Docmuent number requried in inspection lot QA01,QA02,QA03

Hi All,
I have added new tab(inspection lot) in reference object for CV01N transaction. After adding we are able
to create the docment and what ever lots we are entering in CV01N we are able to see in CV02N & CV03N.
But here requriement is the same document  number has to appear in QA01,QA02 & QA03 for the corresponding lots.
Please tell me how to solve this..
Thanks in advance.

Hello satya,
can you please give me steps.. how did you solved this issue.
i am also stuck in same issue
Regards
Tejas

Similar Messages

  • What is the BAPI for Inspection lot change - QA02??

    Hi Guys,
    Can anyone tell me plese, What is the BAPI for Inspection lot change - QA02?
    Thanks

    Hello,
    This BAPI suppose to be able to do that for you:
    BAPI_INSPLOT_SETUSAGEDECISION
    Best regards,
    Marcin

  • Connection between batch and inspection lot number

    Hi all,
    our GR in SAP triggers the creation of a batch number and an inspection lot number.
    If I only know the batch number, where in SAP can I find the related inspection lot number?
    Thanks
    Anne

    we have a Material Master that represents a semi-finished material that requires inspection at Goods Receipt from Production. In order to see the settings maintained for this material, click on the “Insp. setup” button:
    More details
    http://searchsap.techtarget.com/searchSAP/downloads/UsingDigitalSignaturesEMconvtSearchSAP.pdf
    Kevin

  • Inspection Lot number on Process Order

    Hi Experts,
    There's an Inspection Lot field in process order in Assignment Tab, but it doesnt reflect the number of the Inspection Lot of the Material.  What am i missing?
    Thanks,
    Kumar

    hi kumar
    that inspection lot no is assigned to process order when you have maintained inspection type 03 ie inprocess check in material master . when you release process order you can see inspection lot is generated and that inpsection lot no you can on that field.
    Regards
    Pravin

  • Today's inspection lot not appearing in qa32 & so processing through qa02?

    Hi all,
    Now when i created the GR, eventhough the inspection lot is created, it is not appearing in qa32, please suggest me why?
    later on i processed the ud through qa02 only
    regards,
    Sanjana

    Now when i created the GR, eventhough the inspection lot is created, it is not appearing in qa32, please suggest me why?
    later on i processed the ud through qa02 only
    Dear as per my understanding give the exact material code,if batch managed give the batch also,give the lot created date etc and again check in QA32 as you saying you can able to access inspection lot through QA02 then it must be visible in QA32 also.
    Select the all inspection lots radio button in QA32 if still you couldn't able to find the lot in QA32 as UD might have already done.
    Cheers
    KK

  • Create Inspection Lot for Serial Number

    Hello,
    Is it possible to create an Inspection Lot and associate it to a Serial Number right away.
    I've done a process were I've change the Material and Serial Number of my equipment, so now the old inspection lot is not usefull no more and I would need to have a new inspection lot so that the movement to place the stock on unrestricted is cone for the new inspection lot.
    Or is that any other way to do this???
    Thanks in advance.
    BMO

    Atul,
    The inspection lot is created when the mobile is delivered from client and dismantled, and my stock gets increased for the returned material - that stock remains in Quality.
    Later when the Usage Decision for the Inspection Lot is given (depending on the selection) my stock passes from quality to unrestricted, and this is the normal process without issues.
    Possible exception:
    If in the midle of the process I've to change the serial number for this mobile or to change the Material + serial number, the first Inspection Lot created is not helpfull to me because I can´t change there the Material or serial number. So the Usage Decision would be given for the old serial number, isn't it?
    Today I found a Ztransaction that is used to create Inspection Lot. In the first step the material, goes in the warehouse in Quality and in the second step, when the Usage Decision is given, the stock passes from Quality to Unrestricted.
    For the substitution Material / Serial number everything is correct, but for the first one it's not, should this obsolete stock goes to scrap?
    Thanks,
    BMO.

  • Manual Inspection Lot creation using Serial Numbers

    Hi,
    My requirement is to create inspection Lot for Serialized material manually.There is no trigger like Goods Receipt or Issue. I want to assign Serial number for the inspection lot to record the results. When I check the transaction QA01, I can only create it at Material level. Is there any standard way I can achieve this requirement?
    I assigned the Serialized Profile and checked the check box " Serial Number Management Possible" in QM view of material master. Thanks.

    Hi Tim,
    There is a better way of capturing the Serial Numbers for each result recording by using the Inspection Point in the Inspection Plan.
    You may create New Inspection Point in the configuration for the Serial Numbers assignment.
    I hope that this will meet your requirement.
    Regards,
    Bala

  • Manual Inspection Lot Sales Order Reference

    Dear All,
    I have GRN a material and make a Manual Inspection Lot. Then i did the results recording and usage decision.
    1. Can we make a Sales Order reference to a Manually created Inspection Lot?
    2. Can we make a Purchase Order reference to a Manually created Inspection Lot?
    Regards,
    DTD

    We cannot create an inspection lot (QA01) with reference to either Purchase Order or Sales Order.
    Instead we can enter Vendor or Customer Number in the Inspection Lot and capture the Sales ORder Number or Purchase Order Number in Short Text Field.
    Best Regards,
    K. Raghavendra Nayak

  • Scenarios for "manual creation of inspection lot"

    Hi QM gurus!!
       I would just like to ask the main function of QA01 or "<b>Manual creation of inspection lot</b>"
    What are the cases/scenarios where this tcode is used? I would really appreciate if you could help me.. Thank you.
    Regards,
    Heinrick Palad

    HI,
    The table below provides a brief overview of the functions you can use to process inspection lots. Appropriate cross references are included for the more extensive tasks or for those for which additional information is available.
    Prerequisites
    The inspection lot processing functions can be linked to various authorizations that are checked by the system whenever you try to process an inspection lot. The following types authorizations are relevant to inspection lot processing:
    Material authorizations
    The material authorization for QM is stored in the material master. For more information, see  Creating and Changing QM-Specific Data for a Material.
    Inspection type authorizations
    This authorization controls which inspection type the user can access in order to create an inspection lot. The inspection type authorization is plant-specific.
    No authorization checks are executed in QM when an inspection lot is created automatically.
    Features
    Function
    Pushbutton / Menu path
    What you should know
    Accessing the initial screen for the inspection lot processing functions
    Logistics ® Quality management ® Quality inspection ® Inspection lot processing ® Inspection lot
    Creating an inspection lot manually
    See Creating an Inspection Lot Manually
    Changing an inspection lot
    Choose Change
    Enter the number of the inspection lot you want to change and then choose Enter.
    Displaying an inspection lot
    Choose Display
    Enter the number of the inspection lot you want to display and then choose Enter.
    Creating a new batch in an inspection lot
    See Batch Creation in Inspection Lots
    Cancelling an inspection lot
    Call up an inspection lot in the change mode and choose Inspection lot ® Functions ® Cancel lot.
    See Cancellation of an Inspection Lot
    Blocking/unblocking an inspection lot
    Call up an inspection lot in the change mode and choose Inspection lot ® Functions ® Block lot.
    To unblock an inspection lot, choose Inspection lot ® Functions ® Unblock lot.
    When you block an inspection lot, you cannot process the lot further. You must unblock the lot if you want to perform any additional operations.
    Transferring stock in an inspection lot
    See Stock Transfers
    Making corrections to inspection lot quantities
    See Corrections to Inspection Lot Quantities
    Creating a QM order
    Call up an inspection lot in the create or change mode and choose Goto ® Insp. lot acc. assgnmt.
    See QM Order Creation
    Resetting the sample calculation
    See Resetting the Sample Calculation
    Printing inspection instruction/sample-drawing instruction
    See Printout of Instructions
    Approving a task list
    Call up an inspection lot in the create or change mode and choose Inspection lot ® Functions ® Give approval
    If the task lists in your company must be approved before they can be used, you should make sure that only approved task lists are assigned to an inspection lot. If the system selects a task list that has not yet been approved, you can use this function to approve the task list (provided you have the necessary material authorization).
    this link help u.
    http://help.sap.com/saphelp_erp2004/helpdata/EN/be/00bbe7ca5311d2961800a0c930e04c/frameset.htm
    reward is usefull.
    tahnks.

  • QM - Inspection lot release without inspection characteristic

    Hi experts, have initially created an inspection plan without inspection characteristics and a few lots have been Goods Receipt and inspection lot created. However due to no sample size is being defined at the inspection characteristics level, system is currently expecting:
    Insp lot quantity: 5
    Actual quantity: 5
    Sample size: 0
    Now that the inspection characteristics had been added into the inspection plan. Is there anyway to update the inspection lot to reflect the latest change and allow processing? Or do you have any better recommendation besides reversing GR?

    Hello
    please do the following
    1) Go to QA02, input the lot number
    2) Menu > INspection lot > Reset Sample
    3) Enter & Save
    4) QA02
    5) Inspection specification > Assign task list by click on Task/ specification
    6) Go to Sample, do the SAmple calculation
    7) Save
    Regards
    Gajesh

  • Unable to clear Inspection Lot

    Dear Sirs,
    I have a material with Inspection Type - 0101
    The inspection lot of this material has the following status -CRTD,PREQ,CHCR,SPRQ,IRCH
    Unable to clear inspection lot
    in qa02 - insp specications tab -- while using Tasklist / Spec --> following message is coming
    No Inspection Plan could be found
    In samples tab -- sample size could not calculated
    Please help

    Dear
    -In this case you create one inspection plan through QP01 for material code.
    -Assigned the inspection plan through QA02 (At the time of assignment Key date should be current)
    -Calculate the sample size by clicking over Sample tab and then Save the document.
    -Status of inspection lot will get changed to REL.
    -Proceed for the further transactions like QE11 to QA11
    AYK

  • How to cancel inspection lot with REL status

    Hi Guru's,
                     I am not able to close old process orders becuase of active inspection lots in the system, Error message is  "inspection lot doesnot have necessary data" . I could see there are lot many old inspection lots which are in REL status, I am not able to cance these inspection lots in QA02(option is grayed out) How to cancel these  inspection lots which are in REL status?
    Regards,
    Uday

    Hi,
    check the below links....
    cancel QM inspection lot
    QM - Deletion of inspection lot from qa32
    and it would be better if you post this question in QM forum....
    Thanks
    Kumar

  • How to link a Delivery to an Inspection Lot a posteriori?

    Hello,
    we need to created Inspection Lots and make the analysis before the delivery. Thus we use Inspection Type Origin '89'.
    Afterwards, however, we would like to update the Inspection Lot and link it to the actual delivery. This would help in the reporting for example.
    Do you now how we could do that?
    Thank you in advance and regards,
    Didier

    Thanks but it does not fit our process.
    Here are more details:
    We create a sales order
    The sales order is sent to an external shipping system
    The truck driver check-in in the external shipping system
    A sample of the load is sent to the lab for analysis
    The analysis is carried out and gives its visa
    The truck driver can check-out in the shipping system and leaves
    The shipping is sent to SAP and a delivery is created
    The lab manager, at the end of the day would like to assign the delivery number to the inspection lot.
    This would help in administring/reviewing the inspection lot status, etc.
    Do some useful reporting with the actual quantities, truck id, etc.
    regards,
    Didier

  • User Exit for MIGO during inspection lot creation

    Hi Everyone,
    I want to change the vendor number in the  inspection lot while doing goods receipt for an outbound delivery in MIGO. Is there any user exit available to do this or can we do this in standard transaction?
    Please guide me how this has to be done.
    Regards,
    Sugopa

    i am working on 4.6c.
    This BADI is not present there.
    Any other solutions suggested.

  • Reverse GR after the Quality has passed the inspection lot

    I have a situation where the GR was done, Quality has approved the materail, now we are trying to reverse the GR...the system is giving error when trying to cancel the GR...
    "You cannot cancel GR, since inspection lot is already partly posted"
    How can I reverse this GR,
    PLease advice,
    Sam

    hi sameer
    To be able to reverse a stock posting for an inspection lot, the following conditions must be met:
    A usage decision has been made for the inspection lot.
    The goods in the inspection lot have been posted from inspection stock to blocked stock or unrestricted-use stock.
    If you posted the goods to a stock other than blocked stock or unrestricted-use stock (for example, to scrap), you must first post the stock back to blocked stock before you can reverse the original stock posting
    Reversing Stock Postings  
    Choose Logistics ® Materials Management ® Inventory Management ® Goods Movement ® Goods receipt ® For purchase order ® PO number known.
    The initial screen for creating a goods receipt for a purchase order appears.
    In the field for the movement type, enter 102 (goods receipt for a purchase order into warehouse - reversal).
    In the field for the purchase order, enter the purchase order number for the original goods receipt.
    You can copy the purchase order number from the inspection lot.
    Choose Enter to display the selection screen for the purchase order items.
    Select the purchase order item for which you want to create the goods receipt and set the Stock type indicator to the stock to which the goods were originally posted with the usage decision (for example, F for unrestricted-use stock or S for blocked stock).
    Save the goods receipt and exit the Materials Management component.
    Choose Logistics ® Quality management ® Quality inspection ® Inspection lot ® Usage decision ® Change with history.
    The initial screen for changing a usage decision appears.
    Enter the number of the inspection lot for which you previously made the usage decision and choose Usage decision (UD).
    To cancel the inspection lot, choose Usage decision ® Functions ® Cancel lot in the usage decision screen
    regards
    thyagarajan

Maybe you are looking for

  • Cannot load a library unit database_object ( referenced by package name )

    Dear Friends, I am using Plls in Reports 6i. In One of the Pll I am Using Backend Table in package body. I have two 8i instances. when I comiple and save and close this plls with one instance( say instance "A" ), its fine. it is done sucessfully. Now

  • Should I be getting low on memory?

    I have recently built my own desktop. Specs: nVidia GTX 760 i7-4770k 16gb Ram I use after effects and photoshop in a pretty undemanding way (the most demanding thing I do is rotoscoping). However, when using premier pro (and after effects) I keep get

  • RAID status in Conky

    I wrote a tiny script to monitor the status of RAID arrays. It is written in awk and is meant to be used with conky. I have this in my conky config file: RAID: ${execi 60 gawk -f path-to-the-script /proc/mdstat} #!/bin/gawk -f # This script checks th

  • HT1349 How to enter dash "-" on apple tv?

    How to enter dash "-" on apple tv? My wifi pw has dash but seems like there is no such option on apple tv keyboard. Help!

  • Using OS hard drive for captured footage??

    Years back the rule was never to use your main hard drive, with both operating system and FCP, to store and access captured footage. Yesterday an instructor at a school that uses FCP was telling me they no longer follow that rule and use their IMAC's