Discount for the system / not for the components

At our case, the company sells machines. Some of the machines are systems which are made up with the combination-assembly of other machines. These systems are created-presented on SAP by an upper level material. There is no pricing fpr these upper-level machines-systems. There stand material BOMs which are created by the code CS01 for those systems. The price of those systems come from the sum of the price of the components. As I mentioned before, there is no price for the system and the system's material code itself. Thisis provided by the item type customizations. We want to make a specific customer discount when the customer buys a system. This means that a discount will be valid for the components when only they are bought as a part of a system. But if they are bought one by one we don't want make discount. We want to make discount for system sellings. How can we do this?
Thanks in advance.

Hi Yasar,
           Take Header pricing discount conditions 
1.HA00 if you are giving discount in % or
2.HB00 if you are giving discount value based.
If you take Header conditions you need to enter the discount manually at sales order.
Other process is you take condition type K004 and maintain condition record for that Header material (System).
I hope your requirement will be solved.
Regards,
Murali.

Similar Messages

  • The components for communicating with FTP servers are not installed.

    I'm running VS 2013 and when I try to publish to ftp site I get the following message. "Unable to create the Web site 'ftp://xx/'. The components for communicating with the FTP servers are not installed."   It has been running fine. I
    can publish to file system, web sites etc, just not through the ftp settings. I can access the ftp sites from my system, using other programs. It is not trying to connect to the ftp site at all.

    Hi paaccess,
    Glad to receive your reply.
    According to your description, since we can publish an application to ftp site in Visual Studio Prof 2013 in our side. Therefore, to further make sure if the issue is related to the VS IDE issue. We suggest
    you try to publish to ftp site on another machine you installed same version of VS Prof 2013 and then check it again.
    If you can publish on another machine, I suggest may need to re-download the
    VS Prof 2013 from Microsoft website and then install it again on your local machine.
    If you still could not publish on another machine, I think that the issue is not related to the VS2013 IDE issue. If possible, I still suggest you post the issue directly to the IIS.NET Forum:
    http://forums.iis.net/,
    it will better help you solve the issue.
    Thanks for your understanding.
    Have a nice day!
    Best Regards.
    We are trying to better understand customer views on social support experience, so your participation in this interview project would be greatly appreciated if you have time. Thanks for helping make community forums a great place.
    Click HERE to participate the survey.

  • Manual BRS system not picking the doc for clearing the payment

    While processing Manual bank statement if i am  using referance doc no system not picking doc no for clearing the bank payment. So that after finishing BRs I am matching the doc manually, in f-04. This is taking long time for processing. Anyone can tell me why ref doc no not working and to make it to work, or else any problem is there to use the field. please solve my query.
    Edited by: MANISFICO1 on Aug 1, 2011 11:49 AM

    Hi:
           Please follow as given and hopefully you will be able to resolve the issue.
    1...Go to SPRO...Financial Accounting....Bank...Business transactions...Payment Transactions...Manual Bank Statement..Create a new transaction with sign - and do not assign anything in posting rule for now and enter 15 in Algorithm field , save.
    2...In define posting keys and posting rules...create an account symbol for the one you did in step 1..In Assign account to account symbol please use account symbol created earlier and acc mode + and currency should be + too. In GL Account area please list the outgoing GL which you are using for outgoing postings..
    In create key for posting rule define a posting rule and now go back to step 1 and assign the posting rule you created to the transaction type
    In define posting rules please maintain posting rule as define above...in posting area assign 1. give nothing in first posting key.assign account symbol as created earlier...now give give posting key 50..give account credit Bank...and a suitable document you use for posting BRS...In posting type give 4.
    Your Manual Bank statement is ready ....
    Go to FS00 select your bank outgoing GL account there and in create/bank.interest tab double click on Field status group..in general data make assignment number mandatory for posting...
    Go to FB50....post and outgoing transaction using the GL given above it will require you to enter assignment number enter 123 and post.
    In FF67 Select the new statement , proceed with your normal data entry and give the transaction you created in above , enter value date, amount and in bank ref field enter 123 as given in FB50.
    Save and post it. Now it should work.
    Regards

  • VS Exp 2013: Unable to create the Web site ... The components for communicating with FTP servers are not installed.

    I have MS Visual Studio Express 2013 It has worked fine for many months and then suddenly (I have made no configuration changes or added new programs) when I try to publish I am getting the message:
    Unable to create the Web site 'ftp://ftp.xx.xx/xxx.org.uk/www/htdocs'. The components for communicating with FTP servers are not installed.
    (I have replaced actual name with x's).
    I had a similar problem some months ago and found that saving all files, closing VS 2013 and re-starting the program fixed the problem. This time it has not.
    I am at a loss to know how to take this forwards. I do not use IIS.
    Any help would be appreciated.
    Michael.

    Hi Michael,
    For web site development, so you use the VS2013 express for web, am I right? We have to make sure that it is not the VS version issue.
    As you said that it worked well before, did you install other add-ins or tools in your VS IDE like
    Xamarin or others?
    Maybe you could disable or remove all add-ins in your VS IDE, test it again.
    please also install the VS2013 update 4 in your side.
    Best Regards,
    Jack
    We are trying to better understand customer views on social support experience, so your participation in this interview project would be greatly appreciated if you have time. Thanks for helping make community forums a great place.
    Click
    HERE to participate the survey.

  • I am a student who subscribed to the 9.99 photography package, I didn't realize there was a discount for students.  I would like to upgrade to the full package with the student discount.  I can not find the option for this. How do I do this?

    I am a student who subscribed to the 9.99 photography package, I didn't realize there was a discount for students.  I would like to upgrade to the full package with the student discount.  I can not find the option for this. How do I do this?

    Hi Djmontanalv,
    Please go through the link below.
    http://helpx.adobe.com/x-productkb/policy-pricing/cancel-membership-subscription.html
    Regards,
    Anand

  • Employee Discount (from the company you work for, not Verizon employee)

    When trying to pre-order or now order an iPhone 4s while logged in to our account we get a message:
    "Employee Discounts will not be applied to this order, do you want to proceed?"
    If you say no then you exit, if you say yes then sure enough the voice, text, and data plans all are full price and do not show our normal discounts.  Order any other phone on a new line and they appear, order an old iPhone and they appear, but not on a 4s or the new 8gb 4.  I am not going to check with a 2 year contract showing a full price per month.
    If I try via the company link over at AT&T you could pre-order / order and get the company discount.  I have not checked Sprint.
    I was not expecting a discount on the phone, we never got those on any iPhone or many of the top 'droid models. I was expecting to keep the discount on the monthly voice and data dollars as we have been getting for years.
    Is this an error or perhaps the discounts are going to return after the launch excitement dies down?
    Thanks

    s2000 wrote:
    Thanks for the replies.  We are supposed to get 19% off voice and I think 20% off data. 
    The thing that bothers me is that if I choose anything except the 4s or 8b 4 then it shows me the discount on the service (none on the phone). It shows this as you pick the plans and again on the order summary screen.
    If I choose a 4s phone then (in addition to the warning message) it shows no discount on the service at all.  In addition you can't change the billing info - it is all greyed out.  Any order except 4s and you can modify the bill and ship info without a problem.
    So even though you SAY the discount should apply to the bill, I would be more comfortable it the ordering process actually reflected the discount - as it does for any other phone order.  Having a phone rep tell me the discount applies is worthless as that is not something you can take to the bank.  I guess I will wait until VZW fixes the ordering process for the 4s models...
    This same message existed during the Feb upgrades. If you search the forum you should be able to find these concerns. I upgraded and the same warning popped up. I have a 20% data discount and 16% voice discount. My discount did not disappear. Are you changing your plan during the order? If not, then changes to your account aren't being made. If you are changing to a global plan then it's possible the discounts don't apply to that (not sure if they exclude global plans) but otherwise, the discount on data and voice remains. Call CS and ask for a supervisor to get them to give you an answer so that you can be more at ease.

  • I have moved all of my movies from "Search for - All Movies" folder thinking they were shortcuts to the trash folder by mistake.  Is there any way I can restore them to the right place on my system Note most are on an external hard drive. :(

    I have moved all of my movies from "Search for - All Movies" folder thinking they were shortcuts to the trash folder by mistake.  Is there any way I can restore them to the right place on my system Note most are on an external hard drive.

    You can drag them out of the trash folder to wherever you wish. There is no automatic way to restore them.
    If you have a recent backup of your computer (at the risk of preaching, everyone should have one), restore them from there.
    Barry
    P.S. I have no clue what you did or why you have 44,000 on the external drive

  • I am the treasurer of our church.  Do you have a discount for not-for-profits on convert?

    Do you have a not-for-profit discount on convert?

    Good day,
    Unfortunately we do not offer any non-profit/not-for-profit or educational discounts for our Acrobat.com Services (Acrobat.com, CreatePDF, ExportPDF, FormsCentral, SendNow).  These services are all relatively inexpensive already.
    Please let me know if you have any questions.
    Kind regards,
    David

  • Use MF60 for split the components needs in a horizon of several days

    Hi to all,
    I'm working in my Industry to migrate the SAP system from a Repetitive mode to a Discrete one, and trying to launch the use of KanBan and MF60 usage, I'm not doing fine.
    I want to launch MF60 usage, through the bases of using it to distribute the need of components reserve in a Process Order (or several) in a daily frequency.
    I know it is possible to use the pull-list to propose only the replenishment quantity to be used in a time horizon given, for all Process Orders that uses "these" components.
    I ask for guidelines, as I don't know if I need to start building Kan Ban signals through PK transactions, or if I need to reconfigure some Material Master Views, as for the moment I'm not able to split the need as it is only proposing me the overall need of the order, even though I have already upload Resources, Master Recipes and Schedules to obtain a distribution in the Process Order lifetime.
    From what I know, the desire view to work on is the MF60 "Staging type: WM release order parts".
    I'll appreciate any information, or documentation you can share
    Regards,
    David P

    Hi Almeida and thanks for the response.
    I'll try to explain myself in a practical way.
    Now that it has being upload the Master Data in terms of resources and master recipes to work on a SAP Discrete mode, then I am working on the replenishment of components of the BOM's that are "signed" at the Process Order creation.
    My current situation in an example will be: If I create a Process Order for a 7-day duration, it makes the components reserves for the total, nevertheless I want to configure "somewhere"-"somehow" in SAP to be able to use the MF60 transaction to distribute the needs in a given horizon.
    With the scenario I have now, if I run the MF60 transaction for "that" order, no matter the horizon, it propose me the replenishment of the total need of the components minus the product already consumed. And even more, I only can run the MF60 with the "SLoc Level" view, and I have notice the distribution I need should be viewed under the "WM RelOrd. Parts" which is giving me a blank data result.
    What will be my desire usage of the MF60, is to use it to propose me the needed components inside the given horizon, so if I give a 1-day horizon, and expect to get the components quantity for that day.
    I hope, my issue is more clear now
    Thanks
    David P   

  • Xilinx wins Light Reading's Leading Lights Award for Outstanding Components Vendor to the Network and Comms industry

    Light Reading, a leading online publication for the network and communications industry, has just presented Xilinx with a 2015 Leading Lights award for Outstanding Components Vendor at an awards dinner held in Chicago on June 8 in conjunction with this week’s Big Telecom Event.
    There’s a very big reason that explains why Xilinx won this award.
    Equipped with the right IP and software, Xilinx All Programmable FPGAs and SoCs can implement single-chip systems, replacing ASSPs and ASICs entirely. This capability is critical in leading-edge applications where shipping volumes have not yet become—and may never become—sufficiently large to attract the ASSP vendors or to justify the NRE associated with cutting-edge, nanometer ASIC development.
    This is precisely the current situation for networking products that implement 100G and 400G Ethernet and other equally high-speed networking protocols including OTN.
    Quite simply, there is no better way to implement these products—especially with the introduction of the latest Xilinx 20nm UltraScale and 16nm UltraScale+ devices.
    The impact of the Xilinx All Programmable device portfolio on the development of Smarter Networks based on next-generation networking and communications systems is most visible in emerging applications including SDN and NFV, data-center compute acceleration, storage, and high-speed wired communications including Nx100G Ethernet and >400G OTN, 4G and pre-5G wireless radios, and wireless backhaul. Xilinx’s innovation in this space is apparent: Xilinx is the only company delivering a single-chip solution for 500G OTN transponders and 2x100G OTN switching applications with fully validated reference designs.
    Further, Xilinx, Huawei, and Spirent have demonstrated a prototype 400G Ethernet core router, based on Xilinx's high-end FPGAs. (See “Huawei and Xilinx unveil prototype 400GE Core Router at OFC 2104. FPGAs do the heavy lifting.”) This is the first prototype system to validate 400G Ethernet technology, which is still in its pre-standards phase. When standards are in flux, as they are here, Xilinx All Programmable devices are especially useful in getting early products to market. In addition, JDSU and IXIA have announced 400G Ethernet test systems based on Xilinx technology. (See “JDSU 400G Ethernet test platform at OFC 2015 based on Xilinx 20nm UltraScale devices”, “Single-chip 100G and 400G demos at next week’s OFC 2015 highlight UltraScale FPGA and Xilinx IP networking capabilities”, and “Xilinx and Ixia present 400GE and 25GE testing solutions at OFC 2015” for more information.)
    Xilinx owns 100% of the 400G Ethernet platforms announced to date.
    The Leading Lights awards are the telecom industry's most prestigious awards program and focus on next-generation communications technologies, applications, services, and strategies. Xilinx won the 2015 Leading Lights award for Outstanding Components Vendor out of a field of seven finalists in the category.
    For more detailed information on Xilinx and Smarter Networks, see “A Generation Ahead: SMARTER NETWORKS.”
     

    Curtis,
    I believe you can assign a style sheet to a TextArea control
    using the TextArea class's "styleSheet" property (see
    http://livedocs.adobe.com/labs/flex3/langref/mx/controls/TextArea.html#styleSheet).
    Peter

  • How can I use the same session for different components acroos application ?

    I am trying to include the components(chat, filesharing, whitboard) in different parts of my application. User should be able to access any of the component. We would like to have a single "ConnectSessionContainer" so that we don't see same user creating a seperate session for each component.
    Is there a better way of dealing with this other than declaring the "ConnectSessionContainer" in the main application ? Is there a way to check if we have a "ConnectSessionContainer" session already established ? Please help . Thanks.

    Thanks for the response. Let me explain what I am trying to do..
    I am trying to create components at different places(screens) of the flex application (not in the same .mxml file).
    Each time I create a component, I am using a "AdobeHSAuthenticator" and "ConnectSessionContainer" which is resulting a new participant in the room.
    For example
    screen1.mxml -
    <mx:Panel>
    <rtc:AdobeHSAuthenticator id="auth" authenticationSuccess="onAuthSuccess(event);" authenticationFailure="onAuthFailure(event);" />
    <rtc:ConnectSessionContainer id="mySession" >
            <rtc:Roster id="myRoster" width="100%" height="100%" />
            <rtc:Chat id="mychat" width="100%" height="100%" />
    </rtc:ConnectSessionContainer>
    </mx:Panel>
    screen2.mxml (in the same application) -
    <mx:Panel>
    <rtc:AdobeHSAuthenticator id="auth" authenticationSuccess="onAuthSuccess(event);" authenticationFailure="onAuthFailure(event);" />
    <rtc:ConnectSessionContainer id="mySession" >
            <rtc:SharedWhiteBoard id="wb" width="100%" height="100%" />
    </rtc:ConnectSessionContainer>
    </mx:Panel>
    Here, I open a screen1 and authenticate as UserA and when I try to open screen2 flex is considering me as another user though I am in the same application.
    1) How can I use different components which are in different flex files as a same User ?
    2) Should I place my <rtc:AdobeHSAuthenticator> and <rtc:ConnectSessionContainer> in the main application which calls the screen.mxml?
    3) What is the best way to do it ?
    Thanks for your time !

  • Buying a season one episode at a time - discount for the last few episodes?

    If I am not sure about a show, I would prefer to watch the pilot and maybe and episode or two before buying the season. Is itunes smart enough to know that if I buy an episode or two and then buy the season that the season price should be discounted by the cost of having bought two or thre episodes. Similarly, if you buy (say) 10 episodes of a 12 episode season, will itunes "give" me the last episode or two free because the cost of buying 10 out of 12 is the same as a season pass? If the answer is no to all of these, then does anyone have any tips how best to watch a pilot without having to pay for it?

    If I am not sure about a show, I would prefer to watch the pilot and maybe and episode or two before buying the season. Is itunes smart enough to know that if I buy an episode or two and then buy the season that the season price should be discounted by the cost of having bought two or thre episodes. Similarly, if you buy (say) 10 episodes of a 12 episode season, will itunes "give" me the last episode or two free because the cost of buying 10 out of 12 is the same as a season pass? If the answer is no to all of these, then does anyone have any tips how best to watch a pilot without having to pay for it?

  • Exit for changing Components in ME21N based on the production Order

    Hi,
          I have a scenerio in which, while creating PO in ME21N for subcontracting(Item category 'L') against a PR, the components for the material should come with my own logic i.e. it will have its production order number, with this production number i will get material of production order. Now i will get the BOM of this material and want to fill the next screen with the same BOM components. So please can anybody help me out how to work out for this problem. I looked for user exit and BADI but was not able to find anything, or is there some other way to do it. Help will be highly appreciated.
    Thanks and regards,
    Pankaj

    Hi,
                 Anybody having any idea. Plz help with your ideas if it is possible to do or not.
    regards,
    Pankaj

  • [svn:fx-trunk] 5170: Round 2 of bug fixes for the Spark skins for Halo components.

    Revision: 5170
    Author: [email protected]
    Date: 2009-03-04 17:50:32 -0800 (Wed, 04 Mar 2009)
    Log Message:
    Round 2 of bug fixes for the Spark skins for Halo components. Thanks to Alex for help with the data grid issues.
    Bugs fixed:
    SDK-19655 - Setting rowCount property on DataGrid causes extra blank row to be displayed
    SDK-19652 - Items in a DataGrid do not line up after scrolling.
    SDK-19605 - disabled Halo ColorPicker with Gumbo skin draws too dark
    SDK-19596 - When you have a single button on an Alert, the left edge looks flatter than the right
    SDK-19585 - Menus compiled with the halo theme in Flex 4 have a different backgroundColor than in Flex 3
    SDK-19665 - Halo List with Gumbo skin doesnt draw the alternating item color all the way to the right edge of the control if VScrollBar is present
    SDK-19651 - odd header rendering issue on Halo DataGrid with Gumbo skin
    QA Notes: The alert layout code was positioning the buttons/text on sub-pixel boundaries if the width or height of the alert was an odd number of pixels. We always snap to pixel boundaries now, but this may cause bitmap compare issues with Alert.
    Ticket Links:
    http://bugs.adobe.com/jira/browse/SDK-19655
    http://bugs.adobe.com/jira/browse/SDK-19652
    http://bugs.adobe.com/jira/browse/SDK-19605
    http://bugs.adobe.com/jira/browse/SDK-19596
    http://bugs.adobe.com/jira/browse/SDK-19585
    http://bugs.adobe.com/jira/browse/SDK-19665
    http://bugs.adobe.com/jira/browse/SDK-19651
    Modified Paths:
    flex/sdk/trunk/frameworks/projects/framework/src/mx/controls/DataGrid.as
    flex/sdk/trunk/frameworks/projects/framework/src/mx/controls/alertClasses/AlertForm.as
    flex/sdk/trunk/frameworks/projects/framework/src/mx/core/ScrollControlBase.as
    flex/sdk/trunk/frameworks/projects/halo/defaults.css
    flex/sdk/trunk/frameworks/projects/sparkskins/src/mx/skins/spark/ColorPickerSkin.mxml

  • Subcontracting PO - Batch number to be made mandatory for the components

    Hi All,
    I have a situation in Subcontracting PO. The components which are sent to vendor need to be updated with Batch number. Is there any User Exit  / Configuration available, which can provide a error message to the user when ever he tries to save the PO without the batch number entered for the components.
    SAP allows to save the SC-PO, if the batch numbers are not entered for the components which are batch managed. I have checked the PO Fields in Customizing, which has control of the Batch number for the header material in the material data tab & not for the components which will be available after the BOM icon is clicked.
    Appreciate if you experts provide a solution / work around for the above scenario, as the client is a pharma client & they need to exactly match the batch which has been sent out for making Finished product with the Sub contracting vendor.
    Thanks for your help & awaiting your reply at the earliest.
    Regards,
    Sathya Padmanabhan

    Hi,
    you shoudl definitively check out SAP best Practices for Pharmaceuticals, which can be foubnd in the helpportal:
    http://help.sap.com/bp_pharmav1600/Pharma_US/index.htm
    Go to the Business Information area....there are some subcontracting scenarios....
    Oliver