Earlier loaded request status

Hi Experts,
   In my validation program i am checking the source file format and triggering the respective process chain events to load data into BW(FILE->ODS1->ODS2->CUBE) . Now i would like to trigger process chain if the previous request status of ODS1,ODS2& CUBE are green only. I would lke to notify my support team if previous request in any of the above targets is Red.
Please shed some light on this.
Regards,
Ramesh

Hello Ramesh,
I think you will have to include ABAP Program in your process chain which will check the status of previous load from the table RSREQICODS and RSREQDONE and if this is successful then trigger further processes.
There is How to guide for how to integrate ABAP in process Chain.
Hope it helps.
San.
Message was edited by: SAN

Similar Messages

  • Delta load -  request status is partially activated

    Hi to All,
    From one Info package data is loading to 1 CUBE, 1 ODS simaltaneously through PSA, but data is not updated to PSA. Then I have activated the ODS and then I changed the ODS request status to GREEN but here transfered records are 2000 but added records are 0, after few minuets data packets came into PSA then I am trying to CHANGE THE REQUEST ODS STATUS TO RED, IT IS SAYING "REQUEST IS PARTIALLY ACTIVATED".
    In both ODS and CUBE manual updation terminating.
    LOAD IS : DELTA
    Pls can anyody give suggestions/inputs to come out from the problem.
    Thanks In Adv,
    MSM.

    Hi Akash,
    Here ODS request status is changed to(from RED ->GREEN) GREEN forcebly b'z red request is not activating the ODS, after ODS activation when I am trying to change the request status to RED, its saying " REQUEST IS PARTIALLY ACTIVATED NOT POSSIBLE TO CHANGE THE QM STATUS"
    If we want to delete the request the REQUEST SHOULD BE IN RED, its allowing to change to RED
    pls help me on this what can we do now
    Thanks in Adv
    MSM.

  • Request Status for Master Data Attributes Load

    Dear All,
    We are trying to load attribute master data and volume of which is relatively huge around 10,000 records.
    We are facing challenge while updating attribute data from master data info object , the load status remains in yellow status and when we went to details screen it states that data is transfered to transfer rule . ( it has been loaded successfully in to PSA).
    Could anybody please give some hint on this challenge ??
    Regards
    Kapadia

    Hi  Paolo Siniscalco,
    You are right, as number of records are more , i have chosen update of "Only PSA" and then "Subsequently in Data Targets".
    I tried other option also which is infopackage  schedule "Execute in Back ground" and                                                         
    "Request batch process runs untill all data is updated in BW". And process went in to infinite loop.
    Some how i am not able to track out why the request status is not changing .
    Regards
    Kapadia

  • Need help in deleting the data load request

    Hi All,
    In the system one erroneous data load load request is being generated( whoes status is  monitor without Request), because of this I am unable to activate other requests...
    I want to delete this request, I am deleting it but it is not, it is still remain in the system, and i am unable to activate it as it is an erroneous one, I have deleted that request from the backend table RSMONICDP as well, but still no successful results.
    Please give ur suggestions on this.
    Thanks,
    vinay

    Hi
    There is a possible solution for these kind of issues .
    1. Note that bad request number
    2. Go to SE16
    3. Open table RSODSACTREQ.: Filter the contents by that request number . There will be one entry for that request . Delete that entry
    4. Open table RSICCONT. There will be one entry for that request . Delete that entry
    5. Open Table RSMONICDP. Filter the contents by that request number . There will be 3-4 entries for that request depending on number of data packages in that request .Delete all those entries

  • Request Status not Activating

    Dear All,
                  I have created Datasource and DSO and flat file and also created DTP.  If i request perticular request id , its not activating.  request status not activating.
    With Regards,
    Baskaran.

    Hi Baskaran,
    Follow these steps.
    Do the loading process as you are doing i.e. using Info package load to PSA, then using DTP to DSO.
    Then after loading data, you go to manage. Then Select your green request and then click activate.
    A new window will open. There your request will be green. Again select it and click on start (do not click on stop).
    Then you will find refresh button there. Click on it. Your green request will turn yellow. Now go on clicking refresh until your request disappears from there. After that close the window.
    Then again click on manage. Click on refresh. Now select active data. Your data will be displayed.
    Hope this helps.
    thanks,
    rahul

  • Customize the Service Request Status

    I am trying to customize the status for a Service Request form.  We want to add some additional ones to that list.  I am not finding where I go to update that list.
    Cheers!
    Matt

    The list you are looking for is in the Library Tab, Lists view, Service Request status. take a look at
    How to Add a List Item.
    I'd like to argue that this is probably not what you want to do, however, as the status property is pretty tightly managed by the out-of-the-box workflows that move service requests forward, and manually setting these statuses will likely break the out-of-the-box
    activity status engine.
    Instead, you probably want to Create a new MP in the authoring tool, Locate and
    Extend the Service Request Class, add a new Enumeration property to your extension, use the Create List button to create a new list,
    Save and seal your class extension MP, close your original unsealed class extension MP and open the Sealed copy, Create a second MP to contain the form extension,
    Locate and
    Customize the Service Request form,
    add a new List Picker bound to the property and list you created before, Save and seal your Form Extension MP,
    Import both the sealed versions into your test system, Create a new (unsealed) Management pack in the test system and all your list items to the list you created earlier, test the forms
    and make sure they look right and show the right data, then Export the unsealed list MP, and import all three MPs (the sealed class MP, the sealed form MP, and the unsealed list items MP) into your production system.
    This has the advantage that it gives you a new place to store your custom SR statuses that you can set to be whatever you like, and doesn't break the out-of-the-box activity engine workflows, or the grooming engine that depends on the "closed"
    status.

  • InfoPackage error message "Subsequent update (requests) : Status unknown "

    After running an InfoPackage the status is set to green, but when you look at the Details tab you see an error message "Subsequent update (requests) : Status unknown "  and "With DTP in InfoProvider ZHRPYO00 : Further processed " under it. We did not used to get this error message and don't quite understand why are we getting it now. Could someone explain, please?
    Thanks!
    Luda

    Hi,
    Usually this error could be while loading the DSO or loading DSO first and then to other infoprovider.
    Error message tab at the monitor should give you clear error message where it went wrong. check this tab.
    some time while activating the data this may fail for the DSO object. or some time due to authorization problem to load the data automatically from the DSO to infocubes.
    If possible let me know what is error message.
    Regards,
    Vishwa.

  • Changing leave request status.

    Dear all expert,
    I am trying to customize my leave application wf (12300111) to 2 level of approval. I am facing a problem, after my first approval approved the leave request, the status in PTREQ_HEADER will change to approved. How can i reset the status to any other status so that when the schedule posting job (RPTARQPOST) run, it will not pick up this request which has been only approved by first level manager.
    Thanks
    Regards,
    Bryan

    Hi,
    I remember seeing this same topic discussed earlier, and I think that there were also some solution explained. I just cannot find the topic now - maybe you have better luck.
    Anyhow, I think that you need to create a custom method for changing the leave request status back from approved to sent. Take a look to the existing leave request WF class - there should be a generic method for changing the status - or at least some sort of an example about how to do it.
    Then just place a new step after the approval step, which will execute this new method.
    Regards,
    Karri

  • Request Status Icon missing in Manage screen of RSA1

    Hello Friends,
    I am missing the Data mart status, Request status and Load Monitor Icons in Manage screen in RSA1. I do remember seeing it a few weeks ago. Not sure, if some settings changed the screen format. Anyone have any ideas to bring these icons back? Thanks for your help.
    Regards,
    Raj

    Hi,
    Are you able to see the request or completely blank. If you are having a blank cube then change the date selection and see.
    Even then if you are not able to see data, there is a possiblity that it has been deleted. Go to LISTCUBE and see if you are able to get any data in output.
    Regards,
    Akhan

  • Request status in RED color.

    Gurus-
    I am loading the data from Data Stage to BW.
    First load went thru with out any errors. When Data Stage team scheduled load for second time then I see Red indicator in "Request Status" as well as in "Status" tab.
    When I go to details tab I see RED in "Extraction (messages) : Errors occured", Transfer (IDOCS and TRFC) :Errors occured and "Susseq. Processing (message)".
    When I expand " Extraction (messages)" I see "1000 Records sent (1000 records  received)" in red color.
    and if I expand "Transfer ( IDOCS and TRFC)  "it says "Data Package 1 : arrived in BW ; Processing : 2nd processing step not yet finished "" in red color. all the Info IDOCS are in green color.
    But I see Transfered and added records in mange screen of DSO. Can I activate the DSO by changing the indicator to green from red?
    Pls suggest with ur valuable suggestions..

    Hi,
      In the monitor right click on the data package1 and do a manual update.
    Jaya.

  • REQUEST STATUS YELLOW WHILE MONITOR STATUS GREEN - BI7

    Hellow,
    I try to load data with 0CO_OM_OPA_1, 0CO_OM_WBS_1 into Z cubes which are similar to the business content cubes 0OPA_C11 and 0WBS_C11 respectively.
    ETL is BW3.5 (transfer rule and update rules). When I look at the request in the monitor, I see that everything is green but the request status is yellow and not available for reporting. I can change the status to green manually but this is not a good solution for me.
    By the way the same load works well with te standart cubes.
    I use BI7 but I use BW3.5 business content.
    What could be the reason for such problems?
    Regards,
    Hadar

    Hi Hadar,
    We have exactly the same proble. Have you found a solution to it? I'm using Datasource 0HR_PT_2 to load data into Infocube ZPT_C01 (a copy of 0PT_C01). The monitor of the infopackage is green. There are no errors whatsoever. The status for the request in the Infocube>Manage is set to yellow and the data is not available for reporting. I can set it manually to green, but as you said yourself, it'd be nice to have an automated wway of doing this. Is there any way around this problem?
    Thanks
    Michalis

  • Request Status Red

    After data load from ODS to Cube request status is RED.But data successfully transfered and validated the data,exactly it matching.No where I am getting log also.What could be the problem.But forcibly made it to green.But in production i cant change the QM status.Please valuable inputs
    Rajesh

    Hi,
    If it happens only for this target, go to Mange screen ---> Environment (From Menu) ---> Automatic Request Processing ---> Tick the checkbox that Set Quality Status to OK. This will ask a transport request, collect this into TR and move to Quality and Production.
    If this happens for all systems, make the Extraction Monitor settings in SPRO.
    Hope this helps,
    Regards,
    Rama Murthy.

  • Request Status Stay Yellow

    Hi Expets,
    I am using load 0HR_PT_2.
    Because the load gets warning in the source system the request stay in status yellow
    (HR say all the data is good)
    In the Details tab of the monitor under Extraction i see the warning
    "warnings have appeared when extracting data" (message R3 401)
    And i have to change it to green every morning (because all the data is in received in to the BW)
    how can ignore the warnings or chagne it to green automaticly?
    Or what else can i do?
    Thanks and BR,
    Or.

    Hi,
    In the DTP on the extraction tab you can set the DTP extraction mode to ignore warning and make the request status as green. Once you do this setting your request will become green automatically.
    But I don't know if there is any similar setting in BI 3.5.
    Regards,
    Durgesh.

  • Request status changed!

    Hi,
    in the manage tab of data target when i see the status of the request it is yellow and added records and transferred records has adifference of almost 40000.
    but when i click monitor button, it goes to the monitor screen with following msg
         " request status changed, trigger follow on events? followed by YES or NO push buttons?"
    why this msg is coming though upload is not yet completed?
    Thanks,
    Ravi

    This message indicates that there is some change in the data load between now and ur previous visit. If you choose YES, it refreshes and displays the latest status. If you choose NO, it shows the status of ur last visit
    Hope it helps!

  • REQUEST STATUS

    Hello all,
    I am unable to get request status for reporting. Is there any way to get this.
    provide some information.
    amit

    Hi,
    Firstly your request should be loaded to target successfully and status should be green.
    Then if its an ODS you need to activate it so that the latest request becomes reportable.
    If its a cube and has aggregates you need to rollup the request.
    If there are no aggregates, it will become reportable on completetion of loads.
    thanks,
    JituK