Hi All,
I have a ROH which has direcet procuremnt (53) and planned delivery time of 2 days in matl master.
BOM of FERT has only this ROH.
When I create production order with "Current Date" scheduling, the purchase requistion is created automatically for the ROH. A scheduling log is created for a warning message "Can delivery date for material ROH be kept? Realistic date: 05.03.2009. System sets delivery date of ROH to past date.
My requirement is since this is direct procurement process, the system should propose the delivery date for ROH as 2 days from current date (Plnnd Delivery time) accordingly production order "Schduled start" date should be postponed for two days eventhough it is current date scheduling.
Looking forward your valuable answers.
Thanks
Guru

Hi Vivek,
Thanks for your reply.
I have already checked the setting for "Start in past". It is unchecked only.
Moreover this setting is for order start date related. It will not contol PR/PO delivery date.
The system need to consider planned delivery time of ROH before scheduling the production order.
Thanks
Guru

Similar Messages

  • Direct Procurement in Classic Scenario

    Hi Experts,
    We are on SRM 7 Ehp1, ECC 6 Ehp4.
    Classic Scenario.
    1. I have read in the forums , that in Classic Scenario, direct procurement is possible but the system behaves like Extended Classic and creates a Local PO. Just want to confirm this and if yes , does this happen as a standard or do we need to implement any BADI or anything to achieve this.
    2. Also , in Classic Scenario, PDP scenario , can we transfer stock items(Direct Materials) PR's into SRM system or are there any limitations.
    Thanks
    Aditya

    Hi Aditya,
    You are right. Classic system behaves as extended classic for Direct procurement scenario. Your PO will be created in SRM itself and a copy of this will be sent to ECC. This happens as a standard and no BADIs need to be implemented for this.
    Also in your classic system, you can transfer stock PRs into SRM. These will be available as shopping carts in the sourcing cockpit.
    Regards,
    Nikhil

  • Purchase order directly procured

    Hello all, I am working in SRM 7.0
    I know that when I create a purchase requisition with direct procurement shopping cart, default account assignment is U. But for example if shopping cart has all data complete and generate a purchase order, which account assignment put as default?
    Thanks in advance
    Rosa Rodríguez

    Hello Muthu, yes, I know that. But I am refering to purchase order that is created when you create a shopping cart as direct.
    If you create a shopping cart as direct and it generates a purchase requisition in SRM, then purchase requisition has as account assignment category U.
    In this case, I want to create a shopping cart as direct, but it generates a purchase order in SRM. Which account assignment category put?
    Thanks in advance
    Rosa Rodríguez

  • Which movement type to show Directly Procured material in stock?

    Hi All
    Is there another movement type that I can use to reverse from a network, Directly Procured material in to stock?
    Our issue is that we plan and have delivered directly procured material to out production plant (Plant A) and the PO has an account assignment of 'N'. The production team then decide (due to unforseen issues) that they do not need it anymore for that network/WBS and want to send it to our central warehouse (Plant B)
    In order to recover the cost from the network, we process MB1A mvt 222 with reference to the WBS in Plant A and then stock transfer to our central warehouse, Plant B
    My question is....can we use another movement type to remove the cost from the project/network/WBS and return the material in to stock?
    I don't want to reverse the PO but can i use that as a reference?
    Your help is appreciated
    Regards
    Darren

    MB1A transaction is a goods issue
    goods issues are valuated with the material master valuation price.
    in goods issues you cannot reference purchase orders (this is only possible in receipts)
    there is no goods receipt transaction for material which was already received against a PO.
    You credit the network with the leading price from material master, there is no value flow in the opposite direction. But you can control the valuation if you allow external value entry in the movement, which is usually not liked by auditors, especially as such movements are executed by warehouse personnel

  • Directly procured materials in stock help

    To All
    We currently have a problem when dealing with directly procured materials.
    Following a completed build of our product we have a surplus of directly proceured materials that have been ordered in error or are a result of specification changes.
    We want to re-use them for future demand. Therefore, we return them from a network and put into our warehouse and in a bin. The problem arises when the planners create a new demand because the material master data will order the part as a directly procured part and will 'not see' the one we are showing in stock.
    Therefore, my questions is, can a part be set up to look for stock initially and if no stock then order part as a directly procured part?
    Thanks in advance
    Darren

    Saleel
    The material IS in stock showing in the same Plant, Sloc and Warehouse that the planners use to plan the completed product.
    The material is in stock as it has been returned from the network (MB1A mvt 222) However, the material is planned in a BoM as a directly procured part as per the material master settings. When a new demand is loaded in the system, according to the material master settings it will order a directly procured part and not utilise the stock in the warehouse.
    I am looking for help that when a demand is loaded, SAP will reserve the stock of a directly procured part and not order externally.
    Movement 561 is an initial stock load movement type and is not recommended at any other time due to the lack of financial documents albeit a very easy way to load inventory. We use LICC/LX16 to adjust inventory in accordance with auditing rules.
    Thanks you for your response
    Darren

  • Activate order as a direct procurement button

    Hi Experts,
    We are on SRM 701
    Classic Scenario
    can anyone let me know whether we can activate order as a direct procurement button in item tab of SC? is it possible to activate it in classic scenario?
    Regards
    Elham

    Hello Elham,
    There are 4 ways of adding an item to the SC
    1. Selecting from the catalogs
    2. From Old SC and Templates
    3. Description of the Requirement as Free Text
    4. Product.
    From my understanding i think the checkbox 'Order as Direct Material" will be available for selection only incase when you select "Product". So i think it will be visible only for the materials which are replicated from ECC to SRM system.
    Can you check by trying to create a SC and then see whether it is available for selection.
    Regards
    Pramod

  • Rounding value for direct procurement

    Hi,
    I an sourcing the same material from another plant within the same client. The materiale is some times purchased as a standard material using rounding value and going to stock. But, in some cases the material is procured as direct procurement. When purchasing for direct procurement will it then be possible not to use the rounding value but just order the exact quantity?
    thanks,
    Anders

    Hi Andres,
    I think, you do not need to take any action on this requirement.  SAP works the way you wanted, by standard.  For example, you have a setup with a vendor (may be via info record or material master itself may have rounding qty etc)...not a problem.  The parameters you use in material master will control for procurement process either triggered from planning (or production ) or manual purchases.  When you create a SO# and if it triggers a purchase requisition, it sends exact quantity required only, into the preqs.  By standard SAP config, the message about rounding rules is just warning.  I don't think you will be stuck with this message when you try to convert the 3rd party Preq to PO.  Even if there is a message, it must just warning. 
    Let me know with these inputs, if you test both types of PO#s, how it goes.
    Regards

  • PO Error in Transfer for Direct Procurment

    Hi All,
    we are running SRM 550 and are at SP15.
    We need to get SRM to order Direct Materials for a storage location in our ECC system.
    So far all the config has been done,  materials transferred, storage locations defined in Org structure extended attributes.
    Problem is when I create a PO from a SC for direct materials I get an Error in Transfer and the error in RZ20 says that the account assignment is not valid for the ECC PO doc type.
    This all used to work in 2008 when we went live wih SRM but direct procurment was switched off because the business did not need it.
    In PPB_PD for the PO there is no account assignment data so I think this is where I have a problem.
    I must be missing some small piece of config somewhere that provides the account assignment GL for direct procurment but I can't find it.
    Any suggestions would be welcome.
    Thanks in advance
    Allen

    Hi Allen,
    Please create wildcard entries for AccAssCat in IMG  table               
    V_BBP_DET_ACCT, details see encl. file V_BBP_DET_ACCT.DOC                                                
    The issue is that even for subtype DP Direct Procurement Account         
    Assignment Category must exist, otherwise PO cannot be transferred       
    Accounting is going to be eliminiated one step later after ordering,     
    in background task, not visible to the user. Please realize!
    I have uploaded V_BBP_DET_ACCT.DOC to SAPMATS, click on the following link.                                               
    Link: [https://sapmats-de.sap-ag.de/download/download.cgi?id=LL0BCK4LD9DE7XZOG9M7WGGNG11AWE43UCBMUW1T05TKD1IOK2]
    Hope this helps,
    Kind Regards,
    Matthew

  • Direct procurement always as extended classic -- why ?

    Hi ,
    As per SAP's specification , ' SRM Server is the leading server for direct procurement. This means the system behaves according to extended classic scenario' .
    Is there any specific reason on why the scenario would always be extended classic for direct procurement ?
    And does this also imply that in a classic scenario, if a SC is created for a direct material which refers to backend material , the PO created would be in accord with the extended classic scenario ?
    Reasons/Answers --- Anyone ?
    thanks-
    Harmeet.

    Hi Harmeet
    Yes, even in classic scenario, if a SC is created for a direct material which refers to backend material , the PO created will be in accordance with the extended classic scenario by default i.e. a local SRM PO would be created which will be replicated to ECC. However you can alter this behaviour and force the system to create a PO in ECC (like classic scenario) by implementing BADIs.
    Regards,
    Nikhil

  • Direct procurement in Classic

    Experts,
    Need your help once again.
    I have implemented direct procurement in Classic scenario (SRM 7/ECC 6.0) and after reading on this forum, I realised that Direct procurement in classic, functions as extended classic because a local PO is created in SRM and this is replicated to ECC. So far this is working for me.
    Now I want to make changes to this PO. It is not allowing me to edit PO in ECC which is right because PO was created in SRM and copied to ECC. But strangely, I am unable to edit PO in SRM also?
    Is this correct behaviour?
    Please suggest.
    Best Regards,
    John

    Hi John,
    For direct procurement, it will have nothing to do with CS or ECS.
    SRM will create the local PO for direct material and transfer the PO into ERP.  And you could not change the PO in ERP.
    Regards,
    Guoyu

  • Manage direct procurement in classic scenario

    Hi Experts,
    We are on SRM 701
    Classic Scenario
    can anyone let me know how we can manage direct procurement in classic scenario?
    i want to kept goods in storage location and i cant do that because of account assignment tap in SC and as i know account assignment is mandatory to create a Sc
    Regards
    Elham

    Hello Elham,
          As suggested Account Assignment should always be used and one cannot skip it for creating the Shopping Cart. If you are having Classic Scenario then your PO would be in backend system directly which you can manage through dummy account assignment as guided you in your previous post. Just get in touch with your Finance Team and ask them to make a Dummy Profit Center/Cost Center which you can use while creating SC for your local Storage
    Thanks
    Gaurav Gautam

  • Direct procurment indicator in production order

    hi
    I found in a production order, there is a "1" maintained under "direct procurment indicator " which means "external procurment" for an item, and a purchase requisition is generated for it.  And in CO02 I just can't remove it.
    I wanna know where does this come from and what should I do if I wanna delete it, thanks.

    Dear Lauliu,
    1.For all non-stock items which are represented with item category N as BOM items,this is the standard SAP behaviour(system
    will be setting value 1 in direct procurement in the production order).
    2.Only by making that particular item as a stockable item(to be represented as item category L) this can be met.But I would
    suggest you not to make that change because generally the pipe line materials or any component that will be required for
    specific header material's order will be generally maintained as non-stock item and the purchasing data can be maintained there
    itself.
    for what business requirement do you want to change this?
    check and revert back.
    Regards
    Mangalraj.S

  • Planning Horizon & Direct procurement

    Hi, how touse the tabs planning horizon & direct procurement in oppr screen while running mrp?

    Hi Yadav
    The Settings of
    1) Planning Horizon in OPPR is meant for using Processing key - -NETPL (Net change for planning horizon) during MRP run : If u maintain the data say 100 days in this field that mean only those materials are planned in the planning run that have a change relevant to MRP within the period (in work days).The length of the planning horizon should at least include the following:
    period in which customer orders enter
    delivery times
    complete material processing time
    This setting is useful to restrict u r planning Horizon length to defined no of days say 100 days
    2) Direct Procurement : The setting controls whether direct procurement is initiated by the planning run or by the production order.Using this indicator, you can procure non-stock items directly for an order, bypassing the warehouse.Direct procurement for "parts to be provided" is not supported in subcontracting.
    U have to use Special Procurement key in Material master
    Regards
    Brahmaji

  • Direct procurement and Indirect Procurement in SAP AFS

    Hi,
    Can you diffrentiate between Direct procurement and Indirect Procurement in SAP AFS.
    thanks
    Aki

    Hi Aki,
    Direct Procurement
    Raw Material and Production Goods
    Order Qty: Large
    Value: Industry specific (Like shirt in apparel industry)
    Direct procurement supports the conversion of planned requirements to purchase orders.
    Primary Processes-Direct Procurement
    1. Determination of the materials and services required.
    2. Create requisition.
    3. Request for the quotation.
    4. Quotation Management.
    5. Vendor selection.
    6. Create Purchase Order.
    7. Goods Receipt and Invoice Receipt.
    8. Invoice Verification/ Vendor Payment.
    Indirect Procurement
    Maintenance, Repair and Operating (MRO) Supplies
    Order Qty: Low     
    Value: Generic (Machine Spare Parts in any industry)
    Indirect procurement supports the purchasing of indirect materials and subcontracting.
    This process can be dealt with using standard functions such as material requirements planning, purchase requisition, stock transport order, transportation planning and the handling of internal deliveries.
    The cross-plant, internal procurement of materials can be carried out within one company code (intercompany) or by using several company codes (cross company).
    Primary Processes-Indirect Procurement
    1. Requisitioning
    2. Purchase Order Management
    3. Receiving
    4. Financial Settlement
    Hope it helps.
    Regards,
    Anirban Roy

  • Direct Procurement and Indirect Procurement

    Please explain the different between direct procurement and Indirect procurement??

    Hi,
    Direct Procurement
    Raw Material and Production Goods
    Order Qty: Large
    Value: Industry specific (Like shirt in apparel industry)
    Direct procurement supports the conversion of planned requirements to purchase orders.
    Primary Processes-Direct Procurement
    1. Determination of the materials and services required.
    2. Create requisition.
    3. Request for the quotation.
    4. Quotation Management.
    5. Vendor selection.
    6. Create Purchase Order.
    7. Goods Receipt and Invoice Receipt.
    8. Invoice Verification/ Vendor Payment.
    Indirect Procurement
    Maintenance, Repair and Operating (MRO) Supplies
    Order Qty: Low
    Value: Generic (Machine Spare Parts in any industry)
    Indirect procurement supports the purchasing of indirect materials and subcontracting.
    This process can be dealt with using standard functions such as material requirements planning, purchase requisition, stock transport order, transportation planning and the handling of internal deliveries.
    The cross-plant, internal procurement of materials can be carried out within one company code (intercompany) or by using several company codes (cross company).
    Primary Processes-Indirect Procurement
    1. Requisitioning
    2. Purchase Order Management
    3. Receiving
    4. Financial Settlement
    Hope it helps.
    Regards
    KK

  • Direct and in direct procurement

    Hi experts,
    What is the Diff between Direct and In-direct procurement in SRM and i want to to config for Classic sceanrio.
    basis team has given me the servers now please let me know basic Config settings to Implement SAP SRM classic scenario,integrate with ECC.
    Smriti

    Hi Smriti,
    Indirect Procurement = The procurement what you do is not used in the end product of the manufacturing compay. Like Office peripherals,Computers, Stationary. What ever you have procured is not used in your end product
    The business scenario is Self Service procurement. Configuration part you can get from master guide from service market place
    Direct Procurement: The procurement what you do is used in your end product of the manufacturing compay. Example: If a mobile manufacturer company procures the keypads,battery,dispay screen...all these material is used in the end product. So these kind of procurement you called as direct procurement.
    Configuration for Direct Procuremtn will be as follows
    In R/3
    1. You need to configure two views i,e V_T160PR,V_T160EX and you need to schedule report BBP_EXTREQ_TRANSFER
    In SRM.
    1. Do the Technical settings like RFC Connections,Workflow Activations,Publish Templates
    2.(Imp Config)Dedine an entry channel for this (Create a new Org unit which acts as )
    3. Create a RFC user, so that communcation goes between R/3 and SRM
    4.In Org structure you have to define values for an attribute DP_PROC_TY .
    These are the config required for a PDP.
    Hope this explanation resolved your query
    Rg
    Sameer

Maybe you are looking for

  • Audio skimming in event library doesn't work

    Audio skimming works perfectly in my project library, and I can turn it on and off with the appropriate button. But audio skimming in my event library does not work at all! I've tried skimming slower, restarting iMovie and restarting my Mac one at th

  • Sorting within iPhoto albums:  eliminate carryover from prior manual sorts?

    I am working with a large series of photos from a recent vacation, arranging the images for captioning and sharing as slideshows.  I've pulled the images over to new albums, one per day, and would ideally sort them once by date, then change to manual

  • Deferred node loading

    Hi everyone. This is a bit of a cross-post because I didn't realise that this forum was here (I just posted in the Advanced Language Topics area). So I'm sorry about this, but I thought that I would have a good chance of finding out what I need here.

  • MySQL advantages with Java server

    Hi, all! It's not other question about "MySQL vs PostgreSQL". I read a lot of things on the internet about this topic. What I would like to know is that, cosidering that the Sun bought MySQL, does MySQL have any advantage over PostgreSQL when using a

  • Feather radius for selection depending on the image size

    Greetings everyone, I have a question about setting the feather radius for a selection depending on the image size. I'd like make the edge in the resultant layer mask have roughly the 'same' feather appearance for varying image sizes. For files below