Hello all,
I have a BI 7.0 system which is being recently upgraded with EHP1.
After this upgrade we are facing two problems with DTP.
1) The techical status of the DTP is getting red and We have to manually set the status green.Whichever setting we use in          update and execute tab.
There is absolutly no problem with the records and there are no records in error stack also.
2) We are geting a short dump of ITAP duplicate key.After we change the setting in DTP to no update no reporting in update tab it runs successfully.
What can be the pronlem.
Please help.
Reagrds,
Pratighya.

Hi ,
Is there any semantic key declaration for this DTP.
The semantic key declaration gets deactivated when u change the setting to No update No reporting
Let me know if there is any sematic key declaration and any routine created in the related transformation
Prathsih

Similar Messages

  • Data Package 1 ( 0 Data Records ) at DTP with Status RED

    Hi All,
       For 0 records at DTP level it is showing Overall status & Technical status as RED and yellow beside Data Package 1 ( 0 Data Records ).  There is no short dump no error message. At PSA level in status tab the message displayed is Status 8 which says no data on R3 side for this particular load. Help me out.
    Regards,
    Krishna.

    Hi,
    if traffic light is not highlighted, you are probably running a delta.
    You will have to set the traffic light in the according init.
    (and run init again )
    the setting in the delta will be the same.
    Udo

  • Forcing technical status to RED

    I have a load running for a while. I turned the overall status to red, but the technical status remains yellow and its still picking up records from source system. I tried killing the process in SM50, the jobs seems to die but to only reappear after sometime. I think I need to turn my technical status to red, to stop the process.
    How can i turn the technical status to red? Any inputs or pointers would be appreciated.

    tell your basis team to stop the job in SM50, as these jobs requires special authorization for cancelation which only admin person can do:)
    @KJ...

  • How to change DTP Overall Status from Yellow to Red

    Dear all,
      if I choose "set overall status automatically", how can I change DTP overall status when I want to stop the DTP running? Thanks.

    Folks
    I know how frustrating this problem is even in netweaver 7.0 environment. I found a solution for this problem atlast and it works but a not direct way of resolving this issue.
    When this request is in yellow status and not able to change / delete the request, its actually in a pseudo status and it is a bug in the program. This request sits in table RSBKREQUEST with processing type as 5 in data elements USTATE, TSTATE and this 5 is actually "Active" status which is obviously wrong.
    All we need is, ask your basis person to change the status to 3 in both these data elements and then it allows to reload the delta. Once the delta is successfully loaded, you can delete the previous bad request even though it is still in yellow. Once the request is deleted, the request status gets updated as "4" in table RSBKREQUEST.
    Hope this helps.
    Thanks

  • Overall status yellow, but technical status is green

    We are on SAP BI 7.0, SP 17.
    I am having an issue with a few DTP's. I am loading from a cube to 3 DSO's. The process was working correclty for quite a while, but lately has been running extremely long. For something like 7,000 to 8,000 records it takes only 43 seconds for the DTP to finish and the technical status to change to green. However, it takes 2 hours for the overall status to change to green and sometimes it doesn't at all and I have to set it to red so that I can delete it.
    While it is trying to change the overall status to green the DSO is locked - I can't get into the DSO manage screen - gives me an error message about the locks. I have read some fairly similar posts already, but none that I have seen seem to have the exact issue as I'm having. Does anyone have any ideas why the overall status is not being updated?
    I have tried re-activating the target DSO, source cube and DTP, but that didn't work. I also tried to create a brand new DTP, but that also didn't work. Also, this process is already in a process chain. I am compressing the cube on a weekly basis. Any help is greatly appreciated.
    Thanks
    Brett

    Hi Brett.
    We are experiencing similar problems. I am loading initial load from a DSO with a very high number of requests to a infocube.
    Apparently there is a overflow of the lock table (SM12). There is a lock for each request in the DSO and when the number of locks reaches 3500 the DTP stalls. If I manually set the overall status to green, I get the lock table overflow error message.
    I've told my basis team to increase the enque/table_size parameter, I'll let you if that has any effect.
    Regards,
    Lars

  • XI GRMG Scenarios showing Runtime status Red

    Hi,
      I configure the GRMG Monitoring for XI.
    But I am getting the runtime status RED.
      Can any one help in debugging this issue? All my Java Components are running fine.
    Thanks,
    Nagarjuna.

    Hi Nagarjuna,
    Please take a look at these..
    http://help.sap.com/saphelp_nw2004s/helpdata/en/de/9bdb4064da712ae10000000a155106/frameset.htm
    http://help.sap.com/saphelp_nw2004s/helpdata/en/4f/2c9f3f12e1eb0ce10000000a114084/frameset.htm
    cheers,
    Prashanth

  • Technical status nd QM status

    hi..
    wat is the expansion of QM??...nd wat is technical status nd QM status..
    regards
    indu

    QM is overall status of the request.
    Technical status might be correct sometimes but the QM may be errorneous.
    Secondly you cannot change the Technical Status but you can QM status.
    Thanks,
    Manu
    Assign points if found Useful
    Message was edited by:
            Manu Gupta

  • DELTA CACHE REFRESH getting  the status red

    Hi,
    while doing the DELTA CACHE REFRESH getting  the status red. There be a traffic light displaying RED on the right part of the screen.
    regards,
    bobby

    I think you are talking about sxi_cache related refresh. If yes, then you may check the following:
    1. Service user PIISUSER is not locked.
    2. RFC Destination INTEGRATION_DIRECTORY_HMI is working properly.
    Regards,
    Prateek

  • CCMS Status red

    hi ,
    Integration engine is in status red in component monitoring .I tried a self test and the CCMS status is red.
    I cleared all the alerts in CCMS and repeated selft test.Even then the integration engine is in red and the CCMS too.
    Anybody please help to resolve the issue.
    Thnks,
    Am

    Hi,
    The alerts contain a status indicator with a color and a numerical value. Yellow means a warning, red means a problem, and the numerical value shows the severity of the reported error.
    You can configure the CCMS alert :
    RZ20>>activate maintenance mode>>>Monitor >>create
    create a new monitor by copying an SAP monitor
    change the rules to include all systems
    select your new monitor >>change>>select node ccms_define_r3_system, Edit>>change and change the parameter values for systems
    enablee remote monitoring in RZ21
    create a peoperties variant and activate it.
    go back i RZ20 and assign methods
    you can also define auto reaction method to enable emails in case of alerts. and assign method to a node...
    Also check:
    http://help.sap.com/saphelp_nw04/helpdata/en/0c/e65b3b18debb64e10000000a11402f/frameset.htm
    regards,
    Jyoti

  • In RZ21 the Check CCMS Connectivity is showing status red

    Hi,
    While configuring ECC5.0 in to solution manager 4.0 I am getting the CCMS Connectivity status red. All the RFC's which were generated while configuring are working fine. Please advice.

    Hi,
    You are getting the status as "Not cleared" which means that the payment has not yet been done.
    Please do this by using the T.Code "F-28".
    Goto the T.Code "F-28".
    Enter the date,G/L account,Amount.Select the document number.
    Click on "Process open items".
    Enter your document number.Ensure that the not assigned is equal to "0".
    Click on Simulate.
    Save.
    Before doing this goto the T.Code "FBL5n".
    Click on "open items".Your sales order will be displayed in open items.
    When you pay this amount it will be displayed in "Cleared items".
    Simultaneously,the status will be changed.
    Regards,
    Krishna.

  • Process Chain Status Red, DTP status yellow, DTP is green from inside

    Hello All,
    I have a problem where the  Process Chain  status is red, but the process(DTP) status is yellow.
    When I right click on the yellow process there is no error message and the DTP is green in Process Monitor.
    But the chain did not complete and the rest of the process steps are grey.
    After 20 minutes the Process Chain ran again(automatically after new data arrived) and this time without errors and it went green.
    My question is, how to proceed with the red Process chain and complete the further process and make it green.
    Regards
    Alex

    hi,
    There are scenarios where you need to change status of a process chain or a particular step in process chain.
    You might need to change the status in the cases where we need mark these steps successful so that dependent steps get processed. There are other scenarios where one needs to change the status of a single step in the process chain or status of whole process chain.
    Step by step instructions on change process chain status
    1. Right click on the failed step in the process chain monitor and go to displaying messages
    2. Go to u2018Chainu2019 tab and note down variant, instance and start date
    3. Go to SE16 and the table RSPCPROCESSLOG and enter variant, instance and start dates from step 2 and note down log_id, type, variant, instance.
    4. Go to SE37 transaction and execute the function module RSPC_PROCESS_FINISH and enter the values from step 3 and enter the new status u2018Gu2019 in status field and execute the FM
    5. This sets the status of the process chain (PC)
    After you set the status using the FM, go to the monitor screen of the process chain, you will notice the changed status. Now dependent steps in the process chain will start running
    Thanks

  • Technical Status is in yellow but total status is in Red

    Folks,
    My Init load failed due to RFC errors, in the monitor Total is showing Red Status but the Technical is still showing yellow status and I am unable to delete the failed PSA request to re-start my Init load, please let me know how to resolve this issue.
    Thanks,
    Kumar

    Hi ,
    did you cancel the job in source system .. first cancel that job  and the delete that request ..
    request might take long to delete due the more no of records ..
    check the deletion job in source system wether its progressing or not .. In general you can follow this if you face this kind of issue further ..
    regards,
    shikha

  • QM & Technical Status are RED thouh request is running

    Hi,
    I have one request which is running even now-- (load to ODS)
    in the monitor the request is running but in the manage tab of the data target both traffic lights of technical And QM status were RED!
    Before the load was scheduled i had changed the ODS settings to see the QM status automatically and activate the ODS data data automatically.
    This is very huge dataload and if there is anything wrong then i need to change it immedietly ! it takes nearly 40 hours to finsih this load--
    Should there anything to change or is it OK?
    Raj

    Hi Raj
    In General the moment you made the Qm status to RED it is
    automatically stop all the related jobs or process in some
    pecular cases you to kill the process via SM 50 . Just conatc t
    your BASIS people immdeiately on this and ask themn to kill
    the process related to the request.
    And do the rest of the process like deltion of the request or
    what ever...
    Hope it helps you ..!
    Cheers
    K M R
    Assigning points is the only way of saying thanx in SDN***
    >
    Raj Karan wrote:
    > Hi,
    >
    > I have one request which is running even now-- (load to ODS)
    >
    > in the monitor the request is running but in the manage tab of the data target both traffic lights of technical And QM status were RED!
    >
    > Before the load was scheduled i had changed the ODS settings to see the QM status automatically and activate the ODS data data automatically.
    >
    > This is very huge dataload and if there is anything wrong then i need to change it immedietly ! it takes nearly 40 hours to finsih this load--
    >
    > Should there anything to change or is it OK?
    >
    > Raj

  • 0ORGUNIT_HR01_HIER  Status Tab Green/Details Tab Overall Status Red

    Hello,
      We have been loading the Organization Hierarchy for quite awhile. Somewhere along the way, the following started happening. The <b>Monitor</b> shows the InfoPackage load as <b>green</b> (successful). The <b>Status Tab</b> shows both the <b>Total and Technical</b> as <b>green</b>. The <b>Detail Tab has Overall Status</b> as <b>red</b> and the <b>Transfer line</b> is <b>red</b> but all the others (Request, Extraction, Processing, Subsequent Processing, and Process Chain) show as green. The Transfer line can't be expanded. In total it says 'Transfer (IDocs and TRFC): Missing Messages'. There is no short dump and no system messages. The Step-by-Step Analysis shows all green. Records seem to be loading. Can anyone explain the RED Transfer line and RED Overall Status on the Detail Tab?
    Thanks,
    Diane Merrill

    Hi,
    It means the all the record has been reached the BIW, but some missed info idcos . So nothing to worry about it.
    With rgds,
    Anil Kumar Sharma .P

  • Mail to File Integration(Mail Sender Communication channel status RED)

    Hi all,
    I am doing  Email to File Integration Scenario, XI is reading mails from an particular exchange server mail id & putting it in to a file. now all IR & ID configuration is done.
    But in  RuntimeW Bench -> Adapter Monitreing The Sender Mail Communication  Channel is RED with error occured: exception caught during processing mail message; j<b>ava.io.IOException: invalid IMAP status response; not finding * STATUS, but 00KC NO The requested item could not be found
    </b>
    We check the Exchange Server login Acess through TELNET ,as suggested from SAP Service marketplace
    and login is successfull, with details  available of Inbox
    but in TENET when we try to execute the<b> IMAP Status command error message comes
    " expected space not found"</b> .
    Since XI is not able to read the inbox mail, so Sxmb_moni is blank.....
    can any body suggest that this issus is related to that <b>IMAP Status</b>..........or some thing else..
    our URL is correct.
    Regards,
    Ashutosh

    the URL path was wrong...
                          it should end with   .......<b>exchange/Inbox/</b>
    the sender channel was having error RED ,but it was showing green status intially because delay update .....
    Regards