Different Plant in WO and PR

Hi
I have PM order with:
Planning plant: 0000
M Plant: 1111
But when PR is created from this order (operation has external service control key), it contains a different plant, I was expecting it to be 1111.
Where the plant is coming from in Purchase Requisition?
Regards

I have got the maintenance plant 1111 in all objects, including workcentre of the operation, operation itself..technical object, work order header etc....
But still when PR is automatically created it takes 0000 as plant in PR.
In my operation i have assigned service masters, and I want to also assign an Agreement to that operation. Agreement/item is created for plant 1111.
So whenever I enter agreement to the operation level, I got error about mismatch of the plant.
Other option would be as Thyagarajan mentioned above, I could create my Agreement/item with planning plant 0000 in it. But I have four different location (maint plants) which has their owns agreed rate...Our MM person created one agreement with multiple items such as item 10 for plant 1111 & item20  for 2222 & item 30 for maintenance plant 3333. May be i will have to chnage those plant to planning plant. if that what is SAP standard approach...
So there is no way to bring Maintenance plant of WO into auto PR? if not then i can use the above approach.
thanks

Similar Messages

  • Problems in having common material and batch in different plants

    Hi all,
    As the material with the same batch is existing in different plants, we are facing some problems in processing the Process Messages.
    If some user who belongs to a different plant is processing the batch for the material, the Process messages are not being sent the destination as we get an error message that the reservation is currently processed by user (who actually belongs to a different plant). This is effecting the Business.
    Can anyone tell me how we can prevent this? Could the reservation and Batch status set as plant level control via standard IMG change ?
    Regards,
    Brijesh

    Yes Rajanikanth,
    But can you please let me know whether it is not possible to restrict this so that the batch processed in different plants should not affect in our plant?
    Thanks.
    Regards,
    Brijesh

  • Number range of  accounting document for different plants

    whenever a billing document is created in SD (using the T-code VF01); an accounting document will be simultaneously created in the FI module. one document type(TS,number range---60:1 to 9999 ) have four  plants .different plants have own number range and sequential document number .
    eg: doc. type   num.range    fr       to           plant cty       co code
             TS           61            1        1000       PLANT_1      3100
                            62           1001    2000       PLANT_2      3100
                            63           2001    3000       PLANT_3      3100
                            64           3001    4000       PLANT_4      3100
    How can that carry out this function ?
    thank you for your help !

    Hi leung,
      As Mr.Rohit has mentioned it has to be done with the z table and the available user exit.
    Wht we have done is.we have created no ranges in obj rv_beleg.Eg
    AA   0000000001 to 0000099999
    AB   0000100000 to 0000199999
    AC   0000200000 to 0000 299999.
    Using the user exit we have created a Z table.And assignd for this ombination in the Ztable.
    Plant X   Billing type A   AA
    Plant Y   Billing Type A  AB
    Plant Z    Billing type A  AC
    Once this combination matches the appropriate invoice no range gets picked up.
    Regards,
    K.Vivek

  • PP-WM integration - staging pick parts across two different plants

    Hi,
    My requirements are as follows,
    I have a manufacturing plant A and a Sales plant B. For the vast majority of cases goods are manufactured in A, transferred to B and then sold. However in a minority of cases finished goods are transferred from B back to the manufacturing plant A to be consumed in the manufacture of a different finished good e.g. relabelling to another material number etc. Plant B is full WM HU managed.
    I want to enable pick parts staging via WM-PP. I am aware of the PP/WM integration steps in customizing but I am having difficulty in staging from plant B to A.
    I have set up a WM HUM managed storage location for the production supply area in plant A and assigned to the same warehouse as plant B
    Production Supply area is defined in Plant A
    Replenishment movement type is defined for storage type
    Storage Bin created in Plant A exact same type as bins in plant B
    Control cycle created to link Production Supply Area and Storage bin for component materials
    Process steps
    Create process order in plant A, list component material storage location as per production supply area storage location
    Process order staging creates the transfer requirement correctly
    However transfer requirement cannot convert to transfer order for staging. It does not appear to be able to recognise the stock in plant B and returns an error 'negative stocks not allowed in storage type'
    My challenge is as follows, is it possible to setup staging of pick parts between two different plants using WM transfer orders?
    Thanks in advance

    Hi,
    This is not possible. You can only stage from one plant and storage location - based on the supply area. The supply areas are maintained per plant and storage location and this is what the system will use for staging.
    Regards,
    Sinéad Curran

  • Batch Management in different plants

    Hey SAPers
    I am using batch managment for certain materials. But I don't need batch management of same materials in other plant. SAP is not allowing to change the status in other plants.
    Business needs to maintain materials in batches in warehouse but not in stores.
    Do we have a way out for this problem.
    Please respond.
    Thanks.
    Regards,
    MAM.

    dear abdul
    You can manage batches in different plants for many materials. For this reason, batches must be uniquely identifiable. In the SAP System, the batch number uniquely identifies the batch. You use the batch level to specify whether the batch number for a material is unique in one plant, or in all plants.
    You choose the batch level in Customizing for Batch Management under Specify Batch Level and Activate Status Management
    Batch Levels
    Plant level
    The batch number is unique in connection with the plant and material.
    The batch number is only known in the plant in which it was created if the stock is transferred to another plant, the batch is unknown in the recipient plant and the system does not adopt any data. You have to recreate and specify the batch in the receiving plant; that is, the same batch number may have different specifications in several plants.
    Material level:
    The batch number is unique in all plants in connection with the material.
    The same batch number has the same meaning for the material in all plants. One batch number cannot have different specifications in different plants. During stock transfer to another plant, the specification of the batch is known in the destination plant even if the batch is placed into storage in that plant for the first time.
    Client level:
    The batch number is unique in the whole client. A batch number can only be assigned once in the client. You cannot assign the same batch number for different materials.
    The batch number is only unique at the chosen level.
    Changing the Batch Level
    In the standard SAP System, the plant level is set as the batch level. If you want to use a different level in your company, you have to change it in Customizing and carry out a conversion program.
    You choose the batch level in Customizing for Batch Management under Specify Batch Level and Activate Status Management.
    While the conversion program is running, you can only post batches at the old level. You can only post batches at the new level after the conversion has been completed.
    You cannot change back from a higher level to plant level in the standard system. However, you can change the batch level from client level back to material level.
    To change the batch level from plant level to material level, the material has to be subject to batch management in all plants.
    This will help you for config setting:
    Logistics general - Batch Management
    1.1. Specify Batch Level
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Specify batch level and activate batch status management Transaction  OMCT
    1.2. Batch Number - Activate Internal Number Assignment
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Batch Number Assignment --> Activate internal batch number assignment Transaction  OMCZ
    1.3. Batch Creation - for Goods Movements 
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Creation of new batches --> Define batch creation for goods movements Transaction
    1.4. Characteristic Value Assignment -- Update Standard Characteristics 
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Characteristic Value Assignment --> Update Standard Characteristics Transaction
    1.5. Activate Batch Classification for Goods Movements in Inventory Management 
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Characteristic Value Assignment --> Valuation for goods movements --> Activate Batch Classification for goods movements in Inventory Management Transaction  OMCV
    1.6. Batch Determination – Condition Table(Cross Client)
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Condition Tables --> Define production order condition tables Transaction  OPLB
    1.7. Batch Determination – Condition Table(Cross Client)
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Condition Tables --> Define SD condition Tables Transaction  V/C7
    1.8. Batch Determination – Access Sequence(Cross Client)
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Access Sequences --> Define Production Order Access Sequences Transaction  OPLF
    1.9. Batch Determination – Access Sequence(Cross Client)
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Access Sequences --> Define SD Access Sequences Transaction  V/C2
    1.10. Batch Determination – Strategy Types
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Define Production Order Strategy Types Transaction  OPLE
    1.11. Batch Determination – Strategy Types
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Define SD Strategy Types Transaction  V/C1
    1.12.  Batch Determination – Batch Search Procedure
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Define IM   Search Procedure Transaction  OMCY
    1.13.  Batch Determination – Batch Search Procedure
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Define Production order Search Procedure Transaction  OPLG
    1.14.  Batch Determination – Batch Search Procedure
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Define SD Search Procedure Transaction  V/C3
    1.15.  Batch Determination – Batch Search Procedure Allocation
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Allocate IM search procedure/activate check Transaction  OMCG
    1.16. Batch Determination – Batch Search Procedure Allocation
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Assign Search procedure to production order Transaction  OPL8
    1.17.  Batch Determination – Batch Search Procedure Allocation(SD)
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Allocate SD Search procedure Transaction  V/C5
    1.18.  Batch Determination – Activate Automatic Batch Determination(SD)
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Activate Automatic Batch Determination in SD -->For delivery item categories Transaction  V/CL
    1.19.  Batch Determination – Batch Selection Class
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Define Selection Classes Transaction  CL01
    1.20.  Batch Determination – Sort Rule
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Define Sort Rules Transaction  CU70
    1.21.   Batch Determination – Make Settings for Batch Where-used list
    Menu Path  Enterprise Structure> Logistics General> Batch Management --> Make Settings for Batch Where-used list Transaction  OMBB 
    reward points if helpful
    thanks and regards
    ravikant dewangan

  • Stock transfer between 2 projects of different plants.

    Hi All,
    We have two plants and each plant as multiple projects. Some time it is required to transfer stock between two project which are of different plants. Currently we are using MOVEMENT TYPE 415Q , where stock transfer is done using 4 steps. Our client is insisting to do it in SINGLE step.
    Please advice whether it is possible.
    Thanks,
    Vengal Rao.

    Thanks Venkat,
    For the quick reply, but here I think using 415Q in MB1B  it has more than one step, and our projects are in different plants, I mean both project are of different plants.
    Please clarify.
    Vengal Rao.

  • InfoPackage to load multiple flat file for different plant

    Hi
    There is a requirements to load the data from multiple flat files by different plant into BI which source data is coming from other system. Each flat file has it own naming convention.
    As data has to load via infopackage into the targeted cube. Then I have to create multiple infopackage in order to load the data according to the number of flat files that provided. However, new plant will be created due to expansion of bussiness. If that is the case, additional infopackage is required to create as and when there is a new plant. 
    Is there a way to create a infopackage to load the data from flat file by plant? Your advice is much appreciated.
    Thanks and regards
    Kang Ring

    Hi,
    The best way I can suggest is....
    1. Create a folder in AL11 for your requirements.
    2. In InfoPackage under Extraxction Tab you can have File Name , just side of this you can fine ABAP Routines ICon there you click on that and asks Name give some and then it will takes to your into ABAP Code there you can access the AL11 and then write code in such way that to take file irrespective of the File name, whatever the file is there in that Folder it ahoud take from that AL11 Folder path.
    3. Load the Data using PC.
    4.At the end of the PC Delete the File in AL11 folder , becasue we don't need it for next load.
    Else
    See the thread
    Re: Automation of load from application server
    Thanks
    Reddy
    Edited by: Surendra Reddy on Jun 4, 2010 11:03 AM

  • While assigning batch material  get locked in different plant.

    Dear Guru,
    After  implementation ,frequently  facing problem, In CO02  we are  assigning the  batch manually  to the  material  but  one material  is  configured  with valuation type  domestic / import. while  assinging the  bacth to the material  system  showes to another  user  who iis entering the same material in different plant  is  xxxx  user is locked the material  so  u cant  assign  the batch, but   batch we are maintiaining  in   material level. (batch maintianed in material  level.)
    currently we are going  in sm12 transcationa and removing the lock, but   we want to know why it is happening. what is the root cause for the error.
    Please  advice.
    Thx
    Nara

    HI
    It is Standard SAP at a time same material or its masters cannot be used by multiple users ids or with same user id also
    system gives error material is locked.You can unlock it thru SM12 but be careful while soing so some the data which the another user using may be or may not be lost.
    the better way is to ask the user to come out of that material or release it after doing his work
    Regards
    Anupam Sharma

  • Procuring for 2 different Plants(Diff CoCd) in 1 PO

    Gurus
    I have extended a Material to 2 different plants belonging to 2 different Company Codes with a Centralized Purchasing Organization.
    E.g I used CoCd 0001 and 1000 in standard SAP system and two plants, each from these CoCds. The mat I used is extended to both these plants. In the PO I used a Purch Organization (Not assigned to CoCd, but to both those plants) and 0001. It worked!
    Plz lemme know...

    For information on maintaining purchasing organizations, see the IMG activity Maintain purchasing organizations.
    You have the following options:
    You can assign a purchasing organization to one company code. This is company-specific purchasing.
    You can assign a purchasing organization to no company code. This purchasing organization can then procure for all plants assigned to it, irrespective of the company code to which the plant belongs.
    Since each plant must be assigned to a company code, the company code can be determined via the plant in each procurement transaction, even if the procuring purchasing organization is not assigned to a company code.
    A purchasing organization must be assigned to one or more plants. This is plant-specific purchasing.
    For more information, see the IMG activity Assign purchasing organization to plant.
    regds
    ravi

  • How to maintain one vendor with differant plants at differant states.

    Dear All,
    i have one scenario with me in that my client purchasing his goods from one vendor that vendor is having two plants one at mumbai & one at gujarat. Now how i will maintain these two address with the same vendor. Along with that i need to mainatin the tax structure for both in one vendor. While creating purchase order how buyer will pick the tax structure.
    Regards,
    Nandkishor Nachane

    Hi,
      You can create one main vendor code and use partne function to add address of different plant location.
    regards,
    zafar

  • Different order unit for different plant

    Hi,
    I ahve a material whose base unot of measure is kgs. Its purchase order unit for plant 1000 is Tonnes, and I want to have a different purchase order unit say LBS for plant 1100. Is it possible?
    Please advice.
    Regards,
    Vengal Rao.

    Hi,
    You can maintain different order units for the different plants, since purchase view is at plant level.
    Order unit field is available in the purchase view.
    If required, you can maintain different order unit in the PO/Contracts other then the order unit in the material master record for that material and plant by activating variable order unit in the material master record - purchase view. In this way, you can maintain different order units in the PO for the same material and plant.
    Regrads
    KRK

  • Service order operations with different plants

    Hi,
    We would like to use different plants in our operations for service. This works fine but at certain operations we have set components (with backflush). While processing the service order these components receive the service order planning plant where it should be the plant mentioned in the operation.
    The reason why we would like to use different plants is because the material that has to be repaired will pass through those different plants. (or should we just create multiple service orders ?)
    Example :
    Task list created in plant 001 :
    Operation A plant 001 with component Y
    Operation B plant 002 with component Z
    The service order is created in planning plant 001 and when you go to the component tab, the plants of component y and z are set to plant 001 where it should be component Y --> plant 001 and component Z --> plant 002.
    Is setting the plant for components equal to the planning plant, standard behaviour ? (can't find anything to change this)
    Do i have to achieve this with a user exit ?
    with regards

    Hi dear,
    In that Case : u can create a single delivery...... AS the ccriteria for delivery split as per standard are
    1. ship-to-party
    2. shpping point
    3. route
    4. incoterms
    5. transportation zone
    Thanks,
    Raja

  • Stock Posting for Different Plants

    Hi MM Gurus,
    Is it possible to post directly to a Work Order reservation from a different plant?
    Example: A WO is raised and a reservation created for plant A and we want to move stock
    from plant B and post it directly against the reservation. Is there a one step process?
    Thank you,
    Jograd

    Hi,
    If you wish to do that, then open the production order, go to components tab, change the plant & sloc details in the component tab & save. Now you can post from the other plant directly via MB1A or MIGO or co27 with 261 mvt. If
    Hope it answers your query.
    Regards,
    Vivek

  • How to extend same material into different plants?

    Hi all,
    how to extend the same material into different plants anybody please tell me.
    thanks
    s.muthu

    hi
    go to mm01 create a material with name abcd
    then again in mm01 in material filed give same no (abcd)and  in copy from field also give that no(abcd)
    sytem will ask u for from and t locations give that and proceed
    similarly if u want to extend view in the material go to mm50 and do
    reward if helpful
    regards
    kunal

  • Standard movement to transfer blocked batches to a different plant/center

    I am trying to transfer blocked batches to a different plant/center where it is (from 2000 to 3000). Is there any standard movement which allows to move blocked batches to another plant/center without unblocking them?
    Thank you in advance.
    Edited by: TUBAGOL on Oct 1, 2009 11:11 AM

    Prerequisites
    For materials handled in batches, you can carry out stock transfers from plant to plant and from storage location to storage location as well as transfer postings from material to material.
    An issuing batch and a receiving batch are always involved in a stock transfer or transfer posting of a batch material. The issuing batch number is copied as the receiving batch number (except in the case of a plant-to-plant stock transfer in two steps). The batch number can, however, still be changed.
    Stock Transfers in Two Steps
    In a stock transfer from plant to plant using the two-step procedure, you enter only the receiving plant for the removal from storage. The stock in transfer is managed only at plant level in the receiving plant, independent of storage location and batches. You must enter the receiving storage location and the receiving batch when you post the placement into storage.
    In a stock transfer from storage location to storage location using the two-step procedure, the receiving storage location and the receiving batch are already determined during the removal from storage.
    After posting the removal from storage, the quantity is in stock in transfer. Stock in transfer is managed at plant level, as well as at storage-location level and batch level. As a consequence, you must enter the same receiving batch for the placement into storage. If you do not know the batch, enter * in the Batch field. The batch selection list is displayed. This list displays the stock in transfer for the batches in the Stock column.
    Procedure
    You can post a transfer from batch to batch by entering a different batch for a stock transfer using the one-step procedure. To do this, proceed as follows:
    From the Inventory Management menu, select Goods movement ® Transfer posting.
    Maintain the data on the initial screen. Choose one of the following movement types:
    u2013 Movement type ® Transfer posting ® Plant to plant ® Remove from storage/place in storage
    u2013 Movement type ® Transfer posting ® Stor. loc. to stor. loc. ® Unrestr. to unrestr.
    u2013 Movement type ® Transfer posting ® Material to material
    To maintain the items directly on the item detail screen instead of on the collective entry screen, select Edit ® New item.
    On the detail screen, you can enter an issuing and a receiving batch.
    Post the document.
    In a transfer posting to a new batch, batch data (such as shelf life expiration date or vendor) is copied to the new batch. Classification data is copied as well.
    In a transfer posting to an already existing batch, the data of the existing batch is retained.
    Transfer Postings From Batch to Batch, With Status Management
    In a transfer posting to a new batch, the new batch is given the status unrestricted use (even if the issuing batch has the status restricted use), unless the restricted-use status has been predefined by Quality Management.