Doubt in Scheduling of performance based preventive maintenance

Dear Experts ,
                                        This is with respect to scheduling of performance based preventive maintenance.
I will put my doubt in example so that it will be easy for you to understand.
I want to perform a preventive maintenance for every 100 litres of fuel consumption.
annual estimate is 7200 litres , that means 5 litres a day.
so as per plan , for every day 5 days , maintenance needs to be performed.
same will be appear after scheduling in ip10 also.
While updating in the measuring document , I know that , if 100 litres is updated before due date , then order will be generated in the current date itself.
I just want to know how system responds , if 100 litres consumption takes more than 5 days , will the system generates order as per schedule date or will it wait to complete for 100 litres consumption ??
Regards
Keerthan Kumar

Greetings Keerthan,
That depends on:
1) The frequency that you input Measurement Documents in
2) Your Call Horizon on the Maintenance Plans
3) Your Scheduling Period in your IP30 Deadline Monitoring variant
Generally, SAP will adjust the schedule based on the Measurement Documents entered for the counter (1) to account for readings (usage) which are higher or lower than estimated.However, it will NOT reschedule any Orders already called. So to make sure the dates are usually adjusted to your usage, you want frequently input MDs, a high Call Horizon and a short Scheduling Period.
SAP will determine a scheduled due date for the Order based on the Annual Estimate and the readings. So, if the due date is in 5 days and you are on a call horizon of 100% and a Scheduling period of 3 days, for example:
a) if you do not input Measurement Documents from Day 0 onwards, the Order will be generated due for Day 5 when you run the IP30 on Day 2
b) if you input a Measuring Document on Day 1 indicating that less than estimated or no fuel was used, the due date and call date may be pushed into the future and the Order will be generated after Day 2.
c) if you input the MD after Day 2, this Order will already have been called and will not be rescheduled, but subsequent calls might.

Similar Messages

  • Cycle sets in Performance Based Preventive Maintenance

    Hi,
    Can any one explain what is cycle sets in Performance Based Preventive Maintenance means?
    Thanks in advance.

    hi
    Cycle sets are used for multiple counter plan where the unit of measurement is different .For example you have to plan your equipment based on KM it had serviced and also based on Months ,then you have to create cycle set for these 2 measurement like KM and Mon ,then while creating the multiple counter plan you can specify the cycle set and make the scheduling
    Also refer help.sap.com
    regards
    thyagarajan

  • Performance Based Preventive maintenance

    Hi Guru,
    I have equipment motor. But I need to do the preventive maintenance based on motor running hour (ie: every 1000hr).
    How to map the scenario in SAP
    Thanks in Advance.
    Regards,
    S.Babusingh

    Hi
    You need to create the measuring point for the equiment motor.(IK01)
    and in the maintenance plan (IP01)you chose counter based mainteannce plan and set the couter reading 1000 hrs.
    also you can define the other paramenters in the plan.,
    once the measuring documents reading(IK11) updated by you is reached equal to or greter than the set value orders gets triggerd.
    this is standard SAP process
    regards
    Krishna

  • Automation of scheduling for performance-based planning

    Colleagues,
    I've got a question regarding automation option for skipping calls upon measurement document reading update.
    So, scenario as follows
    MP with strategy (activity) is scheduled with 1K, 5K, 10K hours with surpressing hierarchies 1,2,3 accordingly. Initial counter reading is 0, estimated ann perf- 20K. So, we schedule IP10 which gives us all scheduled-on-hold's for 365 days of scheduling period.
    Once I enter 5600 reading measurement doc, the batch would generate four 1K calls and one 5K one..They want the system automatically skip those calls in background and get only one 5K order, avoiding redundant four 1K' ones..
    I don't see much of room for maneuver for automatic scheduling in PM..
    Any suggestions??
    Thanks in advance!

    Hi,
    (that's me who initiated the thread-service marketplace was messing with my last name)
    They've got elaborated on the scenario and aforementioned user exit perfectly serves the purpose of restarting cyclees with offset when late reading is entered, skipping the redundant calls.. However, in that particular scenario described below that wouldn't help..
    so, the requirement is as follows:
    1.minor/mayor PM every 750h and 1500h accordingly
    2. three different overhauls (at 15000, 30000, 60000H accordingly)
    3. 500h inspection after each overhaul
    After 60500H the cycle should start all over
    the sutuation is worsen by the fact that I should create 5 different plans, since every maintenance pack has different call horizons..
    So, we have
    1.  plan #1 for 500H inspections with call horizon 100%, strategy offset '500'
    2. single plan#2  for minor/mayor PM with call horizon 67%, strategy offset '1250' for minor PM and '2000' for major PM
    3. plan#315K overhaul1 with call horizon 93%,
    4. plan#4 30K overhaul1 with call horizon 90%
    5. plan#5 60K overhaul1 with call horizon 95%
    I have two strategies: one for inspections and minor/mayor PM, another-for overhauls, both strategies using supressing hierarchies..
    I was using offset and 'restart'  and 'start-in-cycle'  those plans..
    after first 15K overhaul package completed:
    plans #1 and 2 are restarted with latest counter reading using function u2018Restartu2019;
    Plans #3,4,5, are restarted with latest counter reading using function u2018Start in cycleu2019, selecting the relevant timeframe (i.e. offset shall be set before next due call on relevant cell in package sequence ruler)
    Just wanted to double check with you whether you guys got any suggestions or recommendations..
    Appreciate it!!

  • Customer Exit IMRC0001 for condition based preventive maintenance

    Dear Experts,
    I am using customer Exit IMRC0001 for creating maintenance order if my measuring point reading exeeds the thresold value or it is  out of the upper and lower limit range , which i have set for that particular Measuring point.
    This scenario is working fine if i am creating measuring point with unit *C (Degree centigrade-Temp).
    But it is not working fine for measuring point having unit other then *C
    Like : Kg/Cmsq, Bar, Run Hr, Vaccum, voltage, current, consumption etc
    The Reason for this i have found out.The logic return in the program only considers the *C unit
    Say if i set 50c as my target value in Measuring point*
    In Table IMPTT the value is getting stored as 50 + 273.15 = 323.15
    But if i enter 5 Ohm as my target value in Measring point
    In Table IMPTT the value is getting stored as 5 only.
    Target Value field name is DESIR
    So i want to know why for some units the same value is getting stored and why for some units value with some formula getting stored.
    Regards,
    Amar Jadhav

    does your characteristic allow decimals??
    also why not use deg K instead of deg C
    ignore above
    see note 525948
    Symptom
    When you change the target value of a measuring point, it seems as if the system updates incorrect values for the 'Target value' field in the change documents.
    Other terms
    IK02, IK03, IMPT
    Solution
    The internal display of field 'Measuring Point Target Value' has the SI unit belonging to the unit of measurement.
    Example:
    For temperatures, the target value can be displayed in the user interface (RIMR0-DESIC) in the units of measurement Celsius, Fahrenheit or Kelvin. However, the database display in field IMPTT-DESIR always refers to the respective SI unit Kelvin.
    As the change documents always refer to the database display, they also refer to the SI unit.
    Edited by: Virendra Pal on Oct 1, 2008 2:34 PM

  • Condition based Preventive Maintenance - IMRC0001

    Hi Friends ,
    Can we create notifications of a particular type against a particular equipement automatically , only with the help of user exit IMRC0001 or some other are also required .
    Actually our main requirement is that user will post measurement documents regularly . If the reading falls
    below a decided point then a notification should be created . Like for a rubber pad if width falls below 7 inches then
    notification should be created .
    and I think to satisfy above requirement there are no standard settings in SPRO other than using the user exit .
    thnx.

    Notification creation in exit IMRC0001
    It might be helpful.
    regards,
    Tehsin

  • Deadline monitoring in preventive maintenance plan scheduling

    Dear Experts,
    we are having only single cycle time based & performance based preventive maintenance plans. The individual plans are weekly, monthly or based on specific counter readings. Now i want to schedule it automatically through IP30. since there are plans with different units like days or hours how can i schedule it through IP30? is it possible to run separate IP30 for counter based single cycle plans? Is it ok if I run the program on every midnight? I am confused on the scheduling through IP30. please give me the clarity...Please do the needful.
    Thanks & best regards,
    Praveen

    Praveen,
    Yes you can run IP30 with single cycle plans.
    As IP30 can run for many hours (dependent upon number of plans) it is best to schedule the IP30 job at a time when there are fewest users on-line e.g. midnight on Saturday or Sunday. The timing is very much dependent upon your organisation.
    [Here|http://www.sapfans.com/forums/viewtopic.php?f=7&t=316910] is some good background info.
    It should be someones responsibility in your organisation to review the scheduling log after every IP30 run
    PeteA

  • Performance based maintenance plan

    I am trying to schedule my performance based plan under two conditions:-
    In the first factor,I have kept my initial counter reading as 0 as on today,my cycle as 2000 hrs,estimated as 2500 hrs.
    An my plan date is calculated as  24.10.12.
    In the second factor,I have kept my counter reading as 0 as on today,my cycle as 2000 hrs,estimated as 2500 hrs.
    An my plan date is calculated as  24.10.12.
    Why the planned date is coming as 24.10.12 in both the cases.It should be different.

    Hi,
         I believe you have created counter today and starting value may be 0 or directly 500KM .. in this case last counter reading for both the values will be same date ..so better post 550KM tommorow and then try this way and check :
    First condition :- Start counter reading with 0KM
    Secondition :- Start counter reading with 550KM ..
    Doing the above should give you different dates ..
    In your case  you have posted both OKM & 500KM on same day you will not find any difference in calculation of dates ..
    Note :- System takes the last counter reading date as the start date for calculation ..in case of Counter based plans ..
    regards
    giri

  • Hardware Preventive Maintenance Schedule

    I'm trying to find a recommended schedule for Sun Server maintanence. If anyone can point me in the right direction it would be greatly appreciated.

    Dear Makarand Gurjar
    The purpose of the report is, every month begining maintenance person will give the list of equipment scheduled for preventive maintenance to production department.  If that list has planned time for preventive maintenance, it will be very useful for them to release the equipment for preventive and plan the production accordingly.  In IW38 / IW39, we will get only the equipment for which preventive maintenance order is created.  Say for Eg. If an equipment is scheduled for every month preventive maintenance and the scheduled date is 25th of every month and call horizan is 90%, then the order will be released only on 22nd.  If we take the report on 1st of the month it will not come.
    In IP24 we can get all the equipment schedule for that month, but in the planned time is not there .
    Regards,
    Babu R

  • Preventive maintenance for equipments installed in plant area

    Dear experts,
    I want to implement Preventive maintenance for equipments installed in plant area.
    Requirement is that i should be able to create a maintenance plan & schedul it as per the due dates. Maintenance order should get created. This order can be linked to the service contract item for which service entry sheet is created & released.
    I want a control on service entry sheet creation if the order is not settled or the related inspection lot which is generated is not confirmed.
    Please give advice ,how to proceed.
    Regards
    Vivek Deshpande

    Hi Vivek,
    Not sure on clearly what u need .. but have a look at some of the plans and examples of their usage for better idea ..
    1. Types : Time Based or Performance Based
    2. Single Cycle Plan [Time Based] : Ex u2013 Maintenance of a Vehicle every 03 months
    3.Single Cycle Plan [Performance Based] :Ex- Maintenance of a Vehicle every                                1000KM .
    4.Strategy Cycle Plan [Time Based] : Ex- Maintenance of a Vehicle every 03                                            months, 06 months etc.
    5.Strategy Cycle Plan [Performance Based Plans] : Ex u2013Maintenance of Vehicle                                                                          every 1000km , 2000km etc.
    6.Multiple Cycle Plan with single cycle set [Time or Performance Based] : Ex u2013                                                    Maintenance of a vehicle every 3months or                                  500km
    7.Multiple Cycle Plan with Multiple Cycle Sets [Time of Performance Based] : Ex- Maintenance of a Vehicle every 3months or 500km and 6months or 1000km
    8. The above given are explained with callobject as Maintenance Order. For getting inspection Lot then you can use order type PM05 calibration order in your Maintenance Plan and MO gets created as per the plan cycle and inspection lot gets created once u release the MO ..
    9. If you want MP related to service items then create MP with service procurement as Maintenance plan category in IP41 .. for remaining you can put MO as Maintenance plan category  .. for details refer to SAP Help ..
    regards
    pushpa

  • Changing basic finish date in Preventive maintenance orders

    Hi Experts,
    My requirement is to block PP work centre when maintenance schedule the equipment for preventive maintenance. I am making system condition as zero in generated preventive maintenance order but basic finish date is not changing in the order automatically. Can anybody please explain how to bring this? Finally my requirement is system should change basic finish date and time as time given in operation of task list.
    Thanks in advance.
    best regards,
    Srinivas M

    Hi Praveen,
    I have done all setting and tested but there is no change.
    My client requirement is like this - whenever maintenance plans are scheduled, for the scheduled dates, production capacity should not be considered by production. We could do this for breakdown orders but not happening for PM orders unless we change the finish date.
    The issue is to get the finish date automatically when scheduling maint.plans with respect to values given in operations. Please suggest how to get the  basic finish dates automatically.
    best regards,
    -Srinivas

  • Preventive Maintenance Order is not releasing as per scheduled Planning in Counter Based Plan

    Hi Experts
    In The below schenario
    There is a  counter based maintenance plan. of strategy 100 km,200 km,...1800 km..
    Operaton1,  Operation2,... Operation3... defined in maintenance package for 100 km, 200 km,.... respectively.
    Now issue is that system is releasing order as per sequence of scheduled planing & not according to schedule of current counter reading of counter.
    case:  At 200km order 1 is released with operation1 only, logicaly system should release order with operation1, & operation2
              same like that at 300 km, system has released order with op1 & op2, logicaly system should release order with operation1, & operation3 as per strategy defined in maintenance plan.
    In the present condition, what we have to do to get the desired result like for next counter reading of 400 KM system should release order with op1, & op4.
    Best Regards
    Pravin Gautam

    1st order is getting generated by 100 KM. While doing Preventive Maintenance, vehicle will not have any movements so that counter reading at the completion should as same as 100 KM.
    I am not clear how & why you entered 200 KM for completion of PM order.
    Also, if you complete the 1st Preventive Maintenance at 200 KM, from there only system should calculate the next order. Its not Time based as this will come automatically with predefined frequency. Your plan is Performance based & system will act according to the completion of previous Preventive Maintenance.
    I don't find any reason to change behavior which is correct. I am not convinced with the development which is giving wrong details to the business.

  • Performance based maintenance

    I have made performance based maintenance plan , in this plan i have assin counter with annual estimate 100 nos and my Maintenance plan cycle lenth 10000 nos .  ( annual estimate i kept 100 nos because  i need  maintenance order counter baase only ) so system schedule the plan ,with call plan date 4 jan 2110 .now when  i update the maintenance document ,counter reach 100001 system generate the maintenance call with plan date 4 jan 2110 not on order generate date.
    but we required the plan  date on which maintenance order generate  so what can i do in the master data so i can get same date on which maintenance order generate.
    Pl help
    Raghav

    There are 3 things in Maintenance Plan.
    Maintenance Plan - Call Date
    Maintenance Plan - Plan Date
    Maintenance Plan - Call Horizon
    Call Date is date on which Maintenance Order gets created.
    Plan Date is basic start date of Maintenance Order (when maintenance should start)
    Call horizon specifies as a percentage when a maintenance order should be created
    In your case i would suggest you to maintain call horizon as 100% that means your order created date and maintenance date (basic start date of maintenance order) are same.
    Also plz refer the below link.
    http://help.sap.com/saphelp_crm60/helpdata/en/3c/abb377413911d1893d0000e8323c4f/content.htm

  • Regular Preventive Maintenance schedule for xsan volume ??

    hi
    Is there is any weekly , monthly regular Preventive Maintenance schedule which we should perform for xsan volume like defragment , some commands etc
    What are the steps for regular Maintenance for xsan ,servers which apple recommends ?
    thanks

    Hi,
    I do not do such maintainance. However every night a cvfsck -nv is run. This is a readonly file system check. If in the result of this a line exist which says:
    Filesystem would have been modified
    Then a real filesystem check is needed.
    A defrag is only performed on files, not on empty space. It takes very very long, and I do not expect much of it. So I do not do this.
    Hope this helps,
    Regards
    Donald

  • Triggering of Preventive Maintenance based on Measuring Point

    Hi,
    I have set measuring point & defined upper range limit and lower range limit. Now I want to trigger preventive maintenance, based on reading enter against measuring point specifically if measuring point reading is above or below defined upper range limit or lower range limit.
    Letu2019s say example, If 10 and 5 is upper range limit and lower range limit, now in this case creation of notification / main order if user has enter measuring point value more than 10 or less than 5.
    Regards,
    Dipen Shroff

    Hi,
        You can do it via Condition Based Maintenance ..
    IMRC0001- U can use this User exit
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/a7/fa4c988f6611d29e8a0000e8323350/frameset.htm
    regards
    pushpa

Maybe you are looking for

  • External USB Hard Drive not showing up on Time Capsule

    Hi all, I have a 500 Gb Time Capsule that used to be able to detect my external USB hard drives. I had to store my things for a while and have just started using the Time Capsule again. The TC works fine, however, the same USB external hard drives I

  • Spry Tabbed Panels Keep Shifting

    I have built a page using the Spry Tabbed Panels. I have one set inside of another. The problem is when you click a main tab and then a secondary tab and then roll over the main tabs again the width changes on the secondary tab. I have no idea why it

  • No Sound with "Trim Back" or "Trim Fwrd" keys

    Hi, When using these two keys in the Timeline, I hear no sound. I do hear sound when using the arrow left and arrow right keys. But I need to hear sound as I am trimming. Is there something I can do to hear sound when using the "Trim Back" and "Trim

  • Value for a characteristic changed with an other value in Query Design

    I want to change the value for a characteristic (Type) in Query Design (not the description, the value). In my cube I have these values: Customer *** Type 22222********SmallCorp 22223********SmallCorp 22224********MedCorp The report should like: Cust

  • SDK 3.0 : code signing error : more than one certificate for my profile ?!

    Hi all, Since I installed the SDK3 with OS3.0, I'm not able to develop on the device because of a provisionning profile issue. So, I've revoked all my certificates, created properly a new dev certificate, associated to a developer provisioning profil