Hi,
We have raw material under 2 different location, one is under raw material warehouse, another one is under staging area which belongs to production. From time to time, we will issue stock from RM warehouse to staging area.
The stock GL account (either debit or credit) for the raw material is RM Stock (140001) when we do any movement.
But we do not want like this. We want that when there is any movement from raw material warehouse location, it will charge to GL account 140001 (RM Stock). And when the movement is from starging area location, it will charge to another GL account (140002 - production stock).
We want to seperate out the GL account for the raw material if they are under different storage location.
Can this be done?
Kindly please advise. Thank you.

Hi Sim
Valuation of Stock is done at Plant level and not Storage Location Level. Within a Plant, you can differentiate the G/L accounts based on the Valuation Class assigned in the Accounting view in Material Master.
The above settings enable automatic account determination at the time of GR. If you want different G/L accounts for different areas, there are 2 options:
1. Configure and Activate Split Valuation. This will enable you to give different Valuation Classes for different Storage Locations in Matl Master.
2. The better option is to make the 2 locations as 2 different plants and extend the materials to both these plants.
However, pls mention your purpose of differentiating the G/L accounts. If it is only to view the stocks in the 2 areas, there are many reports like MB52, etc.
Hope this clarifies.
Thanks

Similar Messages

  • Cost object for raw material consumption posting

    the raw material cosumption posting is done in the background when the goods issue is done. so where do we assign cost object for the primary cost element of raw material consumption account. since we create primary cost element for raw material consumption account, it will expect us to give cost object, so where we assign cost object for the raw material consumption cost element

    hi
    since the raw material cost is relevent for cost accounting u need to maintain primary cost elment accounts.When ever u confirm goods, the rm issue will take place automatically and will be debited to either product cost collector or production order. so u need not to assign any cost object for these consumption accounts why bcoz issues will take palce aganist a production order or product cost collector which is a cost object .
    regards
    siva

  • How To Find Opening Stock And Value For a Material

    Hi Experts,
    How To Find Opening Stock And Value For a Material  in Given Dates
    Moderator Message: Search.
    Edited by: kishan P on Sep 15, 2010 4:05 PM

    Thanks For Answering.....
    But I Need Any Function Module To Get Opening Stock And Value For Given Material With in Dates.

  • What are the possible cost objects for raw material consumption postings

    what are the possible cost objects for raw material consumption postings. i want to know whether it can be work order(maintenance order).

    For example, you are confirming a process order and issuing raw materials to the process order, the system in the background creates the consumption posting and will by default use the process order as a cost object.
    Similarly, when you are issuing materials to a work order, you will use MB1A and with movement type 261 and the system prompts you to enter the order number.  If you are using movement type 201, then the system prompts you to enter the cost center and so on.
    Thanks,
    Madhav Nanduri

  • No stock postings possible for this material

    Sir,
    while i try to post MB1A, i got this error "no stock postings possible for this material". kindly solve this issue asap.
    Regards
    Prince
    Edited by: Csaba Szommer on Dec 22, 2011 2:20 PM

    ok
    check these now---
    the  material which is giving error have to me managed as inventory managed material?
    in material master have you filled anything in the plant stauts field.
    check now in  EBD1 cross plant material fields
    may be u have blocked the material for the inventory activity via material master
    CHECK IT
    regards
    rohit

  • How MRP Run exclude QI Stock Type of a Raw Material SLOC?

    Dear all
    Fact:
    All of our raw materials must be subject to quarantinee upon GR. We have Storage Location of Raw Material: RMSL
    In Material Master of that Raw Material
    We are using the "SLOC of EP" (MRP View 2) to put the defaulted GR SLOC. And we also make use of the "Post to QI Stock" in View: Purchasing.
    Upon GR:
    During GR, the Raw Mat SLOC (RMSL) will be copied from "SLOC of EP" of the material master data, and it will be posted to the stock type "QI STOCK".
    Problem:
    However, when the MRP Controller run MRP, it will take the QI Stock Type of Raw Material SLOC into account.
    Is there anyway we can exclude the QI Stock Type of Raw Material SLOC from MRP Run?
    I have read from some threads to suggest to post it to the Quarantinee SLOC. We prefer not to create another Quarantinee SLOC (QISL) which will be filled in SLOC of EP and then after passing QC, we perform Transfer Posting from SLOC: QISL to SLOC: RMSL. We have a few Raw Material SLOCS and we do not want the Warehouse guy to get confused which Raw MAterial SLOC to choose upon GR. Rather, we prefer it to be defaulted in the "SLOC of EP" in the material master.
    Please advise.
    Edited by: Daimos on Jul 13, 2009 1:16 PM

    Hi,
    Generally MRP consider stock from all the storage location when run the MRP for Plant level for material.
    However we can exclude the particular storage location from MRP Run, for those following settings to be done.
    Go to MRP-2 View of material master and select the storage location to be excluded from MRP. (Press Shift +f1 ex .sloc2) As per your case it should be RMSL
    In that MRP view go to Storage location MRP Tab.
    And assign u201CSLoc MRP indicator = 1 (Storage location stock excluded from MRP)u201Dand save.
    Now run the MRP, stock from sloc2 will not be considered to create-planned order.
    Please try this and revert back.
    Cheers,
    Kumar.S

  • Report for raw material usage

    Hi All,
    i need to take the report for the raw material that used in the finished product.
    in the finished products, how much the raw materials are used .

    Hi Raj,
    Option 1. You can get the data from MARD, MAST & STPO tables.
    From MARD you can read the unrestricted stock i.e. LABST field.
    From MAST, read the finished product i.e. MATNR & WERKS (Material & PLant)
    From STPO read the component i.e. IDNRK & MENGE (Component & Qty).
    Option 2. You can get the data from MARD, AFKO, RESB tables.
    This would give you an exact consumption feedback.
    AFKO for production order details. (PLNBEZ for header material).
    RESB for components (qty consumed) for the order - Fields MATNR (Component), BDMNG (Req. qty), ENMNG (Withdrawn qty).
    You can now build the logic with the required multiplication i guess. If any further info is required, revert back.
    If helpful award points
    Regards,
    Vivek

  • QM for raw material 103 mv. type

    Hello QM Gurus,
    Please help me in following senario,
    When I am doing GR for the raw material, I am posting the stock to blocked stock through 103 mov. type.
    In system the inspection lot is being created but it is not in released status, although inspection plan is properly defined, hence I cannot do the result recording for the lot.
    If anybody can suggest where the problem is.
    Your king suggestion are expected.
    Regards,
    Amit Shirsath.

    I'm listing out some common mistakes because of which the Lot wont be in REL status.
    First in MM03 QM view -check for the inspection type(01) and 05 for other GR to be active.This should be fine in ur case since your are saying the lot is created.Make sure the check mark Automatic assignment to be checked ,Check characs and also Insp with task list.
    Second-Make sure the inspection Plan(QP01 display) was created with the same Key date as the Insepction lot or even earlier .The key date can be checked under qa03 to display Insp lot.
    Third-make sure the Usage is the same as in the Inspection lot.The usage is the one which links the Plan to the Lot .It should be 5 for GR from PO and 53 for other GR in the insp plan. You can check the Inscpetion lot usage by going to QA03.
    Check all these, ur problem should be solved.Please let me know if there is any furthur problem.And also reward if helpful and close the thread.
    regards,
    Naik

  • Separate GR/IR clearing account for non material

    HI,
    In the business, already an account is being used as GR/IR clearing account (WRX) for non material receipts (Non material means there is no material code exists in the system but at the time of PO a description is updated manually).
    There are in all two plants and at present all the non material values are getting posted to the same GI/IR clearing account. The requirement is to have a separate GR/IR clearing account for both the plants.
    Please note that its related to non material only and there is no material code hence no valuation class can be defaulted. Also if valuation class is kept "blank", the system allows only one entry of account.
    Please let me know if any exist is available on this.
    Best Regards

    Hi
    It can be done by defining different valuation grouping code for both the plants in OMWD. Then for the respective valuation grouping codes you can maintain different GL accounts in OBYC
    Thank You,

  • Different COGS GL Account for Sample Material delivery

    Dear All,
    Sometime customer is selling their regular finished product as Free Sample, but User want different COGS GL Account whenever he posts PGI for Free Sample material. I checked Split valuation functionality as posted in the forum, but our case finished material managed in the batches and price indicator is S. Appreciate your advice to cater this requirement. 
    Thanks & Regards,
    Santosh

    Hi,
    Option - 1.
    Try testing with GBB - VAX and VAY general modification key.  You need to take care of Cost elements for the GL account assigned.  VAX not a cost element and VAY with cost element. 
    Option - 2.
    You may have a utility which can run as a background job, which transfers the Standard COGS to Sample COGS account for the specific delivery type (only for sample Delivery document type).
    Option - 3.
    This is too lengthy for this requirement.  You might need to create a customer specific movement type. 
    Thanks
    Krish.
    Thanks
    Krish.

  • Cost Run for Raw Material taking Standard Price instead of Moving Price

    Hi all,
    We ran a material costimate with normal components FG>SFG>RM.  The RM price Control is set to
    V (Moving Average Price) and for SFG & FG it is S(Std. Price).  After we run CK11N, the price for
    RM in Material Master changes as per Moving Price.  We found that the RM Component is
    costed based on Standard Price and not on the previous cost run Moving Average Price.  After
    certain period, if we again do cost run, the sytem is again picking up the standard price for costing
    not the revised Moving Price.  We have checked the Valuation Variant in the Costing Variant, where the strategy given is 1. Moving Average Price 2. Standard Price.  We also tried to change the
    sequence as 1. Price as per Purchase Info Record 2. Moving Average Price and 3. Standard Price and
    also 1. Standard Price and 2. Moving Average Price.  Our requirement is when we run the cost estimate the raw material has to pick the price of previous moving price stored in the Material Master.  Kindly tell us where to set the indicator.
    Thanks,
    Sadashivan

    Hi Srikanth,
    Problem solved.  I checked the sequence in Valuation Variant and modified in Valuation Variant for Plant which I have not set previously and now the system is working correctly.
    Thanks,
    Sadashivan

  • CK24 error for raw material

    Dear All,
    We have executed CK11N of current period for single Raw Material ( w/o quantity struc. Selected in material master) and saved it, but when try to mark & release the material for the current period, the system  displays a message as u201COf 0 materials, 0 cost estimates were updated successfullyu201D. Its newly procured raw material.
    When we check in KEKO, KEPH & CKIS table the entry exists, but we are not able to execute the standard price for this raw material. In the start of this period we have executed CK40 for all the material (including raw materials) has been updated with standard price.
    We have deleted the costing run couple of times and recreated the cost estimation,but of no use.
    We have activated Material Ledger and this raw material has price control u2018Su2019 with price determination u20183u2019. We are in ecc 6.03
    Do suggest.

    Hi ,
    We are facing this problem for all type of material. Once we save cost estimation in CK11N  and when we try execute once again CK11n for the same material system is calculating Cost estimation again without error message and we are not able to Mark & Release the Cost estimation.
    Normally the system will not allow to calculate the cost estimation,if the cost estimation has been already calculated.
    We have currently changed price control S from V for all type of material to maintain Standard cost from Actual cost.
    Do suggest,if we have left out any config settings.
    We are facing this issue in production client.
    Do revert.
    Regards,

  • GR based IV Indicator do not appear in PO for Raw material

    Dear All,
    I am creating a PO for material with cost center . Vendor is maintained with GR based IV and ERS Indicators.
    If a non valuated material (i.e. with quantity update and without value update)  is used in PO , I am able to  see  Tick for GR based IV indicator.
    But in the same PO when Raw material( quantity update & value update ) is used , Tick for GR based IV indicator disappears although it is there in Vendor Master.
    Please provide your valuable advice/solution.
    Thanking you in anticipation
    Regards,
    Vishwas

    Hello,
    Check GR based IV tick in Purchase inforecord for Pur. Org., material and vendor combination.
    Regards,
    Shailesh

  • Auto G/L Account for UNBW material

    Hi
    There is a requirement to create a PR with  UNBW material and through an Internal Order (F). But the material does not pick up the G/L account automatically.
    For these Material groups in  customising - MM-Purchaing-Material Master-Entry Aid without material master - for the concerned material group valuation class is defined and for that valuation class in obyc G/L account has been assigned.
    Kindly help
    Regards

    If you create a PO with short text & with out MMD, The below setting is applicable.
    For these Material groups in customising - MM-Purchaing-Material Master-Entry Aid without material master - for the concerned material group valuation class is defined and for that valuation class in obyc G/L account has been assigned.
    and for UNBW material if you are raising against the internal Order,
    Check is whether the Internal order is for Cost Centre , if that is the case then
    Maintain the Cost Element for the Cost Centre.

  • Re: Quality Certificate requirement At MIGO for raw material

    Dear all,
    I have a requirement where I want the system ask for Quality certificate while doing the goods receipt. The system should not allow me to process the transaction-MIGO if certificate is not recieved.
    Please advice
    Regards,
    Vivek Sharma

    Hi Vivek,
    You need to perform following settings.
    Configuration
    Follow the path
    Run trx QCC0->QM in Logistics->QM in Procurement-->Define Control Keys.
    Here create your own control key
    Where you can set the rest data as per your requirement but for to check the check box for "Cert Required" is must be activated to meet the requirement relevant to this thread.
    Save
    Say you have configured your Control Key ZZ01
    Now just below this one small configuration is mandatory is Run trx QCC0->QM in Logistics->QM in Procurement-->Define Keys for Certificate Processing
    Maintain Description
    Execute it and go to "Define Certificate Types"
    Here either for your relevant certification type or  for new type (if you wish to create new), maintain the data as below
    "Certificate Required for Each Purchase Order Item" ==== Active
    "Certif. per GR Item" ==== Active
    "Certif. check required" ==== Active
    "Control W/O Certif." Set any error message, I would suggest to select "Without lot error message, with lot error message"
    "Enhanced cert. processing" ==== Don't Activate
    "No certif. confirmation at GR" ==== Don't Activate
    The rest settings are not important to maintain so leave them blank.
    At Master Level
    In QM view of MM for the material maintain "QM Control Key" that just created "ZZ01"
    and the certificate type that is just created or amended. under the procurement data.
    Maintain Q-Info record for Material - Vendor - Plant combination (QI01)
    Now as per your requirement system will ask for the confirmation for certificate receipt as Yes/No. under the Purchase Order data in MIGO at item level data.
    If you select "NO" to it it will not allow to post the GR.
    I hope this is what you were looking for.