Determination of First Date in Sales Order

Hello SAP Friends, 
Below is the issue we realised during the testing. The issue is with First date in the Sales Order which is not updated as per Unloading Point Calendar .
As per details I received, it should refer Unloading Point Calendar for ShiptoParty and populate the next working day as First date into Sales Order.
How is First Date determined in the sales order?  Is there any config settings which is based on Route to do this? Or Is it controlled purely based on settings done in Tcode: VOV8, Leadtime days? I do not think VOV8 settings is controlling that in our APO system.
I have checked MAD, Pick/Pack, GI date all are populated correctly, But First Date did not follow the logic Unloading Point Calendar of ShiptoParty.
Please let know your inputs in this regard.
Thank you
Satish Waghmare

Satish,
I unfortunately don't have a solution for you.  However, here are a few observations, and a question.
My experience is that 'First Date' in R/3 is not determined.  In every sales order I have ever seen, First Date is proposed (matches the requested delivery date in the Sales order header) by the system, but can be overridden by any changes that the user may elect to make.
Generally, then, after First Date is entered, the R/3 system then may be configured to determine certain master data:  Shipping Point, Unloading Point, Route, Route Schedule.  From this master data, if you are performing ATP in R/3, the system will then also calculate various dates (if configured) for the confirmed schedule proposal:  Normally these calculated dates are Delivery Date, Goods Issue Date, Loading Date, Material Availability date, Transportation Planning Date.  If you have configured Route Schedules in R/3, other dates may be determined.
If you are performing ATP in APO, then any such scheduling must be performed in APO.  Relevant Master data that was determined in R/3 is carried across to APO during the ATP check and is then used to calculate appropriate durations.  This does not happen automatically, you have to configure the scheduling technique you wish to use in APO.
So, my first question:  Are you performing ATP in APO?  If not, then you should probably close this post, and re-enter in one of the SD forums, since it is an SD issue.  If you are performing ATP in APO, then what scheduling technique are you using?
Best regards,
DB49

Similar Messages

  • First date in sales orders

    Hi experts,
    Today, the system automatically proposes tomorrow in "first date" when creating orders, no matter what customers or material. Before today, it proposes current date as first date when creating orders.
    Pls help to dig out the route cause. Thx.
    More info:
    "Factory calendar" shows Jan 26 only as public holidays. Workdays just exclude public holiday. CMIR records are not maintained. "Propose del date" is activated in the sales document type. In material master, "GR Processing Time" 2 days was set in MRP 2 (scheduling) only.

    Hi Cathy,
    Any adviceuFF1F
    My sincere adivse is...when we are handling an issue which requires investigation, we have to check all the possible areas and it needs lot of patience. We cannot expect a straight answer for this kind of issues. It is only on trial and error basis we have to check the possible cause of this problem. Have you checked the calendar assigned to the sales organisation?
    Thanks,
    Ravi

  • Regarding "first date" in sales order

    Hello gurus,
    I  have a forward sales order in which all the line items have 1-1.5 month future first date but one line item have 4-5 months future first date.
    client question is on what basis this vary far date is getting calculated.
    Please help.
    Thanks

    Hi,
    This date is calculated either based on the ATP results or after carrying out delivery/transportation scheduling. Please check the stock situation of those materials. If transportation scheduling is active, check the lead time maintained in the determined route as well.
    If you press "F1" in that field you will see how the system react on that field.
    Best regards,
    Rahal.

  • How to get schedule line date copied to "First date" in sales order

    Dear forum
    I am creating a sales order as normal and put in a Requested Delivery Date (KETDAT) for the order.
    This requested delivery date is then copied to the "First date" (ETDAT).
    Now, the ATP is checked for each line item in the order and a Schedule line date / material availability date is calculated for each line item.
    My question is: Is there any way to have the "First date" field of the line item in the sales order populated by the first material availability date (calculated by ATP), instead of copying the Requested  Delivery Date? Any user exit? Any config?
    It would mean that every time I rerun ATP check in the sales order line item, the "First date" field would change if the material availability date change. If there is multiple material availability (multiple schedule lines) dates per line item, then the earliest date would be copied to the "First date" field.
    Is there such functionality? Or possibility to config/program?
    /Ola

    Kannan
    OK. Unfortunately reservations cannot be created at the serial number level. So the unsupported way of doing this is updating the mtl_serial_numbers tables. I hope you would know (by some means) which serial numbers you want to allocate to a specific sales orders. If you know, update group_mark_id column in mtl_serial_numbers table with your order_line_Id, This will avoid any one from picking the serial numbers (they will not come up in the LOV or will not be auto allocated).
    But you have to make sure to take it off when you actually want to pick this order line and allocate this serial number. So just before you pick release/ confirm this order line you need to update column back to null so that you can allocate that serial number.
    Thanks
    Nagamohan

  • First date in Sales Order

    How could we make the "First Date" field in the SO to be changeable?
    Once I enter the cust.requested delivery date under the "First Date" column in the SO, if later cust. wish to change the delivery date. That field is greyed out !
    Is't it controlled in VOV8?

    Hi,
    Check the dates for delivery in scedule line tab at item level in sales order.
    You can maintain the dates for deliveries and also delete the same. based on these dates system will create deliveries.
    Once you create delivery for total quantity, no schedule line is required so it will be grayed.
    Regards,
    Sameer
    Please reward points if it is useful.

  • First Date on sales Order Line item problem

    I am having a problem with understanding why am I getting different First Date at the line Item every time I create an order using VA01.
    Our lead time for order type OR is set to 3 days in the TVAK table and field VLAUF.
    If I go to VA01 and enter a sales order OR, the date should be today's date (04/02/2014) + 3 work days = 04/07/2014 because 04/05/2014 is a Saturday.
    Today when I calculate the order it brings in the first date as 04/05/2014 in some cases.
    But if I put in the Sales Org in the VA01 screen along with the order type OR, the first date comes in as 04/07/2014.
    Can someone please  explain it?

    """""Users may or may not enter the sales org when creating an order"""""
    You cannot create a sales order without the sales organization.....
    Even though you missed system will always redetermine after entering the Sold to party number in sales order from your master data...
    Phanikumar

  • How to syatem determine delivery date in sales order

    hi sap gurus
    how to syatem determine delivery date in sales order
    Thanks and regards
    ram

    Hi Friend,
    There are many things which determines the delivery dates.
    01. PICK TIME+ PACK TIME +LOADING TIME
    02. LEAD TIME in days (VOV8)
    03. Shipping point
    04. Scheduling line
    05. Kind of availblity check
    06. If the above things are maintained as blank then the current date will be the delivery date
    However whether it must be proposed by the system or not is determined by one check box there find in VOV8 in requesteed delivery date determination tab.

  • How system determine delivery date in sales order

    Hi, sap gurus
    I am new to sdn forum please help me regarding my question
    1) how the system will determine delivery date in sales order
    2) what are factors effects to conform sales order stock
    3) what is different between static check and damanic check in credit mgt
    Thanks and regards
    nishad

    hi,
    Reg question:1 - System determines the Requested Delivery Date based on the Scheduline assigned to the item category of the item in sales order.the schedule line in the order transfers the requirements trhu MRP (can be individual or collective) . If its ruch order , you configure the order type "Deliver Immediately".
    In Detail:
    The TOR depends on the Requirement Type (MMR), Requirement Class(MMR), Checking group(MMR) and the Sc line category (Line Item). For the TOR to happen u need Plant at line item, scheduline category markd for TOR, Requirement Class marked for TOR and Checking group in MMR (Availability check)
    What all stocks need to be checked during Availability check is controlled by using the checking rule.. for example for AV -02 Ind Requirements a checking rule will be assigned and this checking rule- and then what all stocks need to be considered to determine the delivery can be maintained here.
    Rgds
    Sai

  • Calculation of dates in Sales order in gATP

    Hi
    Can anybody please tell me how scheduling works for the following dates in sales orders for materials planned in gATP.
    1) Unloading date 2) Delivery date 3) Goods issue date 4) Loading date 5) Material availability date 6) Transportation planning
    My understanding is that gATP gives the MAD date and other remaining dates like transportation planning date, unload date etc are calculated using master data in the calling system eg ECC.
    We are facing an issue in our system where if a material is planned in ECC, it has all dates in the sales order calculated as expected based on ECC master data.
    If the same material is planned in gATP, it simply copies the MAD date to all other dates. So it is not considering the pick/pack , transportationplanning times from the ECC master data.
    Is this standard system behaviour and to avoid this  Do we need to activate Scheduling in gATP along with master data maintenence in APO ?or any user exit plus execution steps is avaialble to by pass APO master data mentaince.
    Appreciate your responses...Regards - Amit

    Amit,
    We are facing an issue in our system where if a material is planned in ECC, it has all dates in the sales order calculated as expected based on ECC master data.
    If the same material is planned in gATP, it simply copies the MAD date to all other dates.
    The system where the parts are planned is irrelevant.  The important issue is the system where the ATP is conducted.
    My understanding is that gATP gives the MAD date and other remaining dates like transportation planning date, unload date etc are calculated using master data in the calling system e.g. ECC.
    I have never seen that statement validated in any SAP documentation.
    From online help:
    SAP R/3 uses the order type to determine whether shipment scheduling or transportation scheduling should be executed.
    If scheduling is activated, SAP R/3 determines a plant for the material for each item. If it is specified in the integration model that the availability check should take place in SAP APO for a material in this plant, transportation and shipment scheduling also takes place in SAP APO.
    Standard SAP APO GATP supplies three different methods for shipment scheduling.  If you are conducting ATP in APO, and you have not configured one of the three scheduling methods, then shipment scheduling does not take place, and the system will react as you have described.  
    Read up on it here
    http://help.sap.com/saphelp_scm70/helpdata/EN/05/f8923945b12c4de10000000a114084/frameset.htm
    Best Regards,
    DB49

  • I cannot Split Deliv. Date in Sale Order

    Hi expert
    Can anyone give some suggestions.
    - Sale order is MTO and have production order that generated from sale order but production order was closed by user.
    - User create new production order by tcode CO08.
    Users want to change Deliv. Date in Sale Order by refer to new production order but cannot change.
    I cannot edit and split Deliv. date because date of old production order and ATP check not found new split item.
    regards,

    Hi, Allen Qiu2010 
    Thanks for your suggestion, after check at shipping tab than Partial delivery per item is blank.
    After change type, i can split  new delivery date but it refer to the old prod.ord, which was closed.
    Clould you tell me about new item which split delivery?
    How to refer between new Deliv.date and prod.ord. that create by CO08?
       -  first item of Deliv.date, and confirmed dty. have 40 PC (refer to old prod.ord which was closed)
         ->i checked material on MB52 don't have stock of this sale order . (sale order is make to order)
         -> prod. ord which create by CO08 unfinished process.
    Sorry, if i wrong understand.
    regrads,

  • How to get the pricing hierarchy based on the delivery date for sales order

    Hi,
    How to get the pricing hierarchy based on the delivery date for sales order other than system date.
    My requirement is to get the Pricing hierarchy based on the delivery date other than system date.
    Waiting for kind response.
    Best Regards,
    BDP

    HI Sai,
    please refer teh document already how to write FM based extration on generic extractors.
    and here  the logic to find the latest records values:-
    -> get the data in an internal table
    ->Sort the internal table data based from date descending
    -> Using READ statement , we can read the first record of the table which is nothign but your latest record.
    Regards.
    Sakthi

  • Tax date in sales orders and invoices (Billing)

    Hello Experts,
    I have an issue related to Tax date in sales orders and Billing documents.
    In our environment we calculate taxes at the time of sales order creation and billing document (invoice) creation.
    Currently we modified 'ZXFYTU03' exit to pass tax date which is system date. Our business processes are such that, there is a gap of 3-5 days between sales order creation and billing creation. So for some orders we see tax discrepancies between order and billing.
    Through forums I understand that we can use 'service rendered date' at sales order item level. Solution would be passing date in 'service rendered date', we can pass date in 'service rendered date' field in sales order.
    The problem is to copy same date in billing document 'service rendered date'
    Does anyone have any idea how we can copy the sales order service rendered date to invoice service rendered date?
    Through forum i understand that we can use copy controls, data transfer routines etc...Appreciate if someone can guide me on how i can use these...
    Thanks in advance
    Pradeep

    Tried 2 options...
    1. Modify program RV60AFZC (FORM USEREXIT_FILL_VBRK_VBRP) to pass VBRP-FBUDA = VBKD-FBUDA. But in later part of the process, in SAPLV60A-LV60AA21 (perform fakturadaten_lieferbezogen), VBRP-FBUDA is overwritten by LIKP-WADAT_IST which is goods movement date. So this is not solving my problem.
    2. Modify program ZXVVFU08, to get service rendered date from VBKD-FBUDA based on CVBRK-XBLNR (Sales order) and populate CVBRP-FBUDA. But unfortunately this user exit is being called after user exit 'ZXFYTU03' where tax related data including tax date which is being passed. Somehow tax date in this user exit 'ZXFYTU03' is document creation date which is system date.
    With 2nd option, service rendered date from sales order is copied to invoice doc, but the tax is calculated based on document creation date since the tax user exit 'ZXFYTU03' is being called first...
    Per this, coustom routine did not work...
    Refer: Service Rendered Date (VBRP-FBUDA) for SD Invoice

  • Delivery Date in Sale Order

    Dear All
    Delivery date in sales order should automatically changed or by defalt it should be after 2 days of creating the sales order.
    I have tried with lead time period and the ways given in the forum, but the schedule line/delivery date is by default coming as the day of sale order creation.
    Please guide me how to do it.
    Regards
    SB

    Hi,
    Goto Tcode: VOV8
    select sales document types
    goto request delivery date tab
    remove tick mark or uncheck propose delivery date
    and maintain lead time 2 days.
    thanks.

  • Two Delivery dates in Sale Order against one item

    Dear All
    I need two delivery dates in sale order. one is default at the time of creation sale order. second i need actual delivery date which will be confirmed by production planning department after analysis the order whether material can be ready on that delivery date or it need to change. Actual delivery date may vary from original delivery date and both need to preserve in system. kindly provide solution. best regards.
    Manjit

    You need to select the Availability & Transfer of Req. check box in Schedule Line Configuration.It will transfer the req. to PP.So while creating the sale order , schedule Lines will be confirmed as per the Available Stock.
    System will give you the Default Delivery Date as the Date added after Lead Time in days in the Configuration.Else system will give the Current Date.
    Best regards,
    Ankur

  • Schedule Delivery Date in Sale Order

    Dear All,
    I have an order on 03.11.2009 (today) and its last delivery date is 15.11.2009. It means that I have to deliver the complete order on or before 15.11.2009.
    So where can I put this date in Sales Order?
    Regards,
    Vishal

    Hi Vishal,
    Your Last Delivery Date can be entered in the "Requested Delivery Date" field in the sales order.
    By doing so, the system will give us a confirmation that whether the delivery can be made possible on the Requested Delivery Date or NOT (The status can be seen by going in to the Schedule Line Level of your line item).
    The system also gives us the NEXT POSSIBLE DELIVERY DATE with the confirmed  Quantity as a Second Line item in the Schedule line level.
    The System considers mainly the Material Available Date to come to a conclusion on the Delivery Date of the goods. Also, there are other activities (Loading Time, Transporation Planning Time etc) for which some time will take and that also need to be considered (The same can be seen by going in to the Schedule Line Level of your line item and then click the Shipping button).
    Your Scenario: In your case, the delivery can happen ON OR BEFORE the Last Delivery Date.
    So for that follow the steps:
    Step 1: Put the Last Deliv Date in to the "Requested Deliv Date" field in Sales Order.
    Step 2: After enetering the other necessary details in the sales order then Save it. Now go the Schedule Line level of your line item and look for the Confirmation of the Delivery Quantity on the Requested Delivery Date.
    If Yes: Then its your wish that you can Prepond the Delivery Date by giving the required Delivery date during your delivery document creation.
    If No:
    Then you have look for the Next Possible date. OR Make sure that you can manage all your other activities like Loading, Transporation Planning etc. in 10 - 12 days time and make your material Availabilty today and do the delivery.
    Reagrds

Maybe you are looking for

  • Apple TV 2 updating without USB cable?

    Hi, after failing to update to iOS 5 s/w on my ATV it tells me to connect to itunes from recovery mode. I have no micro usb cable to do this with.    - Can i update without connecting a USB cable?    - Where can i get one online (UK)? Because of wher

  • Order of photos in slideshow

    Hi From a slideshow in iPhoto with a theme and music from iTunes, I have successfully published it into iWeb. But. The order of the photos is different from the source file that I can view from the iWeb menu and from finder. I wish for the first phot

  • Bulk collect in pl/sql table SOLVED

    Hi All, TYPE r_nparameter IS RECORD( col1 tab.col1%TYPE, col2 tab.col2%TYPE); TYPE t_no_seq IS TABLE OF r_nparameter INDEX BY BINARY_INTEGER; the t_no_seq is not initialized. My Question is If we use t_itn_seq, in a BULK COLLECT operation in a select

  • How to register a Mobile device Id in the netweaver Administer login?

    Hello all,              How to register a Mobile device Id in the netweaver Administer login? I logged in as J2ee_admin and I see SAP Mobile Infrastructure under the Administration adn underneath I see Mobile device releated configurations But there

  • Language field Validation

    Hello   Currently we have a  DESCRIPTION field in English and French.I have a validation on this field IS_NOT_NULL(DESCRIPTION) But this only checks for the English version and not for French,so I tried to include LANGUAGE function like below: If (La