Hi,
My client want to use F110(Automatic outgoing Payment) to payment the vendors. But they want to avail Credit for at least 30 days .that means , those invoice process had been done before 30 days those should come to the APP PROPOSAL FOR THE PARTICULAR VENDOR,OTHER WISE NOT TO BE SEEN IN APP PROPOSAL  Is there any provision given in FBZP ?
<removed_by_moderator>
With Regards,
Sudipto

Dear Paul,
If you want to check Due date then there is no setting in FBZP but at the time of running APP through T.code F110 , while defining payment proposal parameter there is 4th no. tab page with name 'Additiona Log' . in this tab page there is first option Due date check you tick on it and system will check due date for all vendors and customers which you have selected for Payment.
thx.
Ganpat

Similar Messages

  • Payment Due Date selection in F110

    Hi Experts,
    We have defined a payment term with 2% discount in 30 days time. We take the baseline date form the shipping date via substitution. We execute the payment run two times in a week.
    Now say if the shipping date is 03.08.2010 then due date for discount of 2% will be 02.09.2010 (Which is Thursday). We execute the payment run on Wednesday (01.09.2010) and Friday (03.09.2010) every week.
    Now when we do the payment run on 01.09.2010, the next payment date given is 03.09.2010 and thus this document got selected as it is due on 02.09.2010. But as 02.09.2010 was holiday, so we could have paid that in 03.09.2010.
    How to avoid such kind of scenario, when a document due date is a holiday falling just before the next payment run date, should be paid on that next payment run date? (This will save us the interest for 2 u2013 3 days and the amount is huge, so the total effect will be high.
    We are currently excluding such documents in free selection tab manually, but takes a lot of time.
    Thanks,
    Atif

    Hi,
    Only in the scenario when you have the payment run date just next to the holiday date, (And you do not lose the discount if you pay on the day next to holiday), then
    I will suggest putting the next payment date as that holiday date.
    So in your example given above, I will suggest to put the next payment run date as 02.09.2010 in the payment run of 01.09.2010, so that the documents falling due on 02.09.2010 does not get included in this payment run of 01.09.2010.
    And then when you execute the payment run on 03.09.2010, this document will automatically come as it is falling due on 02.09.2010
    Regards,
    Gaurav

  • Due date Check

    Hi,
    My client wants to enjoy 30 days credit from the vendor and according to that payment terms are attached and they want to avail the credit from the date on which receiving the material (GR Date).so the base line date will be the date of GR takes place.
    Now, in Exceptional Case on the request of the vendor thay can pay the Vendor with a cash discount and for that case how can I change the Base line date in the vendor Invoice?
    <removed_by_moderator>
    With Regards,
    Sudipto

    Hi.
    I saw in Ecc 5.0 those invoics are open< if you click on the Vendor invoice line iten in Vendor ledger the window will open where we can edit Base line date, paymen terms etc. but in case of Ecc6.0 it is not coming. I do not know if there is any matter of display authorization !!!!
    for those invoice posted already but open , how to change the payment terms and also the base line date . My client are using ECC 6.0 version
    can you help me out?
    with regards,
    sudipto

  • Vendors Payment Before Due Date

    Dear All,
    We could like to restric the release of Vendor payment before the due date.
    We feel there is a system in SAP by which it should give a Error/ warining message (pop up) if any payment is made before the due date.
    Do suggest.
    Regards,

    SAP will give you message if your posting date for e.g. is in past or in future, but the next posting date in F110 parameter decides if you can pay some not due items today or not. SAP will not give you a warning message even if the next posting date is 10 days ahead of today's date.
    In the F110 parameter please make sure Next posting date is always the very next day of the payment run date or Posting date and in the Additinal log tab, please check the indicator Due date check
    This user procedure will make sure that payment is never released before the due date.
    But if still you want some system message to pop up, then SAP standard setting I think will not be of great help, you need to use the BTE00001830 (functional module SAMPLE_PROCESS_00001830) which will help group all the not due items in a group, and exclude the entire group from payments. Information about the group will be received by FM in structure C_REGUH and its line items in table T_REGUP
    By Setting the field XIGNO in C_REGUH to the value "X" the entire group of not due items can be excluded from payments. Please take your abaper help
    Thanks
    Ron

  • Outgoing payment vs invoice due date

    Dear Forum,
    Our management wants to get historical due date outgoing payment compare to invoice due date. So we know if out finance paid accordingly based on the invoice due date. 
    The fields ;
    Invoice Number     
    Invoice Date     
    Invoice Value     
    Invoice Due date     
    Outgoing Payment Number     
    Outgoing Payment Date     
    Type of Payment ( check / cash /bank transfer)     
    Due Date Check/Cash/Bank Transfer
    Out Going Value
    If any experts can help me to get the query? thanks

    Hai!
    Run this Query in SAP Query Manager.
    Declare @FromDate datetime
    Declare @Todate datetime
    set @FromDate = (select min(S0.DocDate) from OPCH S0 where S0.DocDate >= '[%0]')
    set @ToDate = (select max(S1.DocDate) from OPCH S1 where S1.DocDate <= '[%1]')
    Select
    P0.DocNum as 'Invoice Number',
    P0.DocDate as 'Invoice Date ',
    P0.DocTotal as 'Invoice Value ',
    P0.DocDueDate as 'Outgoing Payment Number',
    V0.DocNum as 'Outgoing Payment Date ',
    V0.DocDate,
    (case
    when V0.CashSum > 0 then 'Cash'
    when V0.CheckSum > 0 then 'Check'
    when V0.TrsfrSum > 0 then 'Bank transfer'
    end) as 'Payment Type',
    V0.DocDueDate as 'Due Date Check/Cash/Bank Transfer',
    V0.DocTotal as 'Out Going Value'
    From OPCH P0, OVPM V0, VPM2 V2
    Where
    V0.Docentry=V2.DocNum and
    V2.Docentry = P0.Docentry and
    P0.DocDate >= @FromDate and
    P0.DocDate <= @ToDate
    Regards,
    Thanga Raj.K

  • Interest calculation on due date and not on invoice

    Hello,
    Pls can some one let me how to start interest calculation on due date and not invoice date.
    In the interest calculation, T code FINT, the system calculates interest from invoice date till clearing date and not from due date till clearing date.
    BR,
    Zulfikar

    Hello,
    We have selected the Always calculate interest from net due date check box. but now when i run FINT transaction for a customer it is calculation interest from invoice date and not on due date. the item is already cleared.
    The scenarion is
    the net due date of the docuemnt is 30.07.2008 so the interest calculation should stard from 31.07.2008 till clearing date. but the interest calcualtion is starting from 01..07.2008 which is the invocie date.
    BR,
    Zulfikar

  • WLI 7.0 Question about Set Task due date action

    Hi,
    I am trying to manage time out issue efficiently and, as described in the
    WLI documentation, the
    timeout has to be design with a dedicated path with, as the first task, a
    set task due date action.
    I was wondering about the timeout of this task due date...
    How can I stop this action before the end of the 'due date' without deleting
    the instance associated to my workflow ?
    Do you have any advice ?
    Thanks
    Alexandre

    HI,
    Customizing the Task List
    You can customize the column headers or search for required tasks by clicking on Customize Table Header. The option allows you to specify the columns to be showed in the list table, to provide the sorting order, and to set the page size. The sorting order could be complex with option to provide multiple columns for sorting and the order (ascending/descending) for each of them.
    To create a custom query and search for tasks:
    1.In the Task List page, click Customize Table Header.
    In the Construct a Custom Query form, specify the search criteria by specifying any of the following values.
    2.Enter the task name. You can use the * character at the start or the end of the name.
    3.Enter the task ID. Separate multiple values using comma.
    4.Select the check box against the Administration and Working state of the task.
    5.Enter any comment. You can use regular expression.
    6.Enter the priority range.
    7.Enter the Assignee, Owner, or Claimant names.
    8.Specify the completion due date range.
    9.If required, select the Include tasks with no completion due date check box.
    10.Click Apply.
    All tasks that match the specified criteria are displayed in the Task List page.
    To customize the table header:
    1.In the Task List page, click Customize Table Header. The Construct a Custom Query form appears.
    2.In the View form, select the columns that you want to view in the Task List page.
    3.Select the Preserve Search Criteria check box to retain these details for the current session.
    4.Select the maximum number of search results that should be displayed on the page.
    5.Select the number of rows that should be displayed in the page.
    6.Click Apply.
    The view in the Task List page is updated based on the current settings.
    Using this option you can set the completion due date
    Hope this information will help you solve the issue.
    Regards,
    Kal.

  • Unable to set completion due date on a task in wli 10.3

    In the task plan that I have created I have set the property "Completion Due Date" to 7 days in the properties tab for the step, yet when I view that task that gets created from this in the Worklist User Portal the Completion Due date is still not set.
    I have also tried doing this programatically by doing the following:
    this.StepName.getTaskControl().getTaskData().setCompletionDueDate(this.completionDueDateCal.getTime());
    where completionDueDateCal = current Date + 7, and then view in the Worklist Portal and still no completion due date.
    So far the only success that I have is if I manually set the date while viewing the task in the Worklist User Portal.
    Any help would be appreciated. I am ultimately trying to the task to expire after a set period of time(7 days).
    Thanks
    Edited by: user12248500 on Sep 21, 2010 3:20 PM

    HI,
    Customizing the Task List
    You can customize the column headers or search for required tasks by clicking on Customize Table Header. The option allows you to specify the columns to be showed in the list table, to provide the sorting order, and to set the page size. The sorting order could be complex with option to provide multiple columns for sorting and the order (ascending/descending) for each of them.
    To create a custom query and search for tasks:
    1.In the Task List page, click Customize Table Header.
    In the Construct a Custom Query form, specify the search criteria by specifying any of the following values.
    2.Enter the task name. You can use the * character at the start or the end of the name.
    3.Enter the task ID. Separate multiple values using comma.
    4.Select the check box against the Administration and Working state of the task.
    5.Enter any comment. You can use regular expression.
    6.Enter the priority range.
    7.Enter the Assignee, Owner, or Claimant names.
    8.Specify the completion due date range.
    9.If required, select the Include tasks with no completion due date check box.
    10.Click Apply.
    All tasks that match the specified criteria are displayed in the Task List page.
    To customize the table header:
    1.In the Task List page, click Customize Table Header. The Construct a Custom Query form appears.
    2.In the View form, select the columns that you want to view in the Task List page.
    3.Select the Preserve Search Criteria check box to retain these details for the current session.
    4.Select the maximum number of search results that should be displayed on the page.
    5.Select the number of rows that should be displayed in the page.
    6.Click Apply.
    The view in the Task List page is updated based on the current settings.
    Using this option you can set the completion due date
    Hope this information will help you solve the issue.
    Regards,
    Kal.

  • Alert for orders based on due date

    Hi All
    I need to query to get sales order based on tomorrow date.
    scenario:
    Sales orders are imported using DTW and due date is put in as tomorrow , so i need a query to show me all the imported orders based on due date.
    check below the query i'm using
    SELECT T0.DocNum, T0.DocDueDate, T0.CardCode, T0.CardName, T0.DocTotal, T0.U_ROUTEMARKTN, T0.U_ROUNDS, T0.U_DAYOFWEEK
    FROM [dbo].[ORDR] T0
    WHERE DATEDIFF(Day, T0.DocDUEDate, GETDATE()) = 0
    ORDER BY T0.U_ROUTEMARKTN, T0.U_ROUNDS, T0.U_DAYOFWEEK, T0.DocDueDate
    thanks

    Hi Bongani,
    Change your query condition to:
    WHERE DATEDIFF(Day, T0.DocDUEDate, GETDATE(), T0.DocDUEDate) = 1
    Gordon

  • F110 payment only possible 8 days after net due date, why?

    Hi all,
    When we try to post a payment in F110 by choosing a next p/date as for example 24 April all invoices with net due date up to that date will be included. In payment proposal only invoices with net due date up to 15 April is included, not invoices with net due date 16 April and after. There is something with a tolerance of 8 days but I don´t know where this configuration is set. Payment terms is 30 days net and there I can´t find anything about any tolerance days and i can´t find anything in FBZP either. Does anyone know where I can find these days set?
    We want to create the payment per net due date. We don´t work with payment order.
    BR L

    Hi,
    Check in transaction code FBZP, all company codes. Double click on the company code, you will the find the tolerance days for payable.
    Thanks
    Aravind

  • Cash discount calculated even after the due date in F110

    Hi Friends,
    Invoice and Credit memo is created with the reference to PO, but when the payment is made to the vendor through F110 the cash discount is calculated on the credit memo even though it has passed the due date.
    Let me know what else is remaining that has to be checked and corrected
    Regards
    Paddy

    Check the following configuration:  t-code FBZP -> All Company Codes -> double-click on the relevant company code to display the details. 
    In the "Cash discount and tolerances" section, I'm thinking that you'll find that the "Max.cash discount" check box is checked.  This check box tells F110 to always take the discount, even if the terms have expired.  If you uncheck the box, then F110 will only take the discount within terms.
    Regards,
    Shannon

  • F110 - Bill of exchange - latest due date more than 999 days ?

    Hi all:
      We have a problem about Payment run / F110.
      Because finance department want to open "Check" to bank  and the due date is about 4 years later (1500 Days).
      And we run the payment run it shows error message " FZ 732 Item not due in 000 - 999 days " .
      I think the reason is because the maxium latest due date only allowed 999 days,right ??
        "Latest due date in" of "Bill of exchange due date for outgoing payments" in paying Company Code  (OBVS)
      Is there any way ( IMG / Exit / Enhancement ) can resolve this problem ??
      thanks a lot.

    Hi Mauri:
      Thanks your reply.
      actually, we have asked user to open their check - more then 999 days - manually.
      Because this is the second case we met in past 6 months, so we are looking for any solution ( Exit / Enhancement ) to meet user's requirement. 
      We won't create any new add-on program to meet user's requirement, but hope exit or enhancement can make it, anyway, thanks again.

  • Change due date in receivables for credit check

    Hi Sappers!!
    Scenario: When SAP performs a credit check for a customer we need that pending receivables
    (open items) for this customer which have a concrete payment method, don't use due date
    for calculation, instead we want to use invoice date for carrying out the credit check
    calculation.
    Is that posible? Is there any user-exit where we can change this date to be used during
    credit check control for documents which fulfill this requirement?
    We don't want to change permanently the due date for this kind of documents, we only need to take another date into account when performing credit control.
    Thanks so much in advance & best regards

    Thanks so much for your quickly answer.
    Creating a new payment term is not a valid solution because, we don't want to change any date in the financial document. We just only need to use another data only for credit check. Here you have a concrete example:
    Invoice created with invoice date 01/12/2009
    Payment method confirming 90 days.
    Base line calculated: 01/03/2010
    If we create a new sales order, this open item will not be considered exceeded because due date is still in the future.
    We want to consider it as exceeded and the due date would be 01/12/2009 but only for credit check. This "new" due date must not be stored anywhere.
    Thanks so much once again & best regards

  • Show Net Due Date in F110 - Proposal list / Payment list

    Dear Gurus,
    I would like to ask for help in below issues:
    I want to display "Net due date" field in transaction F110 - Proposal list / Payment list (program : RFZALI20) but I only found "Baseline Payment date" and "Payment term" in variant maintenance.
    Would appreciate if someone can give me the solution / suggestion for above issue?
    Thanks & regards,
    LOI

    Hi,
    1) You may copy the sample interface function module: SAMPLE_INTERFACE_00002110 (to get the passing parameters) and code your coding as below:
    **To calculate Net due date = baseline date + payment term
    FUNCTION yyyy.
      LOOP AT T_REGUP_LST.
        T_REGUP_LST-ZZFAEDT = T_REGUP_LST-ZFBDT + T_REGUP_LST-ZTERM.
        MODIFY T_REGUP_LST.
      ENDLOOP.
    ENDFUNCTION.
    2) Make sure you have declared the new field in tbl CI_REGUP_LST and CI_REGUH_LST (item level in tbl-CI_REGUP_LST; header level in tbl-CI_REGUH_LST).
    3) Configure IMG through FI > Financial Accounting Global Settings > Business Transaction Events
    a) Settings > Products > of a Customer > Define a new product and activate it
    e.g Product = Zxxxx
    b) Settings > P/S Function Modules > of a Customer >
    e.g Event = 00002110
         Product = Zxxxx
         Appl = FI-FI
         Function Module = yyyy
    4) Proceed to test the new fields added through F110: Payment / Proposal List from program RFZALI20
    I hope to hear a good news from you.
    Thanks & regards,
    LOI

  • F110 bill of exchange: error FZ731 "...requires payment before due date"

    Hi everybody.
    I'm facing an issue that is driving me crazy <:-)
    I want to configure a payment method of type "bill of exchange" (in Spain, "pagaré"). I have several due invoices (due dates: 30/11/10, 31/12/10...), which have this payment method. Some other items are not yet due (30/1/11).
    When carrying out a payment run thru transaction F110, the system asks for the bill of exchange issue date, which I have populated as 30/11/10. At another tests, I have populated as 10/1/11.
    When running F110, the vendor items are then classified as exceptions, with error FZ731 "Pymt method I in the item requires payment by b./exch. before due date", and also message FZ732 "Item not due in 000 - 000 days".
    I think this problem may be motived because the definition of the payment method "I" (company code data) says: Days until due date: 0. But this field is not updatable.
    I've searched the message numbers in the forums, but found no answer.
    Anybody can help? Kind regards,
    Alvaro

    Never mind, I just had to update the Paying company code, fields Bill of exchange due date... > Earliest-lates due date in...days.
    Regards.