Difference between process order and Production order

Hi Experts,
Can any buddy tell me the difference between process order and production order. Why process order is used for process industries. Why do we use recipe for it and routing for production order ?
Regards,
Amit

Hi Amit
There is a difference between production order and process order.
Supposing a 10,000 lit tank is being manufactured in discrete manufacturing. You have to follow the necessary routing steps and can make by physically seeing its development stage by stage. For this type production you can have a production order.
In case of process of order if some chemical in a reactor is loaded with intial temp of 30 C and need to be heated to 80 C then there is phase change. Hence we use Heating as an operation and the change of temp is phase. For such type of process we process order.
Hope this is useful. Pl reward.
Nanduri

Similar Messages

  • Link between Purchase Order and Production Order

    Hi,
    Could some one tell me how i could get a relation ship between Purchase order and Production Order after a Good receipt is done. Coz after a GR is done I am not able to see the production order for a particular material in MD04 transaction.
    Thanks,
    Arul.

    Hi Arul ,
    i think u may not get the LINK b/w Production Order and PO , Bcos--->
    check the process --->
    RUN MRP , here System will generate the Production Plan and PRs( based on the avail.of that Raw Material).So PO will be generated by PRs.So I think there is no link b/w Production and Purchase .
    this is based on the my system settings and my knowledge.
    Regards
    Prabhu

  • Process orders and Production order in PP

    Hi,
    In our case Process orders are used in most of the case ,than production orders. Pls tell wheather Process orders are also pulled by the extractors(PP) and behave similar in all the Standard PP reports. and what is the diffrence between Process orders and Production order??
    Regards
    Nair

    Hi
    In PP, you can see Production Planning and Production Planning -Process Industry
    Production order is for manufacturing industry
    Process order is for process industries where input raw material is processed to arrive at end product.Process order keeps shop floor person aware of processing status.If your client's business have many processes than manufacturing you might come across more processing orders
    Regards
    N Ganesh

  • Process orders and Production orders??

    Hi,
    In our case Process orders are used in most of the case ,than production orders. Pls tell wheather Process orders are also pulled by the extractors(2LIS_04_PEARBPL,2LIS_04_PECOMP
    ,2LIS_04_PEMATNR,2LIS_04_P_ARBPL,2LIS_04_P_COMP,
    2LIS_04_P_MATNR) and behave similar in all the Standard PP reports. and what is the diffrence between Process orders and Production order??
    Regards
    Nair

    hi,
    both are similar but varies with industries.
    Process order- used in chemical industries- involves process like heating, melting etc.
    Production order- used in car industries- assembling, drilling process
    Assign Points if useful
    Ramesh

  • Relation between Sales order and Production order

    Hi,
    In Make to stock scenario how the relation between Sales order and production order are related.In which table we will get the related fields (expect AUFK,VBAK,AUFO).
    warm regards,
    Surendar reddy.

    The relation between sales order and prodution order  is as follows.
    Pass AUFNR to AFKO/AFPO  Get AUFPL.
    Pass AUFPL to AFVC Get BANFN.
    Pass BANFn to EBAN Get EBELN.
    Hope this works .
    Cheers,
    Lakshmi Prasanna Gandham

  • Open planned orders and production orders

    Hi friends,
    I have one issue with my client.
    Client has 1 lac materials in sap .Now he wants extract all materials open planned orders and open production orders with quantity and dates.
    Please tell me the process how i can extract the data from sap for above requirement.
    Thanks,
    Manoj

    Hi Manoj,
    For open planned order and production order select the respective box.
    But one suggestion. Try to convince client that this report will take a lot of time as you have mentioned 1 lac materials are there.
    You can exclude system status and get it with below screen as mentioned already.
    But my suggestion is to run the report at night when the system load is very less. Please create a background job one for planned order and another for production order. Then run it in midnight as per the customer requirement in background. You can automate the process by sending automatic mail to customer. Please refer the below link to trigger mail.
    Mail Trigger with TEXT file via JOB run
    Regards,
    Krishnendu.

  • List of Sales order and production order

    I need the list of sales order and production order for the period 01.04.2006 to 31.12.2006

    Dear Nau,
    VA05 for list of sales orders and put Document date in Sales Order Data
    COIO Process order information System
    Regards,
    Rakesh
    Pls award points if you find the solution

  • Any stanard BAPI have both sales order and production order

    hi Experts,
    i need to Identify any standard BAPI have both sales order and production order. If such BAPI is not available, create 'Z' BAPI to do the same.it's my require ment?plz give me suggestion it's useful for my project. i will give good points.
    thanks and regards,
    bbm

    hi eswar,
    can you give me how to do? and what i can use import,export,table and sourcecode bcz i am new in BAPI side even now i am working in SAP XMII project.
    so plz guide me.
    thanks and regards,
    bbm

  • How BOM and routing is selected for Planned order and Production order?

    Hi,
    Can any1 plz tell me how BOM and routing is selected for a planned order and production order. ?

    Hello Mathisuthan,
    BOM and Routing selection for the planned order and production order through production version, If u have more than one BOM and more than one Routing then u can maintain this information as Production Version in the system.
    Production version you maintained
    MM01/MM02 -- MRP4--- Production version
    Or you can create Production Versions in Mass also with Transaction Code "C223"
    In the case no production version maintained/created  for the material, then system by default  will pick the first BOM and routing.
    I hope this information helpful to you.
    Regards
    Umesh Mali

  • Scheduling of planned order and Production order

    Dear PP gurus,
    I have run MRP , after running MRP, system has created planned order. These planned order dates are  schedule by the system in 2015....I am not able to understand. how? . When i  double click on
    planned order order and try to convert it in production order  those dates get copied into production order.
    DO i need to change the dates thr? or  keep the same dates  which the system is giving>
    I  m going wrong somewhere. please tell me where and   what is config for scheduling for planned order and production order?
    Please tell me step by step procedure
    Regards
    Edited by: Aadi1981 on Apr 1, 2010 9:02 AM

    Thanks for replying,
    I have done the below setting for shceduling. Kindly check and let me know any setting needs ot be changed or incorect
    FOr scheduling  production order , i have configured below settings in OPU3
    In OPU3 ,  
    Detail scheduling tab
    Scheduling and  Generate cap req tab is checked.
    then
    adjust scheduling , adjust dates  tab,    :  adjust basic dates , adjust  dep , reqt to operation date  is selected
    scheduling type is backward.,
    Automatic scheduling tab is  checked.
    In OPU5
    Scheduling of PLanned order
    Scheduling and  Generate cap req box  is checked  (selected)
    Adjust scheduling
    Sheduling level: via  detail  scheduling
    adjust dates:     adjust basc dates , adjust  dep reqt , req to  operation dates
    For capacity  scheduling ;  always  basic dates, dep reqts to operation dates
    scheduling type ; backwards
    apart from this do i need to do update  ca96/ ca97?
    best Regards
    Edited by: Aadi1981 on Apr 3, 2010 7:42 AM

  • Difference between Plannnig Horizon and Production Horizon

    Hai Can somebody explain me the difference between "Planning Horizon and Production Horizon"?
    Here is the text that led me to this question:
    "If the <b>Production Horizon</b> of SNP is smaller than <b>PP/DS horizon</b>, the <b>planning horizons</b> of SNP and PP/Ds overlap with each other." In this horizon, SNP determines the receipts with most cost effective sources of supply and lot sizes and PP/DS receipts generated by SNP in more detail.

    check the following entries in Product master
    The SNP production horizon is maintained on the SNP 2 tab page in the product master (transaction /SAPAPO/MAT1).
    It also appears in the PPDS tab page along with PPDS horizon
    The PPDS Planning horizon and PPDS Production horizon are the same. PPDs only plans inside this Horizon.
    What is outside the SNP production Horiozon lies in the SNP planning horizon. Actually thought the name is a bit misleading - SNP does not plan anything inside the production horizon.
    If you do not enter a value or you enter the duration 0 for the PP/DS horizon, the system automatically uses the SNP production horizon as the PP/DS horizon during planning. Therefore, the PP/DS horizon is exactly the same length as the SNP production horizon and this means that the SNP and PP/DS planning periods follow on from each other seamlessly and without overlapping.
    If the SNP production horizon is smaller than the PP/DS horizon, the planning horizons of SNP and PP/DS overlap. SNP and PP/DS can both use this overlapping period for planning.
    A gap between the end of the PP/DS horizon and the start of the SNP planning period is a time segment that is neither planned by PP/DS nor SNP. This can lead to inconsistencies.
    So think of two lines - one with its right side shaded(PPDS) and the other with its left side(SNP) shaded. Depending on where you place these lines the shaded sections get planned. how you get the two regions to mesh will ensure the effectivity of your plan
    you can also get a better understanding looking at the product view screen and changing the product master values for the horizons and running heuristics

  • Difference between process chain and event collector

    what is the difference between process chain and event collector and also plz explain about metachain.In what scenarios they are used.
    Many Thanks,

    hi,
    have a look at these help docs
    Process Chain:
    http://help.sap.com/saphelp_nw04/helpdata/en/8f/c08b3baaa59649e10000000a11402f/content.htm
    Event Collector:
    http://help.sap.com/saphelp_bw30b/helpdata/en/c1/6c0538c7cb583ae10000009b38f8cf/content.htm
    http://help.sap.com/saphelp_nw04/helpdata/en/6e/192756029db54192427cf6853c77a7/content.htm
    Creating an event colector:
    http://help.sap.com/saphelp_bw30b/helpdata/en/45/253d3873130057e10000009b38f842/content.htm
    regards
    sham'm

  • Price difference between the requisition and the order

    Hi All,
    There is new functionality in ERP6 that checks the difference in price price between the requisition and the order. The configuration is under Purchase Requisition -> Tolerance Limits -> Define Tolerance Keys. This is very useful functionality when the requistion item is approved at an estimated price, but a purchasing group needs to change the $ value it will block the Purchase Order.
    I have this configuration menu available in SPRO in one of my systems (IDES), however on a newly installed ERP6 system we are missing this menu path in SPRO.
    Does anyone know why this menu path in SPRO is missing on some systems...

    Thanks Henry,
    I've done some digging and the tables that store these config settings are part of US Federal Governement addons.
    Looks like all the (non government) sites that need it aren't able to have it. Great shame really as this would be very useful to communicate with the requestor whena  price difference occurs.

  • Difference between service request and service order

    hi all,
    What is the differnce between service request and service order? when to use what?
    Thanks
    Raghav

    Service Order -> "You use service orders to record the details of a one-off service agreed upon by a service provider and a service recipient. Service orders contain all the information needed to plan, execute, and bill for a service."
    Service Request -> "You use service request management to reliably submit, dispatch, approve, monitor, and fulfill requests for service by your customers. Service requests can be used internally by companies where a department delivers services, for example, in shared service center scenarios, as well as in external customer-facing scenarios.
    Service requests can be logged through a service desk, directly by the service personnel, or by the users themselves into the system and then, if necessary, can be dispatched to the appropriate personnel for service delivery."
    Taken from http://help.sap.com/
    Rg,
    Harshit

  • Internal order and Production order

    Hi,
    I didn't catch the difference between Internal and Production order
    Could You help me
    Regards

    Please refer to :
    http://help.sap.com/saphelp_srm30/helpdata/en/35/26b610afab52b9e10000009b38f974/content.htm
    http://help.sap.com/saphelp_sbo2005asp1/helpdata/en/32/7324f9cdb04cbbaee3dafa4487d4b9/content.htm

Maybe you are looking for

  • Itunes doesnot open on my pc

    this type of message shows on my pc when trying to open itunes. the file itunes library itl cannot open be read because it was created by a newer version of itunes.

  • Error Installing Sneak Preview SP11 on Windows XP

    Hi, I am getting the following errors while installing the NWDS Sneak Preview SP11 on Windows XP. ERROR 2006-02-10 12:23:37 FSL-06002  Error 1060 (The specified service does not exist as an installed service. ) in execution of a 'OpenService' functio

  • How to merge 2 images???

    i have 2 images which are 500*500 pixels, how to merge into 1000*500 pixels image?

  • Problems con opcenum after installing LabView 2014

    After installing LabView 2014, all other OPC compliant software (Matlab with the OPC Toolbox, Wonderware SCADA, OPC Demo Client from Softing, ...) previously installed on my PC (Windows 7) started to have problems in browsing OPC Servers. They were u

  • Mobile accounts reset to normal network accounts ?

    Hello I've switched my network users back from mobile accounts to normal network accounts after experimenting for awhile. I have deselected the mobile account preferences for all my machines in WGM and deleted all the local home folders created by sy