Deployment Horizon in Service parts planning (SPP)

Hi,
I want to trigger deployment in SPP module..I have maintained lead time of 2 days in transportation lane..I want system should take 6 days demand and deploy all the 6 days quantity today..
For this what setting i need to do..i have maintained maximum planning horizon in the deployment service profile as 6 dyas..but system is taking only 2 days demand into consideration..
kindly do the needful
regards
Pradeepta

Hi
My question was answered.
Regards
pradeepta

Similar Messages

  • Simulation in Service Parts Planning (SPP)

    Hello to all!
    I have few questions about simulation in SPP:
    1. Please explain me the differencies between Snapshot Version and Simple Copy of Active Version.
    2. Is it possible to join simulation version and active version or to substitute cuurent active version with simulation version so simulation version will become active version? I need this functionality for preventing 2 runs of planning services instead of this i want to use simulation for planning and if the results of simulation are acceptable so the will become "active" without repeating this operations for active version.
    Thanks in advance!

    Hi
    My question was answered.
    Regards
    pradeepta

  • Service Parts Planning: Config guides

    Hello Everybody:
    Wondering if there are any Configuration guides available online for Service Parts Planning (SPP) irrespective of any particular scenario, if yes please let me know the URL .
    Thanks in advance.
    Sadat

    Dear Sadat,
    please read through following link about SPP:
    http://help.sap.com/saphelp_scm50/helpdata/en/a3/7ed240caeb752ae10000000a155106/frameset.htm
    Here you will find the necessary master datas, the general functionalities etc.
    Regards,
    Tibor

  • SPP for machinery service parts planning within single location ?

    Hello,
    I'm seeking for general directional advices from anyone having gone thru an SPP implementation. We are currently investigating how to handle machinery service parts in one of our main production plants. ERP6.0 does have anything specific in terms of planning/forecasting etc. since such service parts are typically sporadic use and the requirement is to plan for a service level on such. We have roughly 20.000 service parts in the plant  where roughly 3.000 are used within a month (can be once a month or more).
    So far we have checked the SAP ERP "add*ONE INFORM" solution and it looks promising and like a all-in-one for this purpose. Now the question came whether we can use SCM-SPP for this since we do use SCM7.0 DP/SNP/GATP for a couple years now and have a certain experience in DP forecasting and SNP heuristics. We are not sure if SPP in SCM is meant for such a case like we have - we do not need to distribute service parts - we don't necessarily would need BODs etc.. But the interesting part are the predefined forecasting methods and automatic model assigment in SPP etc. in there (in comparison to APO-DP where we have to chose and set the models for each part individually).
    Is there any general recommended use / non-use of SCM-SPP in a certain area or for our single plant service parts planning ?
    Thanks for any advice or hint !
    Regards
    Thomas

    Hi SRS Kannan,
    tks for your reply.
    Questions: our machinery spar parts don't have "Sales Orders" but PurchaseOrders buying such parts from vendors and a consumption history while using such parts for repairing /replacing machinery parts - will this work too assumping we can connect BW datacubes carrying such data into SPP forecasting process (or is SPP "insisting on Sales Order history) ?
    Regard
    Thomas

  • Please help to understand the Service parts planning,we r tring to do poc for project

    Hi
    Please help to understand the Service parts planning,we r tring to do poc for project
    1)How the sales history flow from cube to Interactive forecasting screen(like dp in apo there is no Planning area to store data and no load planning area from cube,so please let me know how it will load data?)
    2)How the Final demand will flow to DRP for further planning?
    3)What is the exact purpose of BOD?
    4)What is the leading indicator forecasting and the purpose?
    5)Where data will store in SPP (forecasting and other data like liveache in dp)?
    6)Product interchangeability and use?
    6)Can you please forward the process document to understand the flow as i am not able understand the help document
    Thanks for advance help
    Regards
    kkk

    Hi,
    Please check Service Part Supply Plan - Enterprise Services in SAP Advanced Planning and Optimization - SAP Library
    BR

  • Please help to understand the Service parts planning doubts/clarifications

    Please help to understand the Service parts planning,we r tring to do poc for project
    1)How the sales history flow from cube to Interactive forecasting screen(in spp,like dp in apo there is no Planning area to store data and no load planning area from cube,so please let me know how it will sales history load data?)
    2)Does Sales History of the child location will agregated to entry level ? if so like that we need to run statistical forecats at entry location?
    3)where we will create the from and To Product(eg:Maping Product A to Product B ) to do the Relignment /Phase in profile/Interchangebility
    4)What is the leading indicator forecasting and the purpose?
    5)Where data will store in SPP (forecasting and other data like liveache in dp)? Mpos and Planning area is not there in SPP?
    6)Can you please forward the process document to understand the flow as i am not able understand completely by the help document
    Thanks for advance help
    Regards
    KKK

    Hi,
    Please check Service Parts Planning - Enterprise Services in SAP Advanced Planning and Optimization - SAP Library
    BR

  • Service parts planning

    Dear all,
    Currently iam working on SAP APO(DP,SNP).
    From the next week i may have to work on SPP(service parts planning).
    Anyone having some links or docs related to SPP,please send me.
    My mail id is [email id removed].
    Thanks in advance...
    Shivaram.

    First of all please do not ask documents to be sent directly to your email id. The email ids will be removed from the post also.
    While it is known very minimal documentation exist in SPP area other than help.sap.com you may like to look into the <a href="https://wiki.sdn.sap.com/wiki/display/SCM/ServicePartsPlanning">SPP</a> page. Please bear for sometime while the <a href="https://wiki.sdn.sap.com/wiki/display/SCM/SPP+FAQ">FAQs</a> are correctly laid out.
    Thanks,
    Somnath

  • ESA Services concerning Service Parts Planning and Extended Warehouse Mngmt

    Hi there,
    Does anybody know know about state of the art, or even better, new or planned ESA Services concerning <b>Service Parts Planning</b> (SPEE) and <b>Extended Warehouse Mngmt</b> (EWM Engine). Thanks in advance...
    Daniel

    Hi Daniel,
    Check the ES workplace for future planned services by SAP.
    <a href="http://erp.esworkplace.sap.com/socoview(bD1lbiZjPTgwMCZkPW1pbg==)/enterpriseservices.asp?id=5F7358118AA6D511B1A80090270F6F87&fragid=5F7358118AA6D511B1A80090270F6F87&packageid=CBD4F2B708B8144DAEA05442D8FD491E">SCM services</a>
    Hope this helps.
    Regards,
    Gajendra.

  • Service Parts Planning with mySAP SCM

    Hello All
    can anybosy tell me where can i get this book in Mumbai/Pune
    Service Parts Planning with mySAP SCMu2122 -Processes, Structures, and Functions
    Publisher     Springer Berlin Heidelberg
    Thanks in advance.

    Hi
    If it is not available in any bookshop ... you can request the bookseller to order it... Check with Cross word

  • Service Parts Planning Substitution of Reman Products Demand in DRP Matrix

    I've got a pretty specific question about how Substitution of Remanufactured Products Demand actually gets distributed in the DRP Matrix in SPP (/n/SAPAPO/SPPDRPM).
    1.)  Two products are involved in an active 1:1 Subst. of Remanufactured Products "Replacement Type" in the Interchangeability UI (/n/INCMD/UI).  One would be the predecessor Reman product and one would be the successor Seed product.
    2.)  Let's say supplier capacity is in weekly periods in the SPRO configuration of 1 piece for each week for 52 weeks.
    3.)  When recalculating the DRP Matrix for the predecessor product, how does the substitution of remanufactured products demand get distributed among different locations within the BOD (Bill of Distribution) on the successor product if the requirements on the REMAN product were greater than the supplier capacity indicated.
    If you don't understand the concept or need more information, please let me know.
    Thanks,
    John V.

    Hi,
    Please check Service Part Supply Plan - Enterprise Services in SAP Advanced Planning and Optimization - SAP Library
    BR

  • Service Parts planning through SAP

    Hi,
    We are looking for the right Parts planning solution for a company engaged in providing after sales service for branded products to various end customers across the country. The company is currently working on SAP R/3 4.7 and is in the process of implementing CRM 5.0 Field Service.
    Following is the business requirements in brief:
    Parts get mobilised from a Central Hub to several Regional Warehouses and from where it further gets distributed to the channel Partners who are actually carrying out the Service.
    (a) The business wants to fix a "Minimum Stock Level" for each Part at the Warehouses and Channel Partners. Apart from this, it wants to fulfill daily demand arising from the field as Service Calls. Currently there is an industry logic that has to use past Service Call details from CRM and compute Min Stk Level at the Channel Partner.
    (b) When requests for Parts come from several Channel Partners to a Regional Warehouse, the WH applies certain priority rules to allocate available stock to each of the requests (for ex: - First in First Serve, Rank of the Channel Partner etc.,) Initially WH fulfills daily demand and if there is surplus then Min Stock Levels are fulfilled.
    (c) Similarly, when several Regional WH places requests to the Central Hub (based on shortfalls arising after fulfilling Channel Partner's requirements), the Central Hub applies its own priority rules to allocate available stock to the Regional WH (For ex: - Proximity, Unfulfilled Calls at the Channel Partners by age etc.,)
    There are other variants that has to be applied in the form of rules while determining optimum allocation quantity to the Channel Partners so that 100 % Service Level is achieved.
    Request experts in this field to suggest the best approach / platform to solutionize the above business requirement.
    Thanks for your time.
    Raj

    Hi GS,
    I can see requirements coming up in APO SPP and SAP SPM solution as a whole( which wiill cover ECC & SCM components) past 2 years.
    Regarding maturity of APO SPP, from experiences we have for some clients, some amount of enhancements are required , because, Service parts supply chain managment processes are done quite differently across organizations.
    Since the basic framework of SPP business processes is well set in APO SPP, it will worthwhile to spend time on this module.
    These are my opinions.
    I hope this gives answers to your query.
    Pleae check.
    Regards
    Datta

  • Using ASCP for Repair Planning and Service Parts Planning

    I have a client that is doing a large scale Oracle ERP (most modules). The customer is a large aircraft maintainer and perform most of the maintenance internal. Has anyone implemented ASCP is a complex repair environment that his heavily influenced by service parts concepts. I am a Xelus/ClickCommerce implementor and I am looking for some insight on how to implement the key service parts concepts including: fractional repair BOM's/Factors, time phased bills of materials, importing time phased re-order points, time phased carcass returns , constraint based planning on carcasses, material and resources.

    Partha ,
    The simple scenario mentioned by you where one supplier/supplier site is there for an item and supplying to two org ... the suggested due date can be different by having different purchasing lead time(pre processing + post processing + processing) set at item org level .
    But this solution will not work when you have multiple supplier/supplier site is there for an item rog combination. However here it can be tried modeling through a combination of post processing lead time at ASL Level and pre processing lead time + post processing lead time at item org level.
    Regards
    Abhishek

  • Service parts planning configuration document

    Hi All,
    I need some document related to configuraton in SPP(Spare parts planning)
    Regards
    pradeepta

    Hi
    My question was answered.
    Regards
    pradeepta

  • What is the schema name for service part planning module

    Hi Experts,
    i need the following info
    1. what is the schema name for SPP module
    say for example we call ASCP as MSC, in similar passion what is the name given to SPP.
    2. I have searched for the table details in etrm site ( in R12.1.1 ) but it is not available, can anyone help me out to get the table details in SPP ?
    Thanks for your valuable time.
    Bye
    Babu

    Thanks Bob for your clarification.
    Do you have any idea, which are all the table that got linked with SPP in the MSC schema ?
    If we have any separate link in metalink, pls share that link.
    Thanks again for your valuable time.
    Babu Ji

  • Supply Parts Planning and CRM

    Hello All ,
    I need to identify which are the standard extractors (BI content ) for pulling Supply Parts Planning (SPP) data from SAP CRM into SAP BI . Please let me know if anybody has information on the same asap.
    Thanks .

    Hi Riddhi.  Did you mean to ask what are the standard extractors, if any, for pulling Service Parts Planning data from SCM, as opposed to CRM, mentioned in your original post?

Maybe you are looking for