Diff between transit time - transportation lead time

Hi all,
What is the difference between transit time and transportation lead time?
Regards
Manivannan R

transpotaion lead time
is the time taken to arrange for a del i.e
your picking / packing and loadin time ususally this is done after material available date and ready for shipping point .....
means if fpr picking and packing it takes 1 days and for loading mat at shiping pint i takes 2 days then ur transpotation lead time wld b 3 days
transit time is whr is the time taken for the matreial dispatched from ur shipping point to reach the ship to party usually ur route.
ok

Similar Messages

  • The time for transit, transportation lead time and loading time of the mate

    Dear Friends,
    Please mail to me, where should I give the time for transit, transportation lead time and loading time of the material at the ware house.
    This is at the time of Transportation scheduling, for a specific material.
    With regards,

    i am giving u the exact & specific answer.
    please follow the menu path in SPRO
    IMG, Logistics execution, shipping, basic shipping functions, scheduling, delivery and tranportation scheduling, maintain duration,
    In that screen, maintain the settings
    Hope it answers
    Do reward points if it is useful

  • Transportation Lead Time and Transit time

    Hi All,
    How to calculate the transportation lead time and the transit time from the delivery document in SAP. Please clarify me.
    Regards
    Srikkanth

    Dear Srikkanth,
    [How to calculate Lead Time|lead time]
    Also refer:
    [Scheduling|http://www.sap-img.com/sap-sd/backward-and-forward-scheduling-in-sap-sd.htm]
    [Scheduling - |http://www.sap-basis-abap.com/sd/what-is-forward-and-backward-scheduling.htm]
    Best Regards,
    Amit
    Note: Path
    SPRO --> IMG --> Logistics Execution --> Shipping --> Basic Shipping Functions --> Scheduling --> Delivery and Tranportation Scheduling --> Maintain Duration

  • Stock transfer between storage locations and lead time

    Hello,
    We use stock transfer orders between different storage locations. Is it possible to maintain the transport lead time between storage locations somewhere or do in need to use routes and scheduling?
    rgsd
    GAR

    Hi,
    Try using movement type 313 and 315
    313 -- Transfer posting SL to SL --- Remove from issuing SL
    315 -- Transfer posting SL to SL  -- Placing in Receiving SL
    Regards

  • Difference between Req with insufficient lead time and lead time const

    Hi ,
    1) Can anyone explain the difference between Requirement with insufficient lead time and Requirement lead time constraint exception messages. Both seems to be similar for me with the compressed time.Also at what situations these exceptions are generated.
    2) what is minimum lead time required ,actual lead time and its calculation.
    Thanks...

    Check out
    http://help.sap.com/saphelp_scm50/helpdata/en/99/ed3a981d0f11d5b3fc0050dadf0791/content.htm
    particularly the section "Which functions of the operations relevant to scheduling are supported?"
    It will give you a flavour of what can lead to difference in planning.

  • DIFFERENCES between BASIC SCHEDULING and LEAD-TIME SCHEDULING.

    Hello SAP Gurus,
    Kindly let me know the differences between BASIC SCHEDULING and LEAD-TIME SCHEDULING.
    Looking for your early feedback.
    Warm regards,
    Kaushik.

    Hi,
    Basic scheduling :
    1.Basic dates are calculated.
    2.Exact to day.
    3.No cap reqmts are generated.
    4.uses the inhouse production time from material master.
    5.carried out automatically during planning run.
    In basic date calculation ( order start date/ order finish date ) the system always
    calculates backward scheduling.
    1. From the reqmts date the system subtracts the GR processing time to
    calculate the order fininsh date.
    2. From the order finish date the system subtracts the inhouse production time to calculate the order start date.
    3. From the order start date the system subtracts the opening period given in scheduling margin key to calculate the order opening date.
    Lead time scheduling :
    1.Exact to second
    2.ie production start date /time and finish date and time are calculated.
    3. cap reqmts are generated.
    4. uses times from routing.
    5. carried out only if the scheduling mode in MD02 screen is kept with indicator 2.
    From the order finish date the system subtracts the float after production to calculate the production finish date.
    From the production finish date the individual operations in the routing are scheduled backwards to calculate production start date.
    From the production start date the system subtracts the float before production
    to calculate order start date.
    Regards,
    nandha

  • LTP run ignoring GR processing time and Lead time

    Hi,
    I am trying to find out way to create a planning scenario (MS31) and run LTP (MS01) which will ignore the GR processing times and Lead times from Material master.
    I would like to use MCEC report (after running MS70 valuation) which will show the values only in my new fiscal year - for budgeting purposes. Currently because of the long GR processing times and Lead times in material master (sometimes even 60 days) - some planned values show in MCEC report 2 or 3 months before the new fiscal year and the last two periods of new fiscla year are empty.
    I would be grateful if you could help me with getting rid of these additional Times and adjusting the periods only for Report purpose. The desired final output should be that S012 table for this specific planning scenario has the values only in periods of the Fiscal year - without hitting previous Fiscal year last periods (due to lead /GR processing times).
    Thank you,
    Karol
    Edited by: Karol on Oct 12, 2010 2:50 PM

    Dear,
    Master data is taken from normal MRP views. there is no other setting is available. you can create a different matrerial number for LTP planning.
    Raj

  • Purchase-How could I consider Transit time and lead time in imported mat.

    My doubt refers about master data configuration of imported material.
    My sittuation is :
    Material - Lead Time:  (depend on source)
                   Transit Time: (depend on source)
    My company is responsable to transport all bought material. Besides, I can buy of differents suppliers.
    Considering these rules, It s impossible to fix dates in material master, because material purchase is related with center and not with supplier. By the way, I need to discover other master data to configure it maybe : Inforecord, quotization... Whatever...
    I need to correct this to generate Purchase order with dispatched date of my source against required date of my company after execute MRP.
    I tried to study this scenario but until now I ve not got a solution.
    Probably, you have had it before and can help me.
    I hope your help!
    Thank you!
    Regards!

    Create POs with respect to either PIRs (if you don't need to print out) or Contract/item, both of these are Vendor/material specific so you can set lead times accordingly .  Probably best to use Source List and set requirement in material master too (Purchasing view).
    Regards,
    nick

  • Product Specific Transportation lead time

    We need to maintain different sourcing lead times for different products in the "Transport duration" field of the "Means of Transport" of the transportation lane. The transportation lane exists between the Supplier and the DC. A single vendor would supply different products which may have different lead times.
    Could anyone kindly give us pointers as to how this could done in the TL ?
    Best Regards,
    Mukundan

    Hi
    as well as Sanjog's answer another option is to keep just one TL MOT record and instead use the Goods Issuing time on the product Location record to account for the different leadtimes of product from a supplier. This time is added to the transportation time on the TL. It is the "GI Processing Time" field on the GR/GI tab.
    Which method you use depends on the amount of different leadtimes you have from a supplier (a few and I would use Sanjog's method, more and I would use the GI time). The GI time can also be integrated in with the transportation planning of deliveries in the ERP system as well to give better visibility of milestones in the delivery tracking. (e.g. you have a planning point when the goods should be ready to ship as well as when they are due).
    Regards
    Ian

  • Difference between r/3 planning( lead time scheduling) and APO planning

    Hello APO Gurus,
    Please let me know the difference between the R/3 capacity planning by using lead time scheduling and APO capacity planning for a work centre.
    Both in both cases you can use the lead time from routing OPERATION.
    Please let me know where the planning differs.
    Regards,
    Ravindra Deokule

    Check out
    http://help.sap.com/saphelp_scm50/helpdata/en/99/ed3a981d0f11d5b3fc0050dadf0791/content.htm
    particularly the section "Which functions of the operations relevant to scheduling are supported?"
    It will give you a flavour of what can lead to difference in planning.

  • Purchase order with transportaion time+replenishtment lead time in PP/DS

    The process: Location 0011 buys by supplier 1080 with normal purchase order. 
    Delivery lead time 30 days of this 20 days transportation time and 10 days replenishment lead time of the supplier. Delivery free on board.
    What to do that the date for free on board is in the purchase order.for example.: Beginning November.
    And the inbound delivery date end of November in the md04 R3 and product view PP/DS.

    Yes 30 days is the total lead time . I am not so good in modelling of FOB in PP/DS.
    In R3 we have a not so good solution for FOB. There we have add the transporting time inte the GR Processing Time. This is not so good.
    The solution beeing
    in the  purchase order the date for finish the supplier on board
    and in the md04 R3 and product view PP/DS the to arrive in the firm location
    kind regards Feth

  • Whats the diff between copying a Transport request and Importing a request?

    Hi gurus,
    Can some one explain me the difference between copying a transport request between clients and importing transport request between clients? say for eg: difference between copying a transport request containing a datasource being copied from client 100 to client 200 and importing the same request from client 100 to client 200?... When do we follow such scenario's?
    thanks.
    kishore

    Hi Kishore,
    A request copy applies only for customizing (client dependent) objects.
    A request tracks object modifications since its last transport. if the object is created in source system and included in a transport request, when it is transported to another system, it will create the object in target system. Then if you modify the  object, it will include modifications since last transport.
    As i said, a request copy is only valid for customizing objects. This is entries in tables, you will see that you have two kind of requests, customizing and workbench. Workbench objects are client independent, so request copy doesn't applies.
    it's very important to keep the order of requests when you transport and also not to delete requests in any system.
    Hope this helps (and hope it is clear, if you have any doubt, just ask!).
    Regards,
    Diego

  • Delivery lead time in Sales Order--URGENT

    Hi SAP GURUS,
    How the Delivery lead time works in Sales Order  i.e
    "From the time a confirmed Sales order is punched till the time we have delivered the material"
    How to confgure to use effectively

    When you create sales order, system automatically proposes data based on configuration settings.
    1. Check the schedule line proposed by system in sales order. Let's say CP. Go to transaction VOV6 and see if availability check is checked.
    2. Check the requirement type proposed by system in sales order. Let's say 041. Go to transaction OVZH and see what requirement class has been assigned to it. Let' say 041.
    3. Go to transaction OVZG and see if availability check has been checked for this requirement class 041.
    4. Check the shipping point proposed by system in sales order.
    Go to transaction OVLZ and check Loading time & pick pack time maintained there for this shipping point. If there is nothing let's say we have 24 hours and 24 hours respectively.
    5. Check the route proposed by system in sales order. Let's say route selected is 000003. Go to transaction 0VTC and see Transit duration & Transportation lead times maintained there. Let's say timings maintained are  2  days and 1 days respectively.
    Now let's say a customer calls and says he wants a material delivered on Apr 25. Now what the system does is that it does backward scheduling. i.e. it goes backward from delivery date i.e. 25th April. It reduces 3 days for transit time, reduces time taken for loading time, reduces days taken for arranging transport, reduces time taken for pick pack. After calculation it arrives at date Apr 21. Now it checks whether material is available on this date i.e. Apr 21.
    If material is available, it confirms delivery date.
    Otherwise, if material is not available on Apr 21, it determines date on which material is available. Let's say material is available on Apr 23. Now, system immediately carries out forward scheduling. So it starts calculating from Apr 23 and adds time and dates maintained for picking & packing; transportation lead time, loading time and transit time.
    Also note that system takes into account factory holidays, factory timings when it is calculating above. If factory works 24 hours and is closed on Saturday & Sunday, system arrives at date Apr 30. It now confirms delivery date as Apr 30 to customer.
    I have given a simple example. There are many other aspects you can configure on scheduling.

  • Transportation lead,pick/pack & Transit time

    Dear Friends,
    After considering transpoartation lead time,pick/pack time,loading time & transit time system do confirm whether stock is available or not.....my doubt is whr do we maintain the above said times in the system?........

    Hi saravanakumar
    Transit time and Transportation lead time is taken  from or maintained in  Route
    Loading time and pick/pack time comes from shipping point
    You need to have clarity on backward scheduling  and  forward scheduling
    For example you are creating a sales order today 15.02.2009 and the requested delivery date is 25.02.2009 from the customer side
    Transit time is 2 Days
    Transportaion planning time is 2 days
    Loading time is 1 day
    Pick/pack time is 1 day
    Consider these settings
    Now backward calculation  System does a backward calculation first
    25.02.2009 (requested delivery date) -- 2 days (transit days) -- 1 day (loading time) -- 2 days (transportation planning time) = that is on 20.02.2009 there should be enough stocks in the unrestricted stocks and system checks stocks for this day or date ,that is 20.02.2009  ,whether the stock is available enough
    This date 20.02.2009 becomes the material available date
    Note Transportaion planning time and Pick/pack time will run parallely and the higest of these two is considered for delivery scheduling so in our case Transportaion planning time is 2 days that is the highest and hence it is taken for calculation and not pick /pack time
    If the system finds enough stocks on 20.02.2009 (that means it performs a availability check for 20.02.2009 depending on OVZ9 settings) that is material available date then it confirms schedule lines for that order this is backward
    Same example order is registered today 15.02.2009 and if the customer wants stocks on 17.02.2009
    This means 17.02.2009-2 days (transit days)-1 day(loading time)-2 days (transportation planning time) = 12.02.2009
    The order registered date is 15.02.2009and the material availablity date is past 12.02.2009 or material available date goes to past.
    This is illogical
    This means backward is failing here and now forward calculation takes place
    Forward calculation
    If you have enough stocks today 15.02.2009 + 2 days transportation planning time+ 1 day loading time+2 days transit time = 20.02.2009
    This means that is on 20.02.2009 the stocks can be confirmed for this order as against a requested delivery date of 17.02.2009
    In forward the system will give 2 schedule lines first that is requested delivery date that is 17.02.2009(in our case) with ZERO qty and the second date as 20.02.2009 with full qty
    In backward you will find only one date in the schedule lines which is the same as requeted delivery date that is 25.02.2009 in our case
    Hope i made things little bit clear to you
    Transit and transporatation planning will come from route if route is maintained otherewise it is taken as 0 days
    Loading and pick pack time will be maintained in shipping pt  if not maintained also then it is taken as 0 days (in enterprise structure logistice execution and your shipping point details it is maintained)
    Regards
    Raja

  • Related to shipment & transportation Dates & Time.

    Hi,
    Could you please tell me where can I find following dates & time in customizing.
    1) Transit time & transit date
    2) Loading time & loading date
    3) Pick/Pack time
    4) Transportation Lead time
    Also can you give one example of forward scheduling & backward scheduling.
    Thanks

    Hi..
    when u r creating sales order first system will go with backward scheduling if it is not reach the dates then system will go for forward scheduling.
    Backward Scheduling:
    material available datepick/pack time loading time transit timetransportation lead time
    for ex order dated is 1st req deliver date is 10th assume like this
    for pick/pack time = 2
    for loading time = 2
    for transportation lead time = 2
    for transit =5
    in backward scheduling from 10th
    522+2 = 11days it is taking that means it crossing the order date ate the time it will go for forward scheduling
    from 1st on wards 222+5 it will confirm 11th..
    this is happening when the material is available on 1st.
    If the material is not available then it will find material available date suppose that is on 3rd the sysstem will calculate like this 225 = 9 ( forward scheduling ) it will not consider Transportation lead time i.e( Lorry arrangement time ) because we can do this arrange ment between 1st and 3rd. then sys confirm on 3rd + 9days i.e 12th.
    Pick/pack time system will pick up from shipping point Transportation time ( Trans lead time+ Transit time ) is from Route. Transit time means travel duration time..
    Delievry scheduling will be started only from the material availability date i.e., system will first determine the material avail date and then do scheduling. By default Standard SAP system does Backward Scheduling in case material availability falls beyond the required delivery date system will do forward schedluing
    Delivery Scheduling consists of the following Basic activities:
    We give deatils while creating order:
    Order Creation Date
    Required Delivery Date
    Order date - Material availability date - Transportation Planning Date - Loading date - Goods Issue Date - Required Delivery Date
    Time Between GI Date and required Delivery Date is called Transit Time
    Time Between LoadingDate and GI Date is called Loading time
    Time Between Material Availability Date and Loading Date consists of 2 components - Pick / PackTime and Transportation Planning Time
    System has to calculate all this before it determines the confirmed delivery date
    Regds
    MM

Maybe you are looking for

  • Image in a table-header

    Hello, I don't know why but I cannot place an image in one specific table-header. It works fine in my table-cells but in the table-header only the text appears. I thought i could place an image in a header, just like a text-string but that is not pos

  • G/L account in cash and bank statement

    Dear All, How to fill the field GL account in the cash and bank statement ? I have press tab but still can't open the list of G/L account. Thanks Rgds, Mark

  • Configuring ACE 4710 for Load Balancing Speech servers

    Hello, I'm configuring ACE 4710's for the first time and I want to load balance my Nuance speech servers on port 554. Here's my configuration on ACE01: hostname ace471001 interface gigabitEthernet 1/1   switchport access vlan 1000   no shutdown inter

  • Calling a form in query mode

    Hi, I have a form "Ledger" in which i have a detail block with the following fields 1. Voucher no. 2. Date 3. Account Code 4. Posted and also i have a form master detail for vouchers entry...and it has three buttons for ENTER QUERY, EXECUTE QUERY AND

  • Windows 2012 Getting files ready for installation.....zzzzz

    Hi, I am using a windows 8.1 management workstation to manage my hyper-v 2012 R2 core server via Hyper-V manager. So I went to create my first Windows 2012 R2 STD with GUI, selected the Dell bootable ISO (6GB) and the installation has started. I wait