on the explosion. If a valid source of supply does not exist, a 'dummy' activity is generated and the order is created without structure and with only a main component.
    We create production orders with dummy activities and only the output component using the BAPI without having the PPMs at the supply plant.
    Regards
    Vinod
    NB: Also try 'Deactivate Dynamic Pegging' option in the product-supply location master data in  the 'Demands' tab to ensure  the dependant demand does not peg to available supplies of the component.

  • CTM and Dependent Demand purchase Requisitions

    Hello Gurus,
    We have a business situation where there are 2 plants which can produce a finished product from a single input product.  It is much less expensive for us to transport the finished product than the input product.  We want CTM to force the plant with the supply of input product to produce the product and send it if that plant has capacity - only transporting the input product to the demand plant if there is no capacity at the supply plant.
    Plant A   Demand 100 units of Product X
    Plant B  Supply of 100 units of Product Y which can be used to create Product O
    PPMs for creation of Product at both plants.
    Desired outcome:
    If Plant B has open capacity to create Product X prior to due date, Plant B creates Supply of Product X from Product Y and transports Product X.
    If Plant B does not have open capacity to create Product X prior to due date, Plant B sends Product Y to Plant A which creates Product X.
    The supply may be at Plant A or Plant B so the scenario must be able to work in either direction.
    Currently, when CTM runs, it see the demand at Plant B and creates a planned order there, creating a purchase Requisition for the dependent demand.
    Is there a solution for this?
    Many thanks in advance,
    Sarah

    I have done some further testing of the system and have found that I can further clarify my question.
    consider 3 production plants situated roughly in a line with PLANTA located 1000 KM east of PLANTB and PLANTB located 500 KM east of PLANTC.  Because PLANTC is nearer to PLANTB, the transportation lane procurement priority for PLANTC to PLANTB is lower than PLANTA to PLANTB (making PLANTC the first to be considered at a procurement source for PLANTB)
    We have demand for a finished product at PLANTB.  We can create the finished material at PLANTA or PLANTC.  PLANTA has the input material in stock for creating the finished material.
    When CTM makes its planning run, it looks at the PLANTB demand and determines that PLANTC is the correct procurement source for the finished material.  It looks for the finished material at PLANTC and can't find it, so it creates a Planned Order to create the finished material.  In order to do that, it pulls dependent demand from PLANTA. 
    The result is that we are moving input material west 1500 KM to PLANTC and then moving the finished material east 500 KM to PLANTB.
    We have set our priority for moving input material very high, so it should be the last resort to move.
    It appears that CTM is looking at the priority of the finished material only when determining procurement source.  Is there any setting I can make to the system so that it will look at both the dependent demand priority and the finished material priority when determining procurement source?
    Alternately, is there a way to mark the ATP group EB as not being available during a specific CTM run (without removing the dependent material from the TLANE)?
    Ideallly, we'd like to be able to move the dependent material to another plant if the capacity at the plant it is currently in is too full.
    thanks in advance for any advice,
    Sarah

  • Handling Planned order created from Demand planning and Sales order in MTO

    Hi all
    In MTO\ Repetitive we genrate Dependent requirement from demand planning (PIR) after running MRP which finally planned order created but on the other hand in short term we have Sales order which generate planned order after running MRP(In MTO), How we should handle planned order generated from Demand planning and the ones generated from sales order.(both after MRP Running).
    Regards
    Babak Bolourchi

    Dear,
    You can combine the planning strategy also main as 56 and second as 65 and in demand managment MD61 you have the option select requirement type.
    Then while creating sales order use MTO strategy and take MRP run through MD50 and then MD02.
    and if you want to assign the stock to sales order then you and do it through MB1b with 412 E movement type.
    As per my knowledge, generally 56 strategy only takes Sales Order Stock into consideration.
    Consider setting the Individual/Collective indicator to 2.
    Mark those characteristics that should have a usage probability in demand management as Relevant for planning.
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Where and How Forcast data is stored in Demand planning keyfigures

    Hi ALL,
    We are using SCM 4.0 for configuring DP module.
    Our requirement is like this...
    1.we have majorly six users (Managers) who should have an access for relevant planning books.
    2. our client have 'kits' which contains sub components
       in it.(all are materials).
    3.They sell materilas individually and through 'Kits'as
      sub components. (One kit contains sevaral materials
      as sub components with defferent quantities).
    4.Forecast is needed on materials individually and also on kit level.
    5. Dependent demand (sub components) should be added to
    individual material forecast to get final forecast.
    Can any body explain the best way to model this situation?.
    assumptions
    1. Can one planning area is sufficient to deal this situation. (I want to use DP BOM also to capture dependent demand).
    2. how many forecast key figures are required.(for six plannimng books)
    Any one come up with solution is highly appreciated.
    Thanks in advance
    Ramakrishna

    Hi,
    Here are my thoughts:
    As per your description below (and only 2 seconds of design thoughts for me), I believe you need at least 3 Key figures (Stat forecast, dependent demand, Total Demand). Total Demand = Stat Forecast + dependent Demand (to be updated by planning book macro).
    I think you need at least the 2 Characteristics: Kit (kit # whatever), Material (9AMATNR). You may also want to add Country, or whatever location characteristic if you need it.
    In your planning books, you can add the characteristic for Kit and Material. In the shuffler, users may select the kit (w/c effectively selects the materials under it) to forecast on "Kit level". Forecast on material level will then depend on the disaggregation rules that you configure. If you need to forecast on material level, then users will select materials on the shuffler. "Kit level" forecast will then be changed based on aggregation rules.
    Hope this helps.

  • We need to change of dependent demand requirement in IDP

    Hi gurus,
    when i click selection profile, we need to change of dependent demand requirement in Interactive Demand Planning screen, what is the procedure. System showing display model.how to change dependent demand requirement.
    REGARDS,BABU

    share the solution with us. please

  • Dependent demand in CTM

    Hi :
    I have a problem when i am creating a demand for FG , dependent demand for component is not getting generated .
    I checked following :
    PPM exist
    Master data selection is right
    Please suggest what else can be the reason .
    Dependent demand is being generated for one other product using same profile

    Hi,
    Assuming that planned order for finished good is getting created , would liekt o suggest ...
    1) Check with heuristic and also with infinite CTM if dependent demand is getting generated.If yes then no major problem with master data set up.
    2) Also go for  "Check CTM Master  Data" in CTM  profile. You may get some clue there. Its  available in Edit option in CTM profile.
    rgds
    nil

  • CTM - Forecast Consumption for Dependent Demand

    Hi
    We have a scenario where the Planning Strategy for a assembly part (say X) is set to a custom copy of 70 so that forecast is consumed by dependent demand. Forecasts are released from DP for such assemblies.
    The Parent of this assembly (say A) is defined when sales order is taken (Engineer-To-Order scenario) and BOM defined with X under it. The Finished Good 'A' itself may have any other planning strategy (say Make-To-Stock or Make-To-Order).
    The problem we are seeing is that when system plans for X during a CTM run, the system adds the the dependent demand of the parent to the forecast of X itself. There is no forecast consumption, so this leads to doubling up of demand.
    I understand that forecast consumption occurs in Livecache and CTM does not store the intermediate results of planning in Livecache as orders, so there is no forecast consumption.
    Any suggestions on how forecast consumption of dependent demand can be achieved during the CTM run ?
    Thanks
    Rishi Menon

    Hi,
    Request you to go thru the CTM help library under topic sub assembly planning to resolve your issue..
    It says you need to carryout two CTM runs.
    In the first CTM planning run, you plan the sales orders, and in the second CTM planning run that you then execute immediately afterwards, you plan the planned independent demands of the assembly.
    http://help.sap.com/saphelp_scm70/helpdata/en/be/503ee3e9ec4531a0179f56e90030a3/frameset.htm
    Thanks,
    nandha

  • Dependent demand flow from SCM to ECC

    Hi ,
    Can any one explain, how the scm dependent demand can flow form scm to ECC.
    scenerio-
    I have 5 level of BOM , i need to plan up to 3 level in SCM and other needs to plan MRP in ECC.
    Is it possible to transfer the dependent demand of 4rth level in ECC form SCM and run the MRP?
    BOM are PDS explosion not RPM matrix.
    Regards
    Lav Mishra

    Yes it is very much possible. MRP type should be X0 for material planned in APO and PD for not planned in APO.
    X0- Means without MRP with BOM explosion so if you are transfering publishing planning results of APO planned material in ECC it will explode bom to plan ECC planned product in MRP.
    Regards,
    Santosh

Maybe you are looking for

  • BI-Beans functionality

    Great Tech-Preview but any information on how and when bi-beans functionality will be available?

  • JSF DB Connection Best Practices

    During the life of a JavaServer Faces request, what are some best practices for storing a db connection? For the duration of the transaction, a single connection should be created before db updates, made available to (possibly) multiple model objects

  • Wifi disconnects after connecting for a few seconds [SOLVED]

    I have an interesting situation and perhaps you guys can give me a hand. I'm installing Arch on a system that only has a WiFi; no big deal. So, I get the live CD and 1. Start it and choose the network install (that's the only choice for this CD) 2. G

  • PDF printable but not save-able?

    Couple questions: With a standard PDF form created in Acrobat Pro, can user "save" completed PDF, or just the "template" (without filled-in fields)? On a regular PDF (non-form), is it possible to make it only "printable" and not "savable?" Thanks...

  • Device time is out if bounds!?!?

    On twitter on my BlackBerry z10, I keep getting a message " device time us out if bounds.please correct"........how do I fix this problem?? It also messed up my clock on my home screen! Can someone help?