ECC 6.0 Upgrade - new functionallity
Dear Experts
Recently we went upgrade from 4.7 EE to ECC 6.0 can any one share the new functionallity in ECC 6.0
new functionallity in ECC 6.0 ( SD, MM , LE , CS ) module
thanks and regrds
kumar
Functionality Changes SAP Version 4.7 (vs) ECC 6.0
1. PURCHASING
1.1 Reference Funds Reservation from PR/PO Going Into Stock(5.0)
1.2 Field Status for PR/ PO Without Account Assignment Categories(5.0)
1.3 Requirement Prioritization(6.0)
1.4 Mass Maintenance of Outline Agreements(6.0)
1.5 Availability Check for Stock Transport Order(6.0)
1.6 Archiving Program(6.0)
1.7 BAPI's in Purchasing(6.0)
1.8 BADI's In Purchasing and Inventory(6.0)
1.9 Version Management(4.7)
1.10 Accessibility Barriers Removed: Purchasing Lists Converted to ALV Grid Control(4.7)
1.11 Automatic Generation of Purchase Orders from Requisitions in New Interactive Design(4.7)
2. INVENTORY MANAGEMENT
2.1 New Reference doc "Material Document" added in the MIGO Transaction(5.0)
2.2 New Executable Actions added in MIGO Transaction(5.0)
2.3 New Movement Types 107 Introduced(6.0)
2.4 New Movement Types 109 Introduced(6.0)
2.5 Customizing Transaction OX18 Replaced by View(6.0)
2.6 Customizing Transaction OX01 Replaced by View(6.0)
2.7 Customizing Transaction OX17 Replaced by View(6.0)
2.8 New field "Plant" field introduced in MIGO Transaction(5.0)
2.9 Setting up u201CCopy Account Assignment Fieldsu201D(5.0)
2.10 Stock Overview (MMBE)
2.11 Pick-Up List: Batch Where-Used List Display in MB56(5.0)
3. EXTERNAL SERVICES
3.1 Putting Service Items in the Purchase Order On Hold(6.0)
3.2 Service-Based Commitments in Purchasing(6.0)
3.3 Invoice Before Goods Receipt for Services in Purchasing(6.0)
4. LOGISTIC INVOICE VERIFICATION
4.1 ERS Invoice Numbering(5.0)
4.2 Automatic Settlement of Planned Delivery Costs(6.0)
4.3 Report RMMR1MRS(6.0)
4.4 Variance Type as Sort Criterion for Invoice Items(6.0)
4.5 Prepayment of Invoices(6.0)
4.6 Invoice Verification in Background(4.7)
4.7 New Report: Display List of Invoice Documents(5.0)
Similar Messages
-
SAP R/3 4.6 C to ECC 6.0 Upgrade using CU &UC method- Unicode conversion
Basis Gurus
I am working on upgrade from R/3 4.6C to ECC 6.0.
ECC 6.0 upgrade completed( still in non Unicode). Now I am in the process of Unicode conversion.
I have used following methods for the upgrade.
1. Combined Upgrade & Unicode conversion(CU & UC)
2. Resource minimized( as I am doing it in Sandbox).
As I understand I need to perform the DB export and Import now for the unicode conversion.
According to the Upgrade document, First I need to run Export using R3load in ECC6.0(Non unicode)
and then install Unicode system and import the same data file.
My understanding was, when I choose, Resource minimized, I need to run Export and import
in the same system.
Can you please help me , whether I need another Unicode system for import ??
GrahamHi,
Dont get confused with upg strategy and unicode conversion.
In general Upgrade strategy (either downtime-minimized/resource minimized)
In unicode conversion you have export/import(exp/imp) of data concept
In CU&UC approach you have to do in a streach to complete migrate from old release to new realease ECC 6.00.
Using database independent (sapinst only) or Using database dependent (migration monitor or Distribution monitor)
It can be done in 2 ways.
If you dont have addtional server for unicode conversion
1)you can either do exp on same hardware and take bakup and do import using the exp dump.
2)Do exp on one server and prepare your target empty database on another server and complete imp of data.
Hope this is clear.
Regards,
Vamshi. -
ECC-600 EHP4 upgrade with VIRSAHR 520 700 - PREP_EXTENSION/ADDON_QCALC
Hi
We are getting following error at phase PREP_EXTENSION/ADDON_QCALC in the ECC 6.0 upgrade:
3 ETN256 You want to install the following add-on components:
3 ETN248 Component: "VIRSAHR" rel. "520_700", Support Package
level: "0" (component type "A")
3 ETN248 Component: "VIRSANH" rel. "520_700", Support Package
level: "0" (component type "A")
2 ETN085X"2. Adding Add-on Installation Queue" " " " " " "
3 ETN262 Calculating queue part for add-on "VIRSAHR" rel. "520_700"
3 ETN490 Use the Add-On installation package "SAPK-523EXINVIRSAHR"
(type &4"AOX") for Add-On &2"VIRSAHR" rel.&3"520_700"
3 ETN245 The following import prerequisites of OCS Package "SAPK-
523EXINVIRSAHR" have not been met:
3 ETN264 In the (alternatively) Requirement set "01":
3WETN491 Required software component "SAP_HR" rel."600" is not installed2WETN543 OCS package "SAPK-523EXINVIRSAHR" does not match the current
software component vector
1 ETN214X."**************************************************"
We have alreacy checked note 1002147, which clearly states that we have to include SAPK-523EXINVIRSAHR in the upgrade. SAP_HR is part of the upgrade.
We have included SAP_HR and other Support Package as per the queue generated by Solution Manager, but we did not include VIRSAHR & VIRSANH Packages until we got to this phase. We then included these support packages in eps\in directory, but we are now getting this error now.
Any ideas?
Regards
ChanduHi
This is what the solution provided by SAP Support:
Quote:
we have finally found the problem, it's a bug in the package upload
functionality used by the upgrade. The consequence of this bug is that
Support Packages whose EPS files (.PAT files) have a certain string in
the name, namely the string 0000000 after the _ and before .PAT
extension, are not properly uploaded to the ABAP system and hence are
not visible or known to the upgrade.
This bug will be fixed in the next upgrade tool fix, but in the meantimeyou can use the following workaround:
Check your EPS/in directory after the CAR/SAR Archives of the SPs are
extracted and rename all .PAT and .ATT files, which have a name like
*_0000000.PAT (or *_0000000.ATT), by changing the string 0000000 to
9000000. For example, for the VIRSANH SP SAPK-52302INVIRSANH rename the
file VS30020106486_0000000.PAT to VS30020106486_9000000.PAT
Afterwards, the upgrade will upload the informations about the SP
properly and the SP can be included into the upgrade.
Files:
31/01/2007 07:32 329 VS30020106486_0000000.ATT
31/01/2007 07:32 554,073 VS30020106486_0000000.PAT
If these two files are renamed to e.g.
VS30020106486_9000000.ATT
VS30020106486_9000000.PAT
the affected VIRSANH SP2 is uploaded correctly by the upgrade
functionality and the SP inclusion of the VIRSANH SPs works.
Sorry, as of now I cannot promise you a date when the tool fix will be
available. I have found this bug only today in the evening (german time)and will discuss this with the responsible colleagues tomorrow.
Afterwards, I will know more...
Unquote:
Hope this helps. We have decided against upgrading to 530_700 as it will involve upgrading GRC system and also new version has lot of new functionalities, which we like explore it after the ECC upgrade.
Also, I would not suggest deleting VIRSAHR as all the config and customising done for VIRSAHR will be lost.
Regards
Chandu
Edited by: Chandu Cheeti on Jan 17, 2010 11:19 AM -
4.6 C to ECC 6.0 Upgrade Project Timeline Sheet in MPP format
Dear all,
We are now proposing our customer for the 4.6c to ECC 6.0 Upgrade.
Our customer is currently in 4.6c/oracle 9i/HPUX 11 i. He wants to move to ECC 6.0.
If you have the project timeline for the above Technical Upgrade, can you pl send it to me.
If you don't have in MPP format atleast send me the Work Breakdown structure with timelines.
I shall modity the same to our customer and submit
Thanks & Regards
Senthil
[email protected]Preparation Phase* 6 days
Kick Off Meeting 1 day
Upgrade Project Procedures Preparation 1 day
Prepare Upgrade Project Plan 1 day
Technical Requirements Assessment 3 days
Assess Training needs of Key-users & End-users 1 day
Prepare Detailed Basis Activity List for DEV, QA & PRD 1 day
Business Blueprint Phase 6 days
Develop System Landscape Upgrade Plan 1 day
Functional Requirement Checklist 1 day
ABAP Development check list 1 day
Develop detailed Training Procedures & Documentation for Key Users & End Users 1 day
Identify Testing Scope & Scenarios 1 day
Identify Authorizations Conversion to Roles for SAP ECC 6.0 2 days
Develop Documents as per Basis Activity List 1 day
Develop Authorization Matrix for Activity Groups to Roles Conversion 2 days
Prepare Upgrade Deliverables Checklist 1 day
Realization Phase 28 days
Installation of Solution Manager 3.2 System 1 day
Creation of New Development System for Upgrade Project (Homogenous System Copy - PRD) 2 days
Upgrade to AIX & Oracle 10g, SAP ECC 6.0 on New Development Server 3 days
Upgrade Frontend Software 4 days
Perform SPAU & SPDD Corrections 5 days
Perform ABAP Development & Corrections 10 days Perform Authorizations Conversions and corrections after upgrade 8 days
Perform Upgrade Testing for each Application Module 7 days
Perform Unit & Integration Testing 6 days
Perform Training to Key Users & End Users (Generic & Specific) 3 days
Upgrade to AIX, Oracle 10g, SAP ECC 6.0 on Quality System 1 day
Homogenous System Copy of PRD to New Quality & Upgrade to AIX, Oracle 10g & SAP ECC 6.0 2 days Perform Testing in Quality System 3 days
Testing by end users on Quality System 1 day
Production Realization & Go-Live Phase 6 days
Upgrade to Production System Operating System to AIX (after close of business hours - 23:00) 1 day
Oracle Upgrade to 10g (after close of business hours - 23:00) 1 day
SAP Release Upgrade to ECC 6.0(Downtime Minimized - Downtime occurs in non-business hours) 2 days
User Acceptance Testing 1 day
Production System Go-Live 1 day
Post Go-Live Support 14 days
Post Go-Live Support 14 days Note: This is high level plan subject to change during Business Blue Print Phase 0 days
This is taken from a post in Ittoolbox, May be this is generic. Hope you can tailor this to meet your requirements. -
DB Migration and ECC 6.0 Upgrade
I have a number of questions, we have a SAP R/3 4.7x200 landscape that is currently Windows 2003 and SQL2000 both 32 bit, we want to do the following, move to Windows 2003 and SQL2005 64bit, perform a Unicode and ECC6.0 Upgrade.
here are the steps I am planning on new hardware
1. Migrate to 64bit
-install 64bit OS and SQL2006 64bit on new hardware
-export db from current 32 bit and import into 64 bit system
a. I am confused, I have seen threads where it appears this was done in house, do we need an SAP certified person to complete this task, this is a hetergenous copy? Note 82478
b. can we do this inhouse if we follow the SAP documentation and checklists provided and have their signoff with checks
- Run tests and then confirm process before real migration
2. Perform Unicode Upgrade
- run this on sandbox, test and verify
3. Perform ECC 6.0 upgrade
- run this on sandbox a no. of times confirm
- freezing development and starting with DEV (this is a small landscape, we can do this)
p.s can steps 2 and 3 be combined in one step, I have broken that out, to in my mind make it simpler to fix if anything breaks.Hi,
DB Migration
1. MS SQL Server 2000 is based on BIN collation and MS SQL Server 2005 is BIN2 collation. SO you need to first convert BIN to BIN2 collation.
Note 960769 Windows Migration from 32bit to 64bit x8664
Note 799058 - Setting Up Microsoft SQL Server 2005
2. can steps 2 and 3 be combined in one step?
Yes. check with link http://service.sap.com/erp-upgrade
Regards,
Srini Nookala -
ECC 6.0 UPGRADE - BW 3.10
We are planning to upgrade our source system from 4.6C to ECC 6.0. We are on BW 3.10 ( But planning to upgrade to BI 7.0 once after ECC 6.0 upgrade)
Would like to know,
1. Do we need apply any plug-in requirements to accommodate the ECC 6.0 compatibility?
2. Will the existing BW 3.10 work without any issue with ECC 6.0?
( We are not going to do any change with new Business content available with ECC 6.0)
3. What are the other precautions, we need to take in order to work BW 3.10 with ECC 6.0?
Advance Thanks.refer replies here:
Re: ECC 6.0 Upgrade with BW 3.5 -
ECC 6.0 Upgrade from 4.7 - EDI Interfaces
Hi Gurus,
Need your inputs on what are the precautions to be taken during ECC 6.0 Upgrade related to EDI Interfaces. with SAP upgrading from 4.7 to ECC 6.0, do you see any precautions need to be taken considering the middle ware involvement. Also, is there any changes in IDOC Structures in ECC 6.0 which my cause issues related mapping with middleware.
Please suggest.
Thanks & Regards,
C.L. Narasimhan "CLN"Hi,
generally, a release upgrade, delivers new idoc/message types or new releases of existing idoc/message types.
So, taking this in mind, you shouldn't have problems for the mapping of the messages, because the versions of the basic idoc, once released, cannot be changed.
You might have some application problems related to the inbound interfaces, but this is part of the game...the testing phase will highlight whether the problem exists.
A known problem is that the upgrade removes all the customer specific entries in the system table EDIFCT.
Further details are provided in the OSS note [https://service.sap.com/sap/support/notes/865142]
Regards,
Andrea -
ECC 6.0 Upgrade - FI Posting (Payroll)
Hi,
We have gone for ECC 6.0 upgrade and face problem with FI Postings(Posting not cleared). We found out that in the new version there is a new node that got added up where we need to add all US taxes(Payroll US -> Posting to Financial Accounting ->Define WT posting attributes).
How can i find which all wage types are US tax related. I know there is one processing class 72, which define Employer / employee tax, but is there any other way i can find out.
Thank you
SreejaHi Ted,
I am talking about GB payroll, so we have to defnitely maintain the tax wagetypes in the new table V_T7US3PRTXSYMKO. Apart from that do we need to do any other settings in FI. Because it is showing the Profit center not filled.
We have also maintained the v_t52swcodist .
-Swetha -
Screens not working in ECC 6 after upgradation from 4.6c.
Hi,
The custom developed screens which where developed in 4.6c version is not working properly in ECC 6 after upgradation.Do i have to make any more changes for this .? If anyone have an idea please help me in this issue.The custom developed things are an extended functionality we have done to r/3.
Regards,
jinesh kumar c.Hi,
Check the Transportatation Logs in STMS for the programs/screens and check whether they are successfully tranported or not?
Because some times we get Dynpro errors for transportation of the screens.
Reward if useful.
regards,
Anji -
Error in WBS Element Hierarchy load after ECC 6.0 Upgrade
Hi All,
After ECC 6.0 Upgrade in R/3, we are doing test load in a Test server. While doing, we have encountered an issue with 0WBS_ELEMENT Hierarchy load. The message in the monitor is like below.
"Node ID 00014240 has not been included in the hierarchy
Message no. RH207"
When I run the same hierarchy in another system which is not upgraded , it works fine.
Anybody has faced similar kind of issues and can throw some light on this issue?
Thanks,
MohanTry activating the Heirarchy in R/3 and re-trigger the load, error is very specific to structure of the hierarchy. there is a possibility that this Hierarcy could have got inconsistent after the upgrade.
Thanks,
Amit -
like i explained in question,before i upgrade newer version of firefox.i can read sinhala(sri lankan language) words.but after i cant see.but if i use windows internet explorer i have no problems.........plz help because firefox is my favourite.
I assume that you have installed the fonts.
For that site you need Sandaru Normal
*http://groups.google.com/group/sinhalacasting/web/sinhala-support
You will have to disable downloadable fonts to make Firefox 5 use a locally installed font.<br />
That will however effect all pages that use downloadable fonts.
* http://www.google.com/webfonts?subset=latin Google Font Directory
You can set the pref <b>gfx.downloadable_fonts.enabled</b> to <i>false</i> on the <b>about:config</b> page.
To open the <i>about:config</i> page, type <b>about:config</b> in the location (address) bar and press the "<i>Enter</i>" key, just like you type the url of a website to open a website.<br />
If you see a warning then you can confirm that you want to access that page.<br />
You can use the Filter bar at to top of the about:config page to locate a pref more easily. -
i upgraded new software onto my iphone 4 however it stopped syncing and said error so when i tried to access my phone the itunes USB was showing in my phone screen and now i cannot access my phone
When it stopped and said error, what was the error? You are saying that you disconnected the phone from the computer and all you see is the USB showing on the phone? Then you need to reconnect to the computer and restore the phone.
-
I using 4s and upgrade new version IOS8 but my unit is very slow why?
I using 4s and upgrade new version IOS8 but my unit is very slow why?
And how I can get lower version. I need to be lowerversion because IOS7 is very smooth on my unit.
-
Load balancing after ECC 6.0 upgrade
Hi
I we this configuration on ECC 6.0 upgrade:
SAPGUI 7.10
SAP_BASIS 700 Patch level 15
SAPportal ESS
Webdispatcher Installed
Internal ITS
Single sign-on
Can somebody assist as with identifying the problem with load balancing (PUBLIC) E.g. When running ESS remuneration package via the Sapportal. we have configured ITS-Based GUI Services on transaction SICF for customised ZESS_PZ11PDF service.
When we have load balancing group on the load balancing does not work, because I see somebodyu2019s payslip
but when using one app server I see my own payslip. Please help.Hi PR,
Please take a look at the following link:-
http://help.sap.com/SAPHELP_NWPI71/helpdata/EN/28/75153a1a5b4c2de10000000a114084/frameset.htm
"You can only use the SAP message server for HTTP load distribution if
the browser is the direct client of the message server. If another
component lies between the client (browser) and the message server, (for
example, the portal), you cannot use the message server to distribute
the load."
When using the External ITS you could balance the load using the message server and logon groups. In 700 this functionality is not present if there is not a direct connection to the client (Firefox or IE). So you will have to install the webdispatcher to balance the load.
Hope this helps
Michael -
Hardware requariment for ECC 6.0 upgrade from ECC 5.0
Hello
I am on ECC 5.0 with oracle 9.2.0.7.I need to upgrade this to ECC 6.0.
I have already implemented MM,PP,FICO,QM and HCM.My current data base size is 900GB.This has 30GB monthly growth.
With this ECC 6.0 upgrade i am planing to implement PM,EP.
I know converting none Unicode system to unicode system is required some more hardware resources than the none Unicode.
Some document says 40-60% more disk space and 35% more processing speed from current system.
Can any one give me the correct information about the hardware requirement for ECC 5.0 to ECC 6.0 upgrade.
Thanks
RoshanthaCheck with the Links
https://websmp102.sap-ag.de/sizing
https://websmp208.sap-ag.de/quicksizer
http://www.4soi.de/
http://www.easymarketplace.de/
Kanagaraja L
Maybe you are looking for
-
Function DYNP_VALUES_UPDATE not working in PBO
Hello, I have a field 'Risk Category' whose value I need to change upon an action. The action is controlled through a button on the screen. For e.g: if the action is 'Update Credit Info', when the user chooses this action, it takes him to another loc
-
Getting a Filename from a Directory Structure
Hi, Our client will be sending us a Fixed Length file via FTP, each month. That file will be in a specific folder, but we will not KNOW that filename, The client doesn't want to put an header record in the file with the filename information... Is the
-
My Library has ten more songs than my iPod. How can I find out which songs are not syncing? I recently had to purchase a new hard drive. Because the size of my music collection exceeds 140 GB, I stored all of my music on a separate external hard driv
-
Travel Display Form: Error while determining the form function module
Hi, In Travel Reqeust (ECC6/ESS) when i click the Display Form after raising the Travel Request it shows the error "Error while determining the form function module" Can anyone have idea on this? Regards, Boobalan
-
Map qmap = new TreeMap( //some initialized Map); Iterator faqs = qmap.values().iterator(); int count=1; Map params = new HashMap(); while(faqs.hasNext()) { params.put("question" , faqs.next()); params.put("qid" , topic + "_" + count); count++; my que