Hello gurus,
I wanted to know how do we maintain early closure in a Holiday Calendar. I have a requirement of early closures for a USA client. In USA a day before the public holiday is an early closure (half day). Eg : A day before the Christmas Day the employees leave early & dont work for the entire day. My doubts are :
1. Can we capture this in a Holiday Calendar?
2. If yes, then is it through Public Holiday Class - 2 = half day holiday?. If yes, then will it not clash with the wroking times. As the working times in the company is 9-5 so if the office close at 3 on a day before christmas its not exactly a half day.
3. Is there any other way we can maintain this requirement?
awaiting help!!
rgds,

Hi,
in the column - Holiday Class : u have marked X in the 1st place, means tht this condition is for holiday class 1
u2022     This is holiday class 0 i.e. not a public holiday
in the column -HolClNxxtDay : u have marked X in the 2nd place, means tht this is for holiday class 2 i.e. half days
u2022     This is Holiday Class 1 i.e. Public Holiday
in the column day : u have X in all places, means the condition is for any of the week days
yes this is for any of the week days
Meaning of above rule is, any working day before public holiday should be marked as early closure through variant 'A'.
Regards,
Lata

Similar Messages

  • Problem in maintaining Public Holiday Calendar

    Dear All,
    I have to maintain Public Holiday Calendar for 2009. For that I have maintained the holiday dates in Change Public Holidays. Please guide me as to how do I assign these holidays which I have maintained to Public Holiday Calendars being used in different PSA's?
    Thanks and Regards,
    Kanupriya

    hi,
    for appearing in the holiday calendar of 2009, the Validity year of ur holiday calendar should contain the year  2009. say,                
    Valid  Fr.year  2008
           To year  2010
    For the day to be a OFF day u have to re-generate the existing work schedule as i mentioned earlier. Only then the new holidays assigned to ur holiday calendar will be taken by the Work Schedule.
    U must give the same Holiday class to ur new holidays (Same that u used to create ur earlier holidays to avoid confusions......)
    Regards
    kiran

  • Public Holiday calendar not to be taken into account for Sick Leave

    Dear All,
    I need help.
    Public Holiday calendar not to be taken into account for Sick Leave.
    Eg -When I employee applies for sick leave, the public holiday in between the dates shouldnt be considered. How can I configure this requirement.
    Please help.
    Regards,
    Poornima

    For that group, you need 2 counting rules:
    - one for Holiday Class 0 (not a public holiday) and Day Work Schedule Class 0 (not a working day)
    - one for Holiday Class 0 (not a public holiday) and Day Work Schedule Class 1 to 9 (a working day)
    If you want, you can add an other one or two for Holiday Class 1 to 9 (public holiday)
    extract from our T556C
    2       1   10 Q      10 Sick leave deduct from quotas (incl personal/spec) XXXXX   X  X    XXXXXXXXXX  XXXXXXXXX X X        XX XX    100.00  100.00              1     1       10              
    2       1   10 Q      11 Sick leave deduct from quotas (incl personal/spec) XXXXX   X  X    XXXXXXXXXX X          X X        XX XX      0.00    0.00              1     1       10              
    2       1   30 Q      10 Special leave with pay (with quotas deduction)     XXXXX   X  X    XXXXXXXXXX  XXXXXXXXX X X        XX XX    100.00  100.00              1     1       30              
    2       1   30 Q      11 Special leave with pay (with quotas deduction)     XXXXX   X  X    XXXXXXXXXX X          X X        XX XX      0.00    0.00              1     1       30

  • Absence Quota Change ( Without Time Evaluation )-Change in Holiday Calendar

    Hi Experts, We have scenario where we need to change the holiday calendar. Add additional holiday. This can be done through SCAL and after that we can generate work schedule through PT01 for the month where the holiday is added. We are not using time evaluation. Our time manangement status is 0 in IT0007. The input I require is how to correct the absence quotas of employees for which they have applied leave for the period where the new given holiday is created. Please advise. Thanks in advance. Regards, IFF

    Hi,
    Standard SAP provides TCode PT_UPD00 for this purpose. It calls program RPTUPD00 which creates a batch input session for revaluating absence and attendance records. You can use this program to resave all the leaves which overlap the given date which is now a public holiday.
    I hope this information is helpful for you and resolves your query.
    Thanks and regards,
    Vivek Barnwal

  • ICal 'Show Holidays calendar' not showing holidays in Australia after upgrading to Yosemite.

    Hello, I had been in Italy before moving to Australia and I had set Show Holidays calendar in iCal to display Italian holidays. When I've moved to Australia, I've changed the regional settings to Australia and therefore iCal was showing Australian holidays. After I've upgraded to Yosemite, I can't see any holidays anymore. I tried to uptick 'Show Holidays calendar' and reboot Yosemite, then tick it back and it is still not working for Australia. if I change my regional settings for instance for Italy, it works. It just refuses to display Australian Holidays so for now I'm forced to use Google calendar subscription for public holidays.
    How can I restore the iCal 'Show Holidays calendar' ?

    Hi guys,
    I had this problem too. I resolved it by going into System Preferences  > Language & Region and making sure the primary language was "English (U.K.)" under primary languages (i.e. at the top of the list of preferred languages).
    I always had this set before, but I think upgrading to Yosemite changed this setting to "English" (without the "U.K.) which I guess is a generic "countryless" language. I believe the holidays setting in the calendar needs to know which country's holidays to display.
    Hope this helps this waiting for a fix...

  • How to create a holiday calendar link on ESS portal

    Hi,
    Can anybody help me how to go about having holiday calendar link on ESS portal.
    Regards,
    Prasad

    Why do you need the whole Holiday Caledar in ESS?
    You can create the Iview of th Tcode SCAL

  • How do I put a Jewish holiday calendar on my iphone calendar?

    I want to insert a Jewish Holiday calendar on my iphone calendar. I already did it with the US calendar but I am having a hard time finding the server address for a Jewish Calendar.
    Thanks

    Bear with me because my system is Italian, but we'll work it out together: iCAL will provide you with myriads of calendars, even those of football team schedules in Oklahoma.
    In my system, I go into iCAL, click on the menu at the top "Calendario" ("Calendar" obviously) and study the roll-down menu. I found "Trova iscrizioni" which might simply be something like "find calendars" "find entries". In any case, it is the item at the bottom of the roll-down "Calendar" menu.
    Be prepared for a bit of scrolling, unless there is an index I missed.

  • Can we manually select the Holiday calendar in iOS 7.1?

    As per my title, is this possible without changing the regional setting? As I'm using Singapore as my regional setting but I'm from Malaysia thus the holiday calendar is showing SG by default. Is there any way to change it to Malaysia without changing the regional setting? Else if I change the regional setting it will affect my language and also the formatting.

    Switching to day view doesn't crash calendar but I can't launch the calendar app in iOS 7.1 (on my iPad 2) if synch is in and it was last in day view. It crashes on launch.

  • Error While Creating the holiday Calendar

    hi Gurus
    This is in regard to the Holiday Calendar When iam tring to create it its showing the error as "A date was Already entered for this year" but when i try to assign a different date for the public holiday also its not taking .. and when i chkd the List of Public holiday its not showing the holidays for the same day
    pls suggest
    Rgds
    M Bharath

    HI Bharath,
    First delete the holiday(which u want to delete ) in the list of holidays calender ID.
    Than Create the same in the holidays than again assign the to your Holiday calender ID.
    Hope this will help you
    KRC

  • Error while accessing public holiday calendar

    Friends,
    Well when creating a work schedule for the year 2008 (practice mode - at home) i am getting the below message..
    I checked all the configurations and no where i mention about 2009. Any tips and suggestions.
    Error while accessing public holiday calendar
    The function module HOLIDAY_CHECK_AND_GET)INFO has generated an error

    friends the problem still exists..
    i created a new calender, new dws, pws, bws.. but again the same error comes in play.
    Friends,
    Well when creating a work schedule for the year 2008 (practice mode - at home) i am getting the below message..
    I checked all the configurations and no where i mention about 2009. Any tips and suggestions.
    Error while accessing public holiday calendar on 20090101
    The function module HOLIDAY_CHECK_AND_GET)INFO has generated an error

  • Error while accessing public holiday calendar on 20120101

    Dear All,
    When I'm posting PL(Personnel Leave) against 31.12.2011 it is working fine but If I'm posting a Sick Leave against 31.12.2011 or CB the error is coming like "Error while accessing public holiday calendar on 20120101".
    Please suggest what to do.

    Dear All,
    When I'm posting PL(Personnel Leave) against 31.12.2011
    it is working fine but If I'm posting a Sick Leave against 31.12.2011 or
    CB the error is coming like "Error while accessing public holiday calendar on 20120101".
    Please suggest what to do.
    the error clearly saying that you dont have holiday calendar for 01.01.2012,, so please change it using PT02 to avoid the error.
    then you check what exactly system is doing.
    you have to create a wsr with one month extra validity than the exact periods required to avoid the future errors as you are getting now.
    system always takes one month extra validity it is standard functionality.
    regards,
    mohammed

  • Error while accessing public holiday calendar on 20100101

    Dear Gurus.
    When i was created Work Schedule TC-PT01
    Error Showing
    "Error while accessing public holiday calendar on 20100101"
    Message no. P2518
    Diagnosis
    The function module HOLIDAY_CHECK_AND_GET_INFO has generated an error.
    Please Advised
    Regards
    MHPO

    Hi
    As Surisetti told that, that public holiday might not created in that year. So check the same in SCAL and again re-generate the work schedule.
    Thanks & Regards
    Bharathi

  • Problem with holiday calendar

    Hi Experts,
    I need to configure different holiday calendars for worker and managemnet employee group in the same personnel area and sub area.I am not able to configure this as under "Set work schedule rule" node we can specify only holiday calendar per personnel area and sub area.
    Please let me know if there is any way to achieve this.

    Thnaks Sikindar and Sheetal for you replies.
    Actaully i was talking about view V_001P_M. in this view when we maintain holiday calendars for personnel area and sub areas, infotype 0007 will show (in search help) only those work schedule rules which has got the same holiday calendar in it.
    example:
    I have already created two calendars say ZM for management and ZW for workers for personnel area (say) MUMB and personnel sub area (say) 0001. i have assigned ZM holiday calendar in V_001P_M for PA MUMB and PSA 0001.
    I have also generated two WSR with ESG grp 1 from Management and 2 for workers. WSR for management is generated with ZM calendar and for workers with ZW calendar.
    now when i got to infotype 7 to assign workschedule rule for a worker in same PA and PSA it display only 1 workschedule rule in the serach help which is for management (coz i have mentioned ZM in V_001P_M). Now how to assign woker's workschedule rule?

  • No 'Holidays' Calendar

    I want to enable the 'Holidays' calendar in Calendar on my Mac Pro. I opened Preferences>General and both "Show Birthdays Calendar" and "Show Holidays Calendar" are already checked. I have a 'Birthdays' calendar, but no 'Holidays' calendar. I've unchecked and rechecked the option, to no effect.
    The 'Holidays' calendar appears in Calendar on my iMac, so I checked there to see what was different, but the settings are the same. On the iMac, I unchecked "Show Holidays Calendar" to see if the 'Holidays' calendar disappeared and it did. Then I rechecked the box ... and the calendar didn't reappear. I now don't have a Holidays calendar on my iMac either, and it looks like some upgrade has broken this functionality.
    I found 'New Calendar Subscription' in the File menu, but it wants a URL and I don't know the URL of the 'Holidays' calendar.
    Can anyone help me out of this mess? It's the Australian holidays calendar I need.
    Thanks in advance,
    Steve  = : ^ )

    Thanks, I found an Australian Holiday's calendar there.
    You're right that it's not the 'Holidays' calendar that I previously had. That was at the bottom of the Calendars list (with the Birthdays calendar), under 'Other'. This new subscription puts a 'Holidays' calendar in the 'iCloud' section.
    However, it works and appears to be up to date, so thanks!
    I've marked your answer as helpful, but won't mark the problem as solved, as there's still the problem of the non-appearance of the 'Holidays' calendar with the "Show Holidays Calendar" checked. I'm interested to see anyone else can uncheck and recheck "Show Holidays Calendar" without losing the calendar. Did you try?
    Thanks again,
    Steve  = : ^ )

  • Holiday Calendar requirement

    Hi,
    Need your inputs to achieve a following requirement:
    In a year or month, most of the Wednesday's are holiday however few of the Wednesday's will be working day. So we want to know if there is any chance of changing the setting in Holiday Calendar to declare wednesday as working day, at that point of time (that is, when we come to know this week, that next week wednesday is a working day).
    Welcome your suggestions.
    Surya.

    Hi,
    I would suggest you to use the functionality of special days for this purpose.
    Create two selection rules for day types - 21 and 22.
    They should be similar to the date type rules currently assigned to these WSRs.
    Delimit the WSRs and assign them from the effective date.
    Go to Table T553S and assign the relevant date for rule 21 and the relevant date for 22.
    Generate the WSRs and you will have the public holidays assigned for these days.
    Thanks and regards,
    Vivek Barnwal

Maybe you are looking for

  • HP Officejet 6700: A problem with the printer or ink system.

    I'm not sure what the problem is anymore since I've bought new cartridges and applied them carefully and correctly. My printer uses 933 for CMY and 932 for Black. Interestingly, it gives me this error when I installed the black cartridge. I don't und

  • Preserving aspect ratio 16:9

    I've placed several Flash videos on a Web site, all 4:3 standard definition. All look fine. I have one video that's 16:9 widescreen high-definition. When I try to place it on the same site (using the same HTML snippet code as the others), much of the

  • User Agent issue - Always defaults to non-Safari user

    If I try to access my www.me.com site, I am told I am using an unsupported browser. However, I am using Safari 5.0.3 on a mac running 10.6.5. When this happens, I have to go to Safari Prefs/Advanced and activate the Developer Menu, then choose either

  • Turn off scroll pane component pt2

    hello kglad sorry, responded by email and it left off message. i guess my answer would be by code, but dragged from component panel. one unprofessional, uneducated workaround was putting a black box behind the text/graphics in other frames so it woul

  • Invoice creation failure

    Good morning, In SUS, a invoice is created without problem but the idoc INVOIC-INVOIC01 fails on R/3 with the message "A company code cannot be determined for LS <partner>" I try to map the idoc like the diagnosis says but the error is the same. Im b