Hi,
In CM01 transaction Menu click on Settings -> General;
In the data area Interval to be evaluated start field will be blank by default. you can enter in -value so that start date would go in past.
click on Time periods button . check Period of database selection From date. You can get details only from the date for the Overall profile attached.
if this has not solved your purpose, you have to change OverallProfile.
Planning -> Profiles -> Overall Profiles.
Select another Overall profile.
Regards,
Krishna Mohan

Similar Messages

  • Capacity Load in a Work Center

    Dear Sir,
    i would like to Displaying the Capacity Load in a Work Center for the previous periods . that is for the last two months i would like to know the capacity load in my work centre. in mc01 capacity load are displayed for the future but not in the past
    thanking you
    arun kumar

    Hi,
    In CM01 transaction Menu click on Settings -> General;
    In the data area Interval to be evaluated start field will be blank by default. you can enter in -value so that start date would go in past.
    click on Time periods button . check Period of database selection From date. You can get details only from the date for the Overall profile attached.
    if this has not solved your purpose, you have to change OverallProfile.
    Planning -> Profiles -> Overall Profiles.
    Select another Overall profile.
    Regards,
    Krishna Mohan

  • What will happen if a maitain both standard available capacity and grouping key ( shift definition and shift sequence) in the capacity header of a work center?

    Hi all,
    Im little confused with the capacity header in work center. In the capacity header there is one place to give start time, end time, length of break and number of individual capacity. And in grouping key i can define the shift and shift sequence. So if im maintaining both of these ( standard avilable capacity and grouping key), which will be considered to calaculate avilable capacity?

    Hi
    If you are running three shifts ,please maintain the data as given belwo
    start :00:00:00
    End:23:59:59
    Break :03:00:00 ( 1 Hour per shift so 3 hrs for 3 shifts)
    No.of individual capacity :1
    System will understand that it is round the clock operation with total three hour brak and you will get 21 hour per capacity
    Hope this helps
    regards
    Prakash

  • BAPI for reading capacity of a workplace/work center?

    Hi,
    I'm looking for a BAPI/RFC using SAP MII to read the capacity of a workplace/work center in a given time period (eg. one or more days/weeks/...). I would like to use the import parameters plant ( WERKS ), date from, date to, workplace/work center (eg. CRHD-ARBPL ) and capacity category (eg. KAKO-KAPAR ). As output I would like to get a list of (planed/used) capacities as the working time for the given time period at the specified workplace/work center.
    In theory the BAPI CBP_EXC_WC_CAPACITY_REQUEST nearly does what I want. The only drawback is, that it outputs the "wrong" time.
    Let me give an example: The work center uses at a given day a capacity from 6 to 22 clock, including one hour break. This gives us a working time of 15 hours for this workplace and day. And "15h" is the time I need. But as there are working 5 worker at this work center the BAPI CBP_EXC_WC_CAPACITY_REQUEST returns 75 hours (which is 5 * 15). But the result "75" is useless for me as long as I don't additonal get the number of workers.
    I've searched in our SAP system and in this forum, but wasn't able to find another BAPI that gives me the correct time. As an alternative I would need another BAPI to get me the number of workers for a workplace/work center at a given time. But I also was out of luck finding one.
    Looking out for help,
    Simon

    Thanks for your fast reply!
    I have looked to both functions before. Beside that they are both not remote enabled (which is not such a big problem as I could copy them or build a custom BAPI around them) I'm not quite sure how they could solve my problem.
    If I got it right, I would first use CR_CAPACITIES_OF_WORKCENTER to get the KAPID and using it as input for CLOI_WC_CAPACITY_READ. But I have problems to understand the output of CLOI_WC_CAPACITY_READ. The data type of the capacity is a float ( FLTP ) and the number seems to be to big, eg. 9.800000000000000E+01= 98h for one day.
    Could you try to explain your solution once again?
    Thanks,
    Simon

  • What is the link between material processing & work-center

    Hi all,
    I have two types of material & few work center.
    How can I determine, that which work centers could be applied over a specific material for the material processing.
    Regards,
    Saurabh

    Dear Saurabh,
    You may allocate one or more capacity categories to a work center.  Capacity categories are defined in customizing.  Examples are labor, machine, energy and so on. 
    You must maintain data to enable the system to calculate available capacity at that work center for that category.  Examples include calendar assignment, start time, stop time, length of breaks, utilization, number of individual capacities. This is maintained in the capacity header screen of the capacity category for the work center. 
    If you indicate that a capacity is pooled, then it may be used by several work centers.  An example is a setup team.  They can perform setups at several work centers but can only work at one work center at a time. 
    Routings within a routing group are used for producing similar materials. One routing group can also contain routings with similar production processes.
    The alternative sequence enables you to select alternative operations for a sequence of operations - for example in the case of different work procedures for different batch sizes or capacity bottlenecks.
    The parallel sequence enables you to process operations independently of others.  
    A routing contains the operations to be performed, their sequence and the various work centers involved to manufacture an item. 
    A routing can include the following:
    *The standard values (times) for activities such as setup and processing 
    *Work centers where the operations are performed
    *The material components allocated to the operations
    *Any production resources / tools necessary to perform the operation
    *Inspection characteristics for operations where inspection is carried out
    *Instructions of what to do at each operation
    *Skills required to perform the operation
    Reward points if it is helpful.
    Regards,
    Naveen.

  • Is it possible to find the Equipment for given PP work center?

    Hello PM Masters,
    Is it possible to find the Equipment for given PP work center?
    Please tell me which table will lend me the EQUNR when I have the PP work center (ARBPL).
    Thank you.

    Yes,
    Provided you maintain this value in Equipment master Location tab like this.
    And then query by this field in IH08
    Jogeswara Rao K

  • How do you display the capacity/free space for the hard drive......

    How do you display the capacity/free space for the hard drive on the desktop, under the hard drive icon.... I have seen this done, but I am not seeing any options to do so.... thanks.

    View, Show View Options…, Show item info checkbox.

  • Itunes will open, but I cannot play any songs, nor enter the store.  It displays the message 'itunes have stopped working' and then closes

    I went in to use itunes today.  It opened up right away, but I can't play any songs nor enter the store.  It displays the message ' itunes has stopped working' and then closes.  I tried removing itunes and reloading.  Same thing.  This is on my PC.  My wife can still open itunes on her PC.  Can anyone help?

    Hello printer12
    Start your troubleshooting with the article below as it goes over issues with iTunes crashing and multiple options to troubleshoot.
    iTunes for Windows XP: Troubleshooting unexpected quits, freezes, or launch issues
    http://support.apple.com/kb/ts1421
    Regards,
    -Norm G.

  • Pooled Capacity Not updating in Work center

    Hi All, I want to update pooled capacity in Work center. But when i delete the existing capacity it is giving error that " Capacity still being used". Can any one suggest,how to tackle this problem? I want to give solution to Client. Thanks in Advance..!

    HI,
    Capacity Utilisation rate = Actual Capacity / Theoritical Capacity
    Theoritical Capacity= Shift period * No. of machines available
                                 = 8 hrs * 2 = 16 hrs
    Actual Capacity value depends on how the company decides it. Say if the break 30 mins has to be considered, then the actual capacity will be 15 hrs for 2 capacities and hence,
    Capacity Utilisation rate = 15 / 16 = 93.8%
    So, decide the utilisation rate based on the Company's requiremnt.
    Hope the above gives you an idea.
    -Thaila Shree

  • Capacity Planer Group --- Maintenance work center

    Hi,
    I have a query
    1. like do we have to create capacity planner groups same as the planner groups in equipment master data....Do they have any link??
    2. What would be the start time and end time in maintenance work center, for 24 hrs open manufacturing industry with 3 shifts???
    thanks
    DM

    Hello Deepak,
    There is no relation between capacity planner grp & Maintenance planner group...These are 2 different things..
    Now the work centers can be defined for the technicians if  HR module is not implemented...
    To perform the capacity planning for the technicians, there daily working hrs must be maintained in the system..Though the maintenance is working for 24 hrs,Single technician cannot work for entire 24 hrs..
    Hope this will help..
    Thanks

  • Different activity type for different capacity category in a work center

    Hello,
    Multiple capacity categories can be created in a work center like
    Engineer
    Sr. Engineer
    Architect
    Rates for all of them will be different (obviously) , however we can only have 1 activity type as default in a work center . We intend to 'HR assignment' corresponding to each capacity category . how can we have multiple activity type for different capacities (Engineer , architect etc).
    With regards,
    Mrinal

    Hi Paulo,
    thanks for your quick reply.
    Requirement is to assign all persons (Engineer, architect ) to 1 work center and to 1 activity , but to default different activity type (corresponding to capacity category) in worklist of time sheet .
    With regards,
    Mrinal

  • Changing the validity date of a work center.

    Dear SAP Guru,
    We are trying to change the validity date of a certain work center via transaction code CR02, however, we can only see the changed validity date in the validities tab (Costing View) but still the default validity date is the first validity created. We are trying to delete the Cost Center assignment for the unwanted validity date but still it came back to the first validity created. Is this a natural SAP behavior or is there something that we still need to do so that we can default our desired validity date?
    Thank you in advance for your help.
    Best regards,
    JMT

    Dear,
    Go to KS04.. enter the cost center. Enter the time period for which u want to delete the cost center. enter the date upto which u wanted the end date as the start date of the deletion.... it will delete the cost center for the future time period.... this will do....Then create new one and assign to work center and then check.
    There is no validity period for work centers...this will be available as long as you use in the routing.
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Apple 23" Cinema Display - The USB Ports Are Not Working

    The USB ports on my Cinema Display are not working. I do have both Tiger and Leopard installed on my Power Mac G5. Does this issue have to do with Leopard? If so, how can I fix this issue?

    I would power down everything, disconnect the monitor from the computer, and the power from the computer and the monitor, wait 15 minutes, and reconnect the power. *Double check* your monitor connections, make sure the USB is properly inserted to the compters USB port. Might try a different port. If the USB ports of the computer work with known working devices (like a keyboard) and the problems continue, it looks like the monitor ports have a hardware problem.

  • Why the second loader doesn't work?

    Hi,
    If I keep the first following action script (Adobe Flash CS4 Action Script 3) which is in BLUE it is workng fine. But If I keep the both action scripts which are in BLUE & RED. It shows nothing. What is the problem with the next one. Please do help.
    var l:Loader=new Loader();
    addChild(l);
    l.load(new URLRequest("MyLogo.swf"));
    l.x = 10;
    l.y = 100;
    l.contentLoaderInfo.addEventListener(Event.INIT, growLoader);
    function growLoader(evt:Event):void {
         l.width = 150;
         l.height = 150;
    var k:Loader=new Loader();
    addChild(k);
    k.load(new URLRequest("MyBanner.swf"));
    k.x = 200;
    k.y = 100;
    k.contentLoaderInfo.addEventListener(Event.INIT, growLoader);
    function growLoader(evt:Event):void {
         k.width = 500;
         k.height = 150;
    Thanks and regards.

    Hi there,
    the error is caused by accidently overriding yout handler function   growLoader()  .
    You will have to define two handlers to solve the problem:
    var l:Loader=new Loader();
    addChild(l);
    l.load(new URLRequest("MyLogo.swf"));
    l.x  = 10;
    l.y = 100;
    l.contentLoaderInfo.addEventListener(Event.INIT,  growLogoLoader);
    function growLogoLoader(evt:Event):void {
         l.width = 150;
         l.height = 150;
    var k:Loader=new Loader();
    addChild(k);
    k.load(new URLRequest("MyBanner.swf"));
    k.x  = 200;
    k.y = 100;
    k.contentLoaderInfo.addEventListener(Event.INIT, growBannerLoader);
    function growBannerLoader(evt:Event):void {
         k.width = 500;
         k.height = 150;
    it is not tested, but this should do the trick.

  • Capacity availability in capacity header screen of work center

    hi all
    In capacity header under Standard avalaible capacity we have start time ,Finish time and Break time and Number of individual capacity . I have definesShift sequence and grouping and assign it in this view.
    but My questionis  Standard available capacity maintaines per day or per shift.?
    what about individual capacity (i.e Number fo machines avalable per shif .   I defined the avalable capacity i.e operating time 7 hours. per shift then in CMO3 t-code Available capacity should be 21 hours per day but it is showing only 7 hours .Why it is
    for examlpe
    Start time 06.00
    Finish time 14.00
    Break time 01.00
    no .of in capacity 01
    so in CMO3 t-code Available capacity should be 21 hours per day
    Regards
    dev

    Hi
    If you are running three shifts ,please maintain the data as given belwo
    start :00:00:00
    End:23:59:59
    Break :03:00:00 ( 1 Hour per shift so 3 hrs for 3 shifts)
    No.of individual capacity :1
    System will understand that it is round the clock operation with total three hour brak and you will get 21 hour per capacity
    Hope this helps
    regards
    Prakash

Maybe you are looking for

  • Tuning a procedure and using dbms_job.submit proc that call's functions

    Hi I have Procedure that have 3 curosrs which are nested one below with in each other and it looks as below it's structure will look some thing look like this declare empno_fetch number; CURSOR deu_process IS SELECT empno FROM emp WHERE flg_process =

  • No Firewire

    Hello all, I have read these forums with a passion for the past couple of weeks seeking a way to fix my problem by myself. Basically what happened was, I was moving something and I accidently unplugged my computer. I plugged it back in, started it up

  • IOS 5.0.1 will not download

    I keep trying to download and update my iphone 4 through iTunes to incorporate the iOS 5.0.1.  Every time I do try to do this an error comes up stating that I need to check the network because the network failed.  I tried to find a link for the iOS 5

  • Writing on an iPad

    Is there an accessory that makes writing on the iPad more like pen and paper and less like LARGE crayon?

  • Excel can't open Personal.xls

    I have Office 2013 on Windows 8.1 but when I open Excel it says it can't open personal.xls.  If I press Alt-F11 the VBA screen opens but there is no sign of personal.xls. The file exists and is in the folder C:\Users\Lorne\AppData\Roaming\Microsoft\E