Hi,
I crearted a Document Type.
I'm able to create a document with the type. Though the Document Status is released, the release Interval (which is next to the Document Status) is showing as 'Not Released'.
How do I change this to released (or), can it be hidden.
Please suggest a solution.
Regards,
Ajai

Though the Document Status is released, the release Interval (which is next to the Document Status) is showing as 'Not Released'.
This behaviour can be corrected by setting/checking the 'Release Flag' attribute for the released status defined for this Document Type.The path is SPRO > IMG > CA comp. > DMS > Control Data > Define Document Types > Select the Doc Type in question and go to Define Document Status.
Hope this helps.
Regards,
Pradeepkumar Haragoldavar

Similar Messages

  • Document Status Not Released

    Hello DMS Gurus,
    I'm trying to figure out how to control DIR so that if the document type does not have a status network defined, the Not Released red light does not show up on the DIR.  I thought maybe if I created a status for my document type but did not link it to change management, the Not Released info would not show, but you will see in my example screen shot below, it still shows.  Does anyone know how to prevent the Not Released from showing on the DIR if a status network is not defined for the DIR?
    Best regards,
    Julie Norman

    Hi Julie,
    If you are not using document status, then you select "Suppress field" for Document Status under Field Selection in DC10.
    Or
    You can also check the RELEASE FLAG under Define Document Status >> Attributes. So once you save the DIR, it will show the green light with document creation date.
    Hope this will help you.
    /Tilak Raj
    Message was edited by: Tilak Raj

  • Will it be possible to create new version of document only after releasing

    Dear Expert,
                      is it possible to create a new version of the document only after release of the document...i don't want document version should be created other then release status.
    Bhuwan

    Hello,
    Since you are a technical consultant also, probably you are in a better position to deside how to achieve this.
    You will have to develop a user exit which will check status/ Release Indicator of  Document when new version option is clicked through CV01N/ 2N/ 3N/ 4N transaction and take necessary action. 
    Regards,
    Milind Dumbre

  • Purcahse document cannot be released after PO reject using ME29N

    Hi gurus/experts,
    is it SAP standard behaviour that once PO was rejected using ME9N, the PO document cannot be release anymore ?
    if that is tha case, how can an approval reject the approval so that the release status can go back to previous release code ?
    TQ

    Hi,
    It is possible to go back into ME29N and cancel the rejection, then the purchase order is available for approval again.  The reject icon will change to a reverse rejection button after the rejection is done..
    Normal process is after rejection the buyer will cancel the rejection, make any necessary changes and save.  This will return the purchase order for approval.  The buyers changes may reset the entire approval process if they exceed the conditions configured for resetting the approvals.
    James

  • Create Service Agreement - In Status field, "Release" is not appearing.

    Hi folks,
    I am creating a simple Service Agreement in CRM Web UI. Entered all data required like Customer, product, org details, price discount etc.. and tried to "release" before saving.
    In the Status field "Release" option is not there to select. I see only "In Process" and "Completed".
    Can anybody tell me how to make 'Release' available, so that I can release the document and save it.
    The price is not determined for the product. Could that be the reason?
    The document is error free as I don't see errors in App log.
    Please give me and idea to resolve. Will be generous in giving points.
    Regards,
    John

    Hi Shashidar,
    Thank you for your response. Here is the following steps I did:
    1. Status profile is CRMORDER
    2. In this status profile, I see the following:   Open with status No.10
                                                                        In Process - 20
                                                                        Completed - 30
                                                                        Rejected - 40
    3. I added a new entry for Released with status number: 50
    4. I have taken care of the Lowest and Highest Limits.
    5. I also checked the 'Object Type' as 'Agreement'
    Now, I am not clear which Business Trans I should assign. In the drop down list, I see many Bus.Trans for 'Release'
    such as APRL - Release / CALL - Release / CREL - Release and so on.
    My question is, which one of these should I select. I tried couple of them, it did not work. (Release still not appearing on CRM7.0 Web UI)
    Currently, I am trying to release a Service Agreement on the Web UI. I played around with lowest and highest limits a couple of times and it changes accordingly in Web UI. But some reason 'Release' is not visible which carries the status No.50.
    I wonder what is going wrong. Any help would be well appreciated with generous points.
    Thank you in advance,
    Fred

  • How to restrict update to a document in state release to the contribution g

    How to restrict update to a document in state release to the contribution group.
    Hi I’m working with UCM 10g and I want to know if it is possible to restrict the update over a document that is on state release for the group of users that made the check in of the document ?
    thanks

    Yes, it is, but IMHO in a rather complicated way:
    - you could change the security settings (security group, or more likely, accounts) during the life cycle, or
    - you could implement collaboration management, and change security settings via ACLs
    Alternatively, depending on what you mean by "updating" documents you could also:
    - check-out the document by a system account (if you want to prevent your users to check-in a new version)
    - modify the GUI so that Update (metadata) action is not available to users (in theory, they could still access it via a direct service call) by a custom component
    - introduce a Java event filter (enhancing the UPDATE service) where you will implement whatever logic you want
    I would probably opt for the last options as it seems to me to be the cleanest solution (but yes, it requires some coding).

  • Approval Status of all the documents which were in 'Approved' state, now showing as 'on going' status after migration to SP 2010.

    Hi There,
    I have recently migrated my SharePoint 2007 portal to SP2010, However, to my surprise  i have noticed all the documents in different document libraries are having 'Approval status' as 'On going' status which suppose to be 'Approved' status.
    I mean, before migration all the documents status was 'Approved' and after migration it is showing as 'on going'.
    This is absolutely incorrect, can someone help in this.
    How can i retain all the documents status as 'Approved'
    Regards
    Vikram P
    vikram padigala

    Hi There,
    I have recently migrated my SharePoint 2007 portal to SP2010, However, to my surprise  i have noticed all the documents in different document libraries are having 'Approval status' as 'On going' status which suppose to be 'Approved' status.
    I mean, before migration all the documents status was 'Approved' and after migration it is showing as 'on going'.
    This is absolutely incorrect, can someone help in this.
    How can i retain all the documents status as 'Approved'
    Regards
    Vikram P
    vikram padigala

  • CRM(TPM): Promotion status to released -- update to which R/3 table?

    Hello experts,
    we have a CRM (with TPM) 5.2 and a connected R/3 (4.6c).
    The saved promotion (CRM) triggers an entering of a rebate agreement on R/3 side.
    If I set the promotion status to "released", where can I see this on R/3 side?? Entry in which DB-table?? After a release I have to trigger a process with the "released" rebate agreements.
    Thanks a lot for info!!
    Michael

    Hi Carminem,
    thanks for your answer!
    Unfortunaltely the table CMPB_MAP will be filled immediatley after creating a new rebate agreement from CRM side - with status "created".
    That means, there is no change any more, when the promotion status is changed to "released"!
    Maybe there exists an other DB-table for that purpose??
    Best regards, Michael

  • Changeability of Purchasing Document During/After Release

    Dear All
    I want that whenever there is any kind of change in PR/PO after start of release process the PR/PO should get de-released.I mean if PR/PO quantity is increased or decreased by 1 ea or price is increased or decreased by even 1 Re or any kind of change(e.g payment terms) then also the PR/PO should get dereleased if it has been approved for some level.
    How can I achieve this?? What should be the changeability status for release indicator or is there any other way out?

    Hi Satish,
    Either u maintain 4 or 6 in release indicator, system is not revoking ur relaese strategy its own after change in price or Qty
    The only solution is that in version tab if u check the complete check box, then it will revoke and u have to release it again.
    but problem is that user usually forget to check that complete check box and save and relaese strategy not revoke.
    Solution is as i think and applied that u must have make some fields mandatory in version so that user has to go in version tab to filled that mandatory field with that and ask the user to check the complete check box.
    2nd solution is set message MEDCM 014 as Error in Configuration. This will prevent GR for the changed quantity (even if it is not released).
    this may help u !
    Regards,
    Pardeep Malik

  • How processing status "In Release " is set in purchase requisitions

    Hi Experts,
    How processing status, iun release is set in item details (Status tab page) of purchase requisition, also is it possible that release status is "release completed" even requisition is not subject to release strategy.
    how release active is set.
    Thank you
    Anand

    Hi
    The Stauses in the PR will be active opnly if you have the release strategy setup for the PR.
    "In release" is set when the PR is created & is subjected to approval & in the approval process.
    Relased is set when the PR is approved fianlly.
    Thanks & Regards
    Kishore

  • API for Work Order status from Released to Unreleased or any user defined s

    Dear All
    Is there any API for to change work order status from Released to Unreleased or any user defined status.
    Take care
    Aamir

    Hi Ben,
    As query is resolved, you should close the Thread after rewarding to the Concerned
    Thanks,
    Manish

  • Function to change CATS status to released for approval

    I have a requirement where I need to change in batch cats records from status 10 to status 20 'released for approval'
    I can't find how to change the status in  BAPI_CATIMESHEETMGR_CHANGE
    and another function CATS_APPROVAL only works for approving or rejection of records.
    is there another bapi or function which I can use to change the record status of cats ?
    or the other way around is also acceptable that I can set the status back from '20' released for approval to '10' locked.
    kind regards
    arthur de smidt

    when debugging cat2 I found a form which handles the release for approval. but I'm nog sure if there is more to it. for so far I can see it updates the status directly and that's it. when I go further on I come in the screenpainter prog. any clues if it's normal to use this code for my own abap ??
    further on I don't understand the function of ASSIGN_FIELDS_IN_ICATSD ?
    can somebody explain this one ??
    include : LCATSF33
          FORM FREE_ONE_CELL                                            *
          free one cell on dynp                                         *
    FORM FREE_ONE_CELL USING U_NUMBER
                             U_WORKDATE LIKE CATSDB-WORKDATE.
    assign the correct fields
      PERFORM ASSIGN_FIELDS_IN_ICATSD USING U_NUMBER.
      IF <STATUS> = STATUS-LOCK OR <STATUS> = STATUS-REJE.
    count records
        TOTAL_RECORDS = TOTAL_RECORDS + 1.
    date in the future ?
        IF TCATS-FUTURE IS INITIAL.
          IF U_WORKDATE > SY-DATLO.
            FUTURE_RECORDS = FUTURE_RECORDS + 1.
            MESSAGE S024 WITH FUTURE_RECORDS TOTAL_RECORDS.
            EXIT.
          ENDIF.
        ENDIF.
        READ TABLE ICATSDB WITH KEY MANDT = SY-MANDT
                                    WORKDATE = U_WORKDATE
                                    COUNTER = <COUNTER>
                                    BINARY SEARCH.
        IF SY-SUBRC = 0.
          ICATSDB-STATUS = STATUS-FREE.
          IF ICATSDB-ACTION IS INITIAL.
            ICATSDB-ACTION = ACTION-UPDATE.
          ENDIF.
          MODIFY ICATSDB INDEX SY-TABIX.
          <STATUS> = STATUS-FREE.
    set global marker that data have been unlocked
          FREE_DATA = YX.
        ELSE.
          MESSAGE X030.
        ENDIF.
      ENDIF.
    ENDFORM.
    kind regards
    arthur

  • Request having function group released but function module attribute shows not released

    Hi experts,
                   I am a beginner.
                  There is a transport request in which my function group and other objects were present . This transport request and its task were released . But if i check the attributes section of the function module that is present in that function group , it shows not released .
    Is there some problem ? did the function module not get released with its group? It wasn't showing anywhere in the request even though i had added it during creation.
    Here is the image :
    Thanks,
    Unnati

    Hi,
    Those two meanings of 'released' are unrelated. Don't worry about it.
    Also, a function module sometimes does not explicitly appear in a transport request, if the function group is already in there.
    cheers
    Paul

  • Maintaining the systems status as release at the time of upload

    Dear all,
    While uploading the master data for Business Entity and Buildings I want to make the system status as release. How do we achieve this?
    Also at the time uploading the contracts   I want to make the system status of the contract as active. How can we do this at the time of upload.
    Expertu2019s  pointers are highly appreciated.
    Regards.
    Vara Prasad

    Hi Vara,
    I guess you are using the API_RE_* function modules for uploading the data. You can use these
    APIs also to set the system status. You have to set the parameter ID_TRANS and provide the activity that sets the status (example: for system status "released" the activity BFRE, for activation of contracts the activity is MCAK).
    I hope this information is helpful for you.
    Regards, Franz

  • Assignment of task list after the inspection lot status is released

    Hi,
    I have applied a user status with  which i am able to release the inspection lot.After that i am going to assign a task list. But it is not getting assigned.
    please help me.
    Regards
    Vivek Deshpande

    Hi,
    Key date is same. I have checked for it.
    What i am saying is , i have manually updated inspection lot status to release state by applying user status. And after that i am trying to assign inspection task list to the inspection lot.But i am unable to do so.
    Can i do this ? Please help
    Vivek Deshpande

Maybe you are looking for

  • Cisco Unified Real-Time Monitoring Tool Administration Guide

    Hello Pros, I am in process of upgrading CUCM from 8.6 to 9.1.2 and receiving "not enough disk space on the partition" error. The show status from CLI shows 13499216K free space but I don't understand why we are getting the error message. I tried FTP

  • When Brother plays Xbox I lose internet

    Okay, when my brother plays Xbox with the wireless chip, my macbook says i still have connection with the router, but not with the internet. I use comcast netgear with 4 channels. I heard I could change the frequences of the two... Please help

  • Error Installation SAP ITIM

    Gives the following error when installing the SAP ITIM is: If the Reporting Services is installed on the server: Windows Server 2008 r2 with SQL Server 2008 Sp2 Plase help, thanks Luis Angel

  • Error in URL (host name coming twice)

    Hi All,   I am facing a error while running any query in browser (Web Analyzer), in the URL that the system is generating the host name (sapdevqas) is coming twice due to which the page is not getting displayed, for now I have to delete it manually t

  • Firefox keeps opening links as well as new tab

    While browsing, if I long-click a hyperlink and select "Open in a new tab" from the ensuing menu, even though it opens the tab it also follows the hyperlink in the original tab. How do I prevent it from opening the link in my current tab?