Dyanmic safety stock cal

Hi,
Suppose there is some days of supply in the past, then will the CTM generate supply for the same in the past?
Thanks
SS

Hi,
Maximum earliness:
By using the Maximum Earliness function we can  restrict the timeframe between individual receipts and
requirements for a location product, and so prevent the system building up too much supply. The system
only generates  a receipt to cover a requirement when the availability date for this receipt falls within
a specific timeframe before the requirements date. However, the system can use existing receipts to
cover the requirement.
Order creation frame (horizon for creating orders):
By using the Order Creation Frame (Horizon for Creating Orders) function we can  restrict the processing
time for a product across all BOM levels in such a way that generally, less supply is built up. However, if you have entered a specific timeframe for creating orders, CTM planning can think that only an alternative with a lower priority can cover the requirement in the given timeframe. This results in a shorter timeframe between the availability date of the receipt
and the due date of the requirement.

Similar Messages

  • Safety stock data update in APO product master

    Hi Gurus
    I have an active IM for a product . when i change the safety stock in R/3  , the same is not getting updated in APO. The method maintianed is SB
    Please suggest

    Finally i need to apply the below code in Exit EXIT_SAPLCMAT_001
    INCLUDE ZXCIFU01 *
    IF CT_CIF_MATLOC IS REQUESTED.
    if no saftystock-method is explicitly set
    use method 'SM' if safty stock & time is transfered
    use method 'SB' if only safty stock is transfered
    use method 'SZ' if only safty time is transfered
    LOOP AT CT_CIF_MATLOC.
    LOOP AT CT_CIF_MATLOCX WHERE MATNR = CT_CIF_MATLOC-MATNR AND
    LOCNO = CT_CIF_MATLOC-LOCNO.
    CT_CIF_MATLOCX-MSDPSBMETH = 'X'.
    *APO und R/3: Safety stock
    IF CT_CIF_MATLOCX-SAFTY = 'X' AND
    NOT CT_CIF_MATLOC-SAFTY IS INITIAL.
    *APO: Safety days' supply R/3: Safety time/act.cov.
    IF CT_CIF_MATLOCX-SVTTY = 'X' AND
    NOT CT_CIF_MATLOC-SVTTY IS INITIAL.
    *Maximum of stock und safety time
    CT_CIF_MATLOC-MSDPSBMETH = 'SM'."Maximum
    ELSE.
    *Safety Stock
    CT_CIF_MATLOC-MSDPSBMETH = 'SB'.
    ENDIF.
    ELSE.
    IF CT_CIF_MATLOCX-SVTTY = 'X' AND
    NOT CT_CIF_MATLOC-SVTTY IS INITIAL.
    *Safety days' supply
    CT_CIF_MATLOC-MSDPSBMETH = 'SZ'.
    ENDIF.
    ENDIF.
    MODIFY CT_CIF_MATLOC.
    MODIFY CT_CIF_MATLOCX.
    ENDLOOP.
    ENDLOOP.
    ENDIF.
    Thanks all for the input

  • Report for Reorder point, safety stock, current stock and fixed lot size

    Hi,
    Purchasing Dept. is looking for a report which can give list of materials falling below the reorder point, so that they can go ahead and create procurement proposals for those materials.
    They also want to see the Reorder Point, Safety Stock, current stock and fixed lot size in the same report.
    Let me know if there ia any standard report availbale which displays the same or any approach to get the same.
    Thanks in Advance.
    Regards,
    Shankar Goud.

    Hi,
    There is no standard report because this is meant to be managed by the MRP run.
    The MRP lists show all materials that have a problem (such as stock below reorderpoint) but MRP generates requirements for these anyway and so all you need to do is to look for the MRP generated requirements (requisitions?) and you have your list?
    Are you using MRP?
    If so then please use the standard functions in MRP to get this.
    If not, then WHY NOT?
    Steve B

  • Report on current stock and safety stock

    Hi,
    I want to have the report on current stock and safety stock.
    In MC.9 it gives wrong safety stock. When I go to cross check the safety stock in material master & in MC.9 I see differences.
    Thanks,
    Kiran

    You can user tcode MC.9 or MC.5 to know valuated stock available at given plant. Stock lying in Returns (MB52) will not be a part of this report as it non-valuated stock.
    The stock in the accounting view of the material master considers stock at plant level including stock in Transit (Intra & Inter plant stock trasnfers) & special stock like stock issued to vendor , consigment stock etc which is valuated at plant level.
    whereas and stock in the plant stock view of the material master does not consider such special stocks hence there will always difference in both veiws.
    For Physical stock as on particular date you can consider MB5B report with radio button "Storage location/Batch Stock" wherein you will get Quantity issued & Qunatity received in those SLOC along with Opening stock & Closing stock for the specified period.
    use tcode
    MBLB to know stock at vendor.
    MB54 - Consignment Stock.

  • Safety stock not covered by schedule lines in planning run

    Hi !
    In our organization we are trying to implement scheduling agreements and automatic creation of delivery schedule lines through MRP. We have MRP type PD and it considers the reservations created by PM orders and Production orders as requirement elements. When I do the planning run, it creates schedule lines for the PM order reservations and purchase requisition for safety stock. I need it to create schedule lines for all scenarios. Kindly help and suggest a solution.
    Regards,
    Satya

    Hi,
    Please refer the below links.
    Schedule Lines not getting created in MRP
    Re: No Scheduling line is generated when RUN MRP
    Hope it helps you.
    Thanks.

  • Calculation of Safety Stock and Reorder Point under Forecast Model T

    Hi Gurus!
    Happy Holiday!
    I would like to ask for your assistance on how the the safety stock and reorder point was calculated with the following values available. I would really appreciate it if you could give me details on the calculation.
    Below are the values:
    Basic data
    Forecast date        01.12.2009        Unit                  CTN
    Forecast model       T                 Service level         0.0
    Period indicator     M                 Paramtr profile
    Control data
    Initialization                                Tracking limit        4.000
    Model selection      A                 Procedure selection   2
    Parameter optimizatio                Optimization level    F
    Alpha factor         0,10               Beta factor           0,10
    Gamma factor       0,00              Delta factor          0,30
    Basic value           5.464-           Trend value          5.603-
    MAD                      4.758            Error total              4.722
    Safety stock         1                   Reorder pnt.          1
    No. of values
    Consumption           6                Forecast periods       1
    Initial. periods      0                Fixed periods          0
    Periods per season   12
    Historical data
    Period                Original     Corrected value
    11.2009                3.000              3.000
    10.2009                0.000              0.000
    09.2009                0.000              0.000
    08.2009                9.000              9.000
    07.2009               21.000             21.000
    06.2009               20.300             20.300
    Forecast results
    Period                Original     Corrected value
    12.2009                0.000              0.000
    Appreciate your assistance!
    Thank you and Happy Holidays!
    Ji

    Sweth, you are asking for consulting, and in my opinion it is way beyond what can or should be reasonable to achieve in such a forum. You are asking complex questions, that most probable have more than one possible answer.
    I suggest that you get on-site help from a knowledgeable and experienced consultant. These are crucial business issues, and should be dealt seriously.

  • Safety stock and Reorder point calculation in inventory planning

    Hi,
    How System does  the calculation of own safety stock, and Reorder point, maximum safety stock level at parent and child location while running inventory planning services in SAP APO SPP. does anyone about the calculation  please let me know
    Regards
    Puneet

    Hi,
    How System does  the calculation of own safety stock, and Reorder point, maximum safety stock level at parent and child location while running inventory planning services in SAP APO SPP. does anyone about the calculation  please let me know
    Regards
    Puneet

  • Safety Stock T-code

    Dear Experts,
    What is the T-code for viewing all the safety stock which are maintained for all materials.
    Regards,
    Phalgun Patel

    Hi,
    Execute t-code se16, then enter MARC table and press enter. Enter list of materials or plants or this can be run without any selection parameter.
    Execute it and look for field EISBE (Safety stock).
    Regards,
    Gaurav

  • No planning file entry for safety stock

    hello!
    i do not have a planning file entry for safety stock. my material has required safety stock and no quantity on plant stock. therefore MD01 should create a purchase requisition - but is does not. i do not have an entry in the planning file as well.
    any ideas what could be the reason?
    thanks!
    matthias

    Hi,
    - First of all check whether MRP is activated or not for Perticuller Plant.T.code is OMDU.
    - Which MRP type is maintained for that material?
    - In rare cases (Materials uploaded by LSMW using Badi) it is observed that system miss to make the entry in Planing File.So better will be set a Back Ground job to activate Planing file OMD0 or make manual entry using T.code MD20.
    Regards,
    Dhaval

  • Dynamic update of safety stock in SAP R/3 systems (ECC 5.0 version)

    Hi Friends,
    Forgive my newness to SAP. Let me explain the problem i am facing in SAP. I want to identify the parameters to dynamically update the finished goods safety stock for each depot by SKU wise.
    Current process :- Safety stock is calculated manually and updated by using Transaction code MS02 in the system.
    It would be highly useful if i know the flow in SAP system and how the current process can be changed?
    If more info is required i'm ready to give.
    Thanks in advance

    Hi Mario Adler,
    Thanks a ton for ur answer.
    Will it update safety stock for finished goods in each depot by SKU wise? Raw material safety stock isn't my concern.
    project description :  Manufacturer of chemical goods , 70+ products,350 skus
    Distribution : factory to depot (bulk volume)
                          Mother go-down to depot(Stock transfer)
                         No of depots :33,factory:3,mother go-down -1
    Sales forecasting is done in excel for every month and updated to SAP via  BAPI. After that DRP,MRP and other runs takes place.
    What are all the areas i need to touch in to get the parameters to update the safety stock?
    Regards
    Arasu
    Edited by: Arasu_IIM on Apr 26, 2011 12:52 PM

  • MRP with Safety Stock

    Hi All,
    I am working on a trading Company. I have one scenario for Make to Stock, whenever the MRP will run it should consider the safety stock and the MRP should be run through the reorder Point. As i do not have much idea about the MRP, so please guide me on this. Please give me step by step Procedure to do this. What MRP type,shall i choose while creating the material master and which lot size? Its will be better if you clarify with an example.
    Sure,Points will be awarded.
    Thanks in advance.

    Hi Dharama,
    I have run the MRP same as the example given by you for Lot size HB and MRP type VB as--
    Ex. Stock 50
    Reorder point 60
    safety stock 30
    MAx stock level 100
    When MRp run system create P.R for 50 no's.
    I understood the first two line items as we have the safety stock as 30, so it will be reduced from the avalaiable quantity 50. It will become as 20.
    But after that, how the system is calculating on the reorder level and the maximum stock level. Please clarify me on this.
    Thanks in advance
    Sure, Points will be awarded.
    Edited by: Neeraj Saini on Oct 23, 2008 7:53 AM

  • MRP - project stock - safety stock

    Hello,
    My MRP plans on a project stock.
    When I try to fill in the field "safety stock" in material master data MRP plans the safety amount on unrestricted use stock. I would like it to be planned on a specified project.
    Do you know how to do it?
    Best regards
    Piotr

    Hi,
    procurement for safety stcok will always happen wo ac assignment. So you may have look for use of some other parameters like lot sizing or minimum lot size fields etc.
    Regards
    Vineet

  • In Material master safety stock field is in display

    Hi,
    As a consultant i am able to change the Safety stock field in MRP view in the test system and Production also,but for the user this particular field is in display mode wheras other field in the MRP view user is able to change.
    Kindly help me if,there is any settings for the same.
    Regards,
    Prashant

    Hi Prashant,
    Have you checked if there is any configuration made to lock same fields on material master? Follow the below path please;
    Logistics u2013 General ==> Material Master ==> Field Selection ==> Define Lock-Relevant Fields
    May be someone defined some fields as u201Clock-relevantu201D in customizing and during creation or changing of material master he/she set this indicator. You are able to change those fields because you may have SAP_ALL authorization whereas others may not.
    Best regards

  • Safety Stock Issue

    Hello Gurus,
    We are in SCM 4.0 and currently we are facing an issue in safety stock calculation.
    We run a macro to calculate the safety stock. The safety stock for a particular bucket is calculated by the sum of total demand of next consecutive 4 buckets. The problem is that the macro works fine if we select a single product-location combination but when we select a product at multiple locations combination (aggregated level) the macro doesnt work. The value is not displayed in the planning book. However, we could see the total demand value for that particular bucket.
    Hope I am clear and please help me on this.
    Thanks,
    Sai

    Hello all,
    I have a quick question:
    Do we need to maintain the data at Location-Product Group level to go for Aggregated Safety Stock Planning?
    Let me explain my case:
    We have the following selections at Location-Product level:
    Sel1: Prod1 at Loc1
    Sel2: Prod1 at Loc2
    Sel3: Prod1 at Loc3
    When I make either of these selections individully in the Planning book the safety stock macro works fine but if I make any of these two selections or all the three selections at a time, then the values does not show up at the Total but I can see the values at 'Details' level if I select Location at the Header Information.
    We are thinking of Aggregated Safety Stock Planning and We do not mainatain the data at Group level. Can we still go for Aggregated Safety Stock Planning?
    Could anyone give me some suggestions on this?
    Thanks
    Sai

  • Safety stock Warning message ?

    Hello Friends,
    Need some help in creating a new functionality,Currently our customers can order a large quantity for any given material.  There is no check in place that warns the customer service rep (CSR) that this will stock us out or that this order is 1-2 times our safety stock.  I would like to get a function in SAP so that at order entry, if a CSR enters a quantity that is more than 50% of our safety stock, they will receive a warning stating that this could wipe out the inventory for other customers. 
    I would like to be able to set-up this functionality for a certain set of materials that have safety stock and that are active and high-volume materials.
    Please advice what configuration changes needs to be done in order to fullfill this requirement.
    Thanks in advance.
    MO

    Hi Mohammed
    there are no configuration changes. I hope the following would work.
    1. How do you identify high volume materials.
    2. How do you identify Active materials.
    You must find a way to do these or choose some field in the material master for which this check needs to be performed.
    Once this is done you can write code in MV45AFZB to perform the check at VBAP level.
    Thanks
    PG

Maybe you are looking for

  • Installation and creation of first database in Oracle on Solaris 5.10

    hi all, I have dug around and found that /etc/system is no longer used in solaris 10. i found that the command prctl is now envoked to setup the kernel parms. I have solaris 10 - oracle 10g - Intel Processor. Can anyone point me in the right directio

  • Sip 500 Internal Server Error Reason: Q.850;cause=16

    Please help in understanding what is wrong in the config .Incoming calls don't work. show run: voice service voip ip address trusted list   ipv4 87.226.136.164 255.255.255.255   ipv4 172.16.24.0 255.255.255.0   ipv4 188.254.68.66 255.255.255.255   ip

  • Settings in Safari on Laptop

    Just got a MacBook Pro. For some reason my settings in Safari didn't follow over. How do I get them on the laptop? Larryjay

  • Help remove hot spot from sun

    Help! I have no clue on how to do this. I have a wedding photo of mine, but the sun's glare is in the photo. I need to remove the color cast it's causing in the shape of a circle. I have the raw version of the photo as well, if that helps. Thanks in

  • Patch made controller change

    Hello, Curently, we have 11.5.10 and to fix some issues applied the patch 855411. And after that, in the procurement pages, the Controller gets changed from the custom one to the seeded one. Due to that, the page functions with standard behaviour. Co