Dependent requirement v/s order reservations

Dear Guru's,
Could you please explain me the difference between dependent rquirement & order reservations? As we check MD04 for any material we could see both for same material & both requirements are coming from upper or header material.
Reservations are done against production order & dependent requirement is generated due to the requirement at header material. Please explain in detail.
Regards,
SAP CONS

Hi,
Dependent req. are generated by o planned order (for its components), whereas order reservation are ceated by production orders (for its components).
One sets the other off, as planned orders are converted into production orders.
You see both in MD04, since you may have both planned and production order for the upper level material at the same time.
Regards,
Mario

Similar Messages

  • List of dependent requirements of planned order for a component

    Dear guru ,
    I search a list of dependent requirements of planned order for a component
    What do you suggest ?
    Thanks.

    Hi Cristano,
    Go to MD04 transaction, enter comopenet and plant. Then from the list select the Planned order and click on the Order Report from the bottom tool bar available below the list.
    You can see the componets details for that planned order.
    Thanks and regards
    Murugesan

  • Dependant Requirements and Planned Orders

    Hi,
    For dependant requirement, question is whether once the planned orders (of independent requirements) are converted to production orders, then only will the dependant requirements be converted to planned orders…or it is converted once independent requirements are converted to planned orders? I.e. independent requirements are blown down all the way in MRP.
    Thanks.
    Rgds,
    Sue

    Hi,
    Let us take some example so that it is easier to explain.
    Material A - Finished Good
    Material B - Raw material
    PIR generated for A - 100 Nos , MRP is run and Planned order created for A - 100 Nos. Now
    For Mtl B Dep reqt is generated for 100 Nos.
    If No stock is available then a planned order for 100 nos generated.
    IF Stock is availabel then no planned order is generated.
    When production order is created for Mtl A then the "dep reqt" status of Mtl B changes to
    "ordres"(order reservation)status.U can check this MD04.
    Thanks and regards,
    Rajesh

  • Dependent Requirements vs Planned Orders: how to retrieve?

    Hello SAP Gurus,
    I have noticed that in table PLAF, we can see which (simulative) requirement has been generated by MRP for a given planned order.
    Also, in table MDSM, we can see what was the originating planned order for a given requirement.
    My question is: is there a way to know what is the originating requirement for a given planned order? (most probably, in another table than MDSM and PLAF).
    Thanks in advance for your light...
    Regards,
    Rudy

    Hi,
    You can see the ordinal planned orders in MD05 and MD06 t-codes.
    for tables search in SE93 by key in MD05 and MD06 where you can get all programs, Tables related to that T-codes.
    revert me if any issue..
    Regards,
    Ravi

  • Function module to find out dependent requirements

    Hello Experts,
    Any function module to determine the dependent requirements for process order...
    Pls let me know.
    Regards.

    use the following FM
    MD_STOCK_REQUIREMENTS_LIST_API
    give material no and  plant and following\
    DISPLAY_LIST_MDPSX = X
    DISPLAY_LIST_MDEZX =  X
    DISPLAY_LIST_MDSUX =  x
    o/p
    MDPSX filter for the values of here DELKZ(MRP element indicator) = AR
    you will get all depnedent reservation from process order.

  • Strategy 50- Assembly's Dependent Requirement Grouping

    hi Gurus,
    MRP settings of materials I am using is as under
    1.FG-- Strategy-50-----Availability check: CH -
    Indiv Collec ind : 2 ---Consumpt mode : forward/ backward with 30 days each
    2.--Level-1 SFG--
    Strategy-50 -
    Availability check: CH -
    Indiv Collec ind : 2 ---Consumpt mode : forward/ backward with 30 days each
    3.--Level-2 SFGNo StrategyAvailability check 02---Indiv Collec ind : 2 ---Consumpt
    My requirement is to maintain PIR for level-1 SFG...after providing PIR of SFG level-1 and performing MRP run. Planned orders are created agains the dependant requirement of Level-2 SFG which are drawn from PIR of SFG level-1. Using strategy50 i m not able to convert planned orders of SFG-Level 1 into process order on the other hand Planned orders of SFG level-2 are convertible into process order, which is the desired functionality.
    Now if i create a sales order of the FG following results appear.
    at SFG level-1
    - Unconvertible Planned Orders created remain unchanged.
    - PIR is not effected
    - Depandant requirement is created for the quantity exploded from FG sales order and corresponding planned order is also created which is convertible.
    "Desired result is: PIR of SFG level-1 should be consumed "
    at SFG level-2
    two seprate planned orders are created, one against the PIR of SFG level-1 and second agains the dependant requirement of the sales order created for FG ( i.e. FG--> SFG level -1 > SFG level>2)
    Desired Result is
    one netted off planned order to be created at this level..i.e. the planned order quantity should be increased only if the dependant requirement of sales order exceeds the dependant requirement coming from PIR of SFG level-1.

    hi,
    use the strategy 50 only for FG,
    For sfg and raw materials leave the strategy as blank.
    if you use strategy 50 for sfg,the planned orders created would be unconvertible,order type VP.so only use strategy 50 for fg.
    this will solve your issue.
    regards,
    sikkandar basha

  • MRP Planned order generation for Order reservation excluding Dependent Requirements

    In our Project we have a requirement like for FG stage & SFG1 stage are M.T.O So after sales order are punched through  MD50 we have created Planned orders against sales orders,But dependent stages like SFG2 & SFG3 which are pure M.T.S so only Dependent requirements will get generated.Suppose for SFG1 i have partially converted planned order to Production order then for component SFG2 we get Partial Quantity as order reservation.Now requirement is if i run MRP for SFG2 system need to generate demand only for order reservation excluding Dependent requirements.Is there any possibility where we can generate demand only for order reservation.As system will create Planned order for SFG2=Dependent requirement + Order reservation

    Hi Uli,
    Suppose i have Sales order--100 kgs for FG
    B.O.M levels
    1.FG-----M.T.O
    2.SFG1---M.T.O
    3.SFG2---M.T.S
    4.SFG3---M.T.S
    5.ROH
    So if i run MRP via MD50 system would generate planned orders for FG & SFG1 level as they are M.T.O specific
    Now my requirement list would be
    FG-100kg planned order
    SFG1-100kg planned order
    SFG2-100kg dependent requirement.
    Now suppose i have partially converted SFG1 planned order to production order
    SFG1--100kg planned order to 30 kg production order
    Now my requirement list would be
    FG-100kg planned order
    SFG1-70kg planned order & 30 kg production order
    SFG2-70kg dependent requirement & 30kg order reservation.
    Here my requirement is if i run MRP for SFG2 in MD02 as these stage is M.T.S system should provide 30 kg planned order & if we see down the line it would be like
    Now my requirement list would be
    FG-100kg planned order
    SFG1-70kg planned order & 30 kg production order
    SFG2-30kg planned order & 70kg dependent requirement.
    SFG3-30kg planned order
    ROH-30kg Purchase req
    Client requirement is like these..

  • Planning of Dependent Requirements for BOM Components in Make to Order scen

    Hi Friends - I want to execute a full cycle Make to Stock Scenario with Materials planning using MRP.
    The scenario will include BOM Components with Routing.
    The process flow I want to execute -
    1. Create a Sales Order for a Finished Product (Product should have a BOM for Production)
    2. Do the product Materials Planning for the Sales Order through MD50
    3. Get all the dependent material requirements (both for products as Planned Order and also for BOM Components - all the BOM components should also be planned)
    4. Convert Planned Order for Product to Production Order
    5. Convert Planned Orders for BOM components to Purchase Requisition
    6. Confirm Production Order
    To execute this I have done the following
    1. I have created a Material Master data for Finished Product (FERT).
    2. I have assigned Item Category Group - NORM, and General Item Category group as NORM
    3. I have assigned MRP Type PD in MRP 1 View and Strategy Group 20 (Make to Order Production) in MRP 3 View.
    4. Now created a Universal (Type 3) BOM for the product with one material component.
    5. Now also created a Routing for the Material with two operations having PP01 a control key.
    6. Now created a standard sales order for the product.
    7. Executed the MD50 for the Sales Order Item.
    Now where do I find the BOM components for this material in the Sales Order?
    After executing the planning Run MD50 I am only getting the requirements for Product only. I can't see any dependent requirements for the BOM components.
    How do I make sure that the BOM components are also planned while the product is planned?
    I have checked the component Stock Requirement List - there are no requirements generated from the Sales Order Product BOM.
    Pls help me on this. How to do this so that the raw material components are also planned?
    Thanks
    Purnendu

    Hi Dhaval, Sandeep, Ashok - Thanks a lot for your replies.
    I have checked the Planned Order Created through Planning Run.
    If I click on the Components Tab I am getting following message
    No material components were determined
    Message no. 61027
    Diagnosis
    Until now, no BOM explosion has been carried out or no BOM has been created for this material yet.
    Procedure
    Either explode the bill of material for this material, or
    create the components manually by processing the planned order in change mode.
    If I try to explode the BOM through Header Menu - Edit> Explode BOM
    I am getting the same message.
    If I click on the Bill of Material Tab - I am getting the same above messge.
    Ashok - I have tried both the Selection Method -
    Nil - Selection by Order Quant.
    1 - Selection by Explosion Date
    But with no effect.
    Waiting for your advice.
    Thanks and warm regards
    Purnendu

  • MRP: how to segregate the planned orders by dependent requirements

    Hello SAP Guru's,
    I would like to know if this is possible to make the MRP work is this way:
    - generate global planned orders (by date) for several dependent requirements, for inhouse production;
    - AND generate individual planned orders for each dependent requirement, for external procurement;
    For the moment, it is grouping the quantities of all the dependent requirements to generate a unique planned order by date.
    But we would like to get separate planned orders for each dependent requirements that are externally procured.
    Do you think it is possible to do so? and if yes, how?
    Thanks in advance for your help on this subject.
    Regards,
    Rudy

    In MD04 the demand n supply that is seen is considered as plant segment. In some cases when you plan demand n supply for a given storage location separately it is called as SLoc segment, also if you're working with MRP areas then its called mrp area segment, likewise for project & sales order.
    In short it is just a way MRP would do its planning. In normal cases, the demand n supply is in plant segment, so in this segment the least resolution that you can work with is a day, so all demand on a given day is clubbed together and a supply proposal is made (depending on the lot size).
    If you want further split on a given day, then MRP needs some way to identify the difference & this is provided by the special stock segment such as project segment. To see how it works, if you're working with PS module, ask your PS colleague to create a demand for the material from different projects for a given day. Then in MD04 you will see each project demand show up in different segment & when you run MRP, you will see the results.
    I guess more than me writing quite a lot out here, a simple test at your end should help clarify... good luck

  • Technical data for planned order dependent requirements .

    Dear All,
                  I have to call the dependent requirements created by MRP run in my report. Can anyone please tell me that where these dependent requirements are stored in the database or is there any function module to get these values?
    Thanks.

    Dear,
    RESB Reservation/Dependent Requirements Link with PBED for FG and SFG releation. Function module MD_STOCK_REQUIREMENTS_LIST_API
    Also refer this link,
    Dependent Requirements report required
    Regards,
    R.Brahmankar

  • Conversion of Planned order to PR and Dependent Requirements

    Hello Everyone,
    I had two issues to be dealt with..
    1. When i run my MRP run for a specific plant i do not want the system to automatically convert planned orders to Purchase requisitions for specific material in specific plant. How do i Configure the same?
    2. I use planning strategy 40 for the header material. During MRP run dependent requirements are automatically  raised for lower level components. But how does the user know which planned order is generated for which higher level order?
    Moreover, since the same raw material is used in multiple  finished  materials, a single planned order is raised for the same raw material. This makes it all the more complex.
    I think Individual/ Collective requirement does not help in this case because i am using stategy group 40 which is a MTS strategy.
    Any help in both these cases would be greatly appreciated..
    Sincerely,
    Aji
    Edited by: Aji Kurian Mani on Nov 28, 2009 2:51 PM
    Edited by: Aji Kurian Mani on Nov 28, 2009 2:51 PM

    1) Select the indicator "3"- Planned Orders in the MRP Screen or in a Variant you use to schedule the MRP
    2) Under a make to stock scenario, requirements are summarized in a planned order (or many, according to the lot size key). But in general as the stock is generic and not customer-specific, there is no assignment of planned order to a given customer.
    Regards

  • RESB - Reservation/dependent requirements

    Hello
    I am SAP BI consultant who needs to build an delta enable extractor out of table RESB - Reservation/dependent requirements
    This table doesnt containt any doc creation or change date.
    Where can I find material reservation creation or change dates? Any log for material resevation?
    Thanks

    Hi,
    look in the logical database MMIMRKPFRESB.
    The relevant tables are RKPF (Header), RESB (Position) and the regarding movement type (RKPF-BWART).
    Does it help if you use the requirement date RESB-BDTER, or what additional information do you need?
    Regards
    Carola

  • Order reservation should not get planned in mrp run

    Hello friends,
    Actually for a finished material i have created one production order by CO01.Because of it for semi finished material system created order reservation.I dont have any stock of semi finished material.Now i want while running the mrp run system should not planned this Order reservation of semifinished material.For these in configuration of availability check (Scope of check T.C  OPJJ), I  made the settings that system should not consider reservation (i deactivated the tick for include reservation) and for include depend reservation , i selected Donot check.And all these settings i made in checking group 02 and checking rule PP.After doing all these settings than also system is considering the order reservation for semifinished material and generating the planned order for it.
    Do i need to do any other configurations?
    Thanking you guys in advance.

    Hi Jitendra,
    Checking Control (OPJJ) has no relation with MRP.It is useful in the case of Plan and Production / Process Order only to find out Missing part.
    Now come to MRP again.
    You have a choice of only 3 type of stocks to include or exclude them during MRP run while rest of the things like (PO,PR,Reservation etc are consider by default)
    Go to OPPQ and after selecting Plant go to Available Stock.You will find that options,
    - Stock in Transfer
    - Block Stock
    - Restricted Stock.
    And one more thing Reservation is not a available stock but its one kind requirement and if there is no stock then system will activate the Planning file entry and during next MRP run it will generate Planning proposal also.
    Regards,
    Dhaval

  • Dependent requirements

    Dear friends,
    For example I am having a Sales order for 20 items. Due to some constrains, at a time I can not produce more than 1 item. So I am creating a production order for 1 item with reference to a sales order (using CO08).
    My problem is while running MRP, system is creating the dependent requirements for all the 20items. So I want to run MRP for the production order (like MD50 for sales order). Otherwise my MRP run should not consider the Sales orders for the dependent requirements calculation.
    Dependent requirements for all the 20 items is creating a big confusion. My scenario is pure MTO. Down the line all the production is for the respective sales order only.
    Please suggest me...
    Regards.

    Hi Kodand Nag,
    Please explain your scenario once again, I get confused little bit, 
    What I understood from your last reply, u have created sale order  with order qty is 20 nos for one material. (I assume).
    Then u have created prod order for one Nos (Partially – since is capacity constraint) with reference to sale order.(CO08).
    In MTO, system consider the sale order to create dependent requirements for dependent  material.
      Here u want system to consider production order not sale order requirements  – This is not possible.
    My solution is since u have converted partially qty as Production order, order reservations should have created for dependent material, if u run the MRP for dependent material (Next one below the header material) , sale order requirements is not taken into the account only production order req. I hope i am not mistaken, else please comeback.
    Regards
    Pradeep

  • Dependant requirements are to be considered in reorder point planning

    Hi,
    We are currently using safety stock planning with PD.but the problem is that MRP triggers a procuement proposal when ever the availabile quantity(not the stock) falls below safety stock(as it considers MRP elements like DEP REQ etc in the net requirements calculation).
    Now if i propose VB,it does not consider the dependent requirements at all(they are not even displayed)
    Requierment is that the procurement proposals should only be triggered when the safety stock falls below the physical stock and DEPREQ's and all other requirements should still be displayed.
    I appreciate your help in getting me through with this.Thanks.
    Ram

    Dear Ram,
    go to the customizing of MRP type ,
    ther you will find the field 'Reorder point planning with external requirements'
    Indicates whether an external requirement (sales order or manual reservation) is included in the net requirements calculation for reorder point planning.
    If yes, you can decide whether it is to be included:
    -in the complete planning horizon, or
    -only within the replenishment lead time
    I hope the above information will be useful,
    best regards

Maybe you are looking for