ECC 600 - Cost Estimates for Consigned Material

We are in ECC 600and planning to implement Consigned Inventory in short time. However I am stuck with Inventory revaluation for consigned material.
Consingment Flow: Vendor ship these items against standard PO at zero price. At the consumption pricing is captured from Purchase info records.
Material valuation: We are using valuation variant 001 Planned valuation - mat. with
<b> Primary Strategy Sequence            </b>
Planned Price 1             
Valuation Price 1 Based On Co
Price from Purchasing Info Re
Sub-Strategy Sequence with Purchasing : Strategy Sequence                 
Purchase Order Price via Condition
Gross Purchase Order Price        
Effective Price from Purchase Order
However when I try create cost estimate I am getting following error,
" No price could be determined for material/batch <......>/ plant <..> "
Any suggestions.
Thanks
Uday

Thanks for the quick response. I did maintain Purchasing info record using ME12. We do see pricing information at the time Production order backflsh. However contract and PO has no pricing information. Therefore initial GR is created with zero price. However at the time consumption against prod order, consignment material gets price from the Purchase info record. Bur consumption documents are not linked back to PO.When I try to cost these material using CK11N, SAP gives following messages,
Msg.typ Material Plnt Area MsgNo Message Text
I 1000 CK 037 Lot size 1 EA taken from costing view
I 1000 CK 776 No valid source of supply found for material plant 1000
E 1000 CK 465 No price could be determined for material/batch / plant 1000
I 1000 CK 361 Value of costing item 00001 in itemization is 0
E 1000 CK 240 Cost component split costed with value of zero
Any clue.
Thanks,
uday

Similar Messages

  • Error when Create Cost Estimate for Material using CK11

    Dear Experts,
    I have a material ABCD which is FOC parts:-
    1) Procurement type: F
    2) Special procurement type: Z (at first, it was wrongly entered as B. I changed special procurement to Z & the message 'The procurement type of the special procurement type is E' displayed but I still can save & system allowed it).
    3) Standard price is 0.00 as this is FOC.
    Firstly, I run CK11 for material EFGH which is the parent of material ABCD.
    This time, the material ABCD has special procurement type B. I received error messages:
    1) No price could be determined for material ABCD in plant xyz,
    2) Cost component split costed with value of zero,
    3) Cost estimate for material ABCD in plant xyz is incorrect.
    Then, I changed special procurement type for material ABCD from B to Z and run CK11 again. Still the same error occurred.
    Could someone advise me how to run CK11 without errors.
    Thanks in advance!

    I don't know if B and Z are really the name of your special procurement keys or you are just using them as examples.  Either way, the special procurement key is critical for determining how your material is valued.  It is used for such things as stock transfer from other plant, subcontracting, and consignment processes.  Can you tell me how these special proccurement keys are set or what you want to use these keys for.  You can find the configuration for these key under menu path Controlling - Porduct cost controlling - Product cost planning - Material cost estimate with quantity structure - Settings for quantity structure control - Master data - Check special procurement types.
    thanks,

  • Error reading material cost estimate for sales order (KE292)

    Dear All,
    I have an issue with billing. we are posting july month transactions, the material cost is maintained through MR21. When releasing billing document for accounting we are getting error message like"Error reading the material cost estimate for sales order "11"
    Message no. KE292
    Diagnosis
    In Profitability Analysis (CO-PA), the system tried to valuate item 000010 of sales order 11 by reading the corresponding product cost estimate.
    However, no product cost estimate could be found for this sales order item.
    The system accessed product costing for product AMLFP011011XX00P using costing key YB3 as defined in the
    CO-PA Customizing settings.
    System Response
    The system cannot process the document any further.
    Procedure
    Check your Customizing settings."
    We cross checked with other client as a current date and we ran cost estimate through CK40N with same material. and we posted entries. Here it is working fine. but in above process it is not working. Can you pls guide me where i missed.
    Regards,
    Nagaraju,

    Hi,
    When the Costing Key is assigned to the material types in the COPA customizing, then system expects Cost estimation when billing is released to Accounts.
    If you dont run cost estimation but update the material master through MR21, system will not accept as in the Costing key configuration you must have selected the Current Standard price field for the valuation.
    Hence, try to run cost estimation and then do releasing.
    Thanks & Regards
    Ravi Kumar

  • Cost Run for Raw Material taking Standard Price instead of Moving Price

    Hi all,
    We ran a material costimate with normal components FG>SFG>RM.  The RM price Control is set to
    V (Moving Average Price) and for SFG & FG it is S(Std. Price).  After we run CK11N, the price for
    RM in Material Master changes as per Moving Price.  We found that the RM Component is
    costed based on Standard Price and not on the previous cost run Moving Average Price.  After
    certain period, if we again do cost run, the sytem is again picking up the standard price for costing
    not the revised Moving Price.  We have checked the Valuation Variant in the Costing Variant, where the strategy given is 1. Moving Average Price 2. Standard Price.  We also tried to change the
    sequence as 1. Price as per Purchase Info Record 2. Moving Average Price and 3. Standard Price and
    also 1. Standard Price and 2. Moving Average Price.  Our requirement is when we run the cost estimate the raw material has to pick the price of previous moving price stored in the Material Master.  Kindly tell us where to set the indicator.
    Thanks,
    Sadashivan

    Hi Srikanth,
    Problem solved.  I checked the sequence in Valuation Variant and modified in Valuation Variant for Plant which I have not set previously and now the system is working correctly.
    Thanks,
    Sadashivan

  • How is cost allocated for consignment item ?

    Hi Gurus,
    How is cost allocated for consignment item ? Is it based on inforecord price ? Or is it based on the split valuation price ?
    Detailed and answers appretiated. Points will be rewarded suitably.
    Thanks,
    Anil

    Hi All,
    Thanks for your help. I will award points.
    Another question>>>>We want to move consignment material to other location. Now this can be - a plant few miles away or another country.
    Material price in this case will be inforrecord price or price in material master MAP.???
    Thanks,
    Anil

  • Costing run for a material with alternative BOM

    Hi Friends,
    My requirement is to have product costing for a material with 3 different BOMs, in CK11N i can change the alternative BOM number to have costing run for 3 differesnt boms, but in ck24 how to proceed, My client requirement is such that the standard price should be the average price of the costing run from 3 different boms, and they are not interested in manual price change in MR21
    Regards,
    Arun Kumar R V

    Hi Arun,
    You can have a Standard cost estimate based on only one of the alternative BOM and Routing. This alternative is selected based on the business ie., whichever alternative is generally used in production frequently. This will be the std cost and whenever you do the production using the other alternatives, the difference in cost will be captured as Variance.
    There is no option of having average or cost estimate for each alternative at the same time.
    There is absolutely no use in maintaining price in MR21 for an in house produced material, since during Prod Order process the planned costs will be arrived at based on the quantity structure of BOM & Route only.
    Thanks & Regards,
    Vijaya Bhaskar A
    Edited by: Vijaya Bhaskar A on Jan 7, 2009 8:57 AM

  • How to run cost estimate for the purchased materials to updt Pln prices?

    Hello Experts,
    Can any body explain how to upload the plan prices through cost estimate in purchased materials..
    Regards,
    Ravan

    Hi Ajay,
    Thank you for reply
    I do agree update plan prices through LSMW or Manually in Material Master
    I am trying to  update planed price1 and 2 through cost estimate, for this I configured like below
    New costing type:G1
    here I selected for prices update as "prices other than standard price" and valuation view as Legal valuation
    New valuation variant :GG1
    here I given MAP as a first priority in strategy sequence
    Regards,
    Ravan

  • Cost estimate for Finished goods

    Hi SAP guru
    While Posting billing Document from SD to FI,   I am getting error as mention below
    " The system tried to read the product cost estimate for product 20000050 using the costing variant YPC1 and the costing version 01.
    However, the product cost estimate has the status KF, which means that it contains errors. Therefore the cost estimate is not valid."
    Kindly suggest any solution
    Regards
    FI

    Hi Friend,
    For that product you dont have the valid cost estimate, that's why the recent cost was not updated to the material master. And at the same time, system is telling that you have a standard cost estimate with errors. Go to CKR1 and remove the cost estimate and create a new one without erros. Then post billing document.
    Sateesh Kumar

  • BOM Cost Estimate for sales order items

    Hi experts,
        Which data source could extract data created by CK51N (Order BOM Cost Estimate )? We need to get BOM Cost estimate (including input material and activity) for sales order items.
        The closest one is 0CO_PC_01, but it extracts itemizations for production order.
        It's urgent.Helpful answers would be awarded.Thanks.
    Regards,
    Aaron

    Hi Henry,
       They even do not have Sales Order segment. How could I get cost estimate data based on sales order?
    Regards,
    Aaron

  • Cost estimate for sales order

    Dear Friends,
    In a make to stock scenario a finished good is sold from the depot and thereafter it is returned. After creating the credit memo for return, when the same is being released to accounting in VF02, the system throws an error message which reads 'Error reading the material cost estimate for sales order "12000373". and the document cannot be passed on to accounting. Although, we are able to release the sales invoice to accounting without any error. In the item condition tab for sales order the standard cost VPRS is updated as we enter the plant.
    Strategy group for the material is 40-planning with final assembly. The concern over here is that why the system is asking for cost estimate at the level of sales return.
    Please suggest why this error is coming and how the same can be released to accounting.
    Regards

    Hello Friend,
    The problem is that Material you are using for that Cost Estimate is not done. So go to T.Code CK11 give the Costing Variant, Material & Plant and go on entar and entar. If everything is green in end then save it.
    Then Go to T.code CK24 give the Company Code, material & Plant and then execute.
    Click Back and click on Release Button and then execute.
    Then try the Transaction you have got the error again.
    Hope this helps.

  • Cost object for raw material consumption posting

    the raw material cosumption posting is done in the background when the goods issue is done. so where do we assign cost object for the primary cost element of raw material consumption account. since we create primary cost element for raw material consumption account, it will expect us to give cost object, so where we assign cost object for the raw material consumption cost element

    hi
    since the raw material cost is relevent for cost accounting u need to maintain primary cost elment accounts.When ever u confirm goods, the rm issue will take place automatically and will be debited to either product cost collector or production order. so u need not to assign any cost object for these consumption accounts why bcoz issues will take palce aganist a production order or product cost collector which is a cost object .
    regards
    siva

  • Cost variance for the material master

    Hi all,
    This is very urgent requirement.
    How to maintain cost variance for the material master?
    I will assign the points
    venu

    Hi,
    Material Variance key will be assigned in Material master Costing data tab
    Best Regards
    Ashish Jain
    Message was edited by:
            Ashish Bohara

  • How to deactivate  cost estimate for pordcuctin lot

    hi
    we have activated cost estimate for prodcution lot in CKW4, now how to deactive it because of it is activated with costing error , while doing gr it showing costing error, we need to do again costing for porductin lot (wbs) .
    while doing ckw1, it showing already  productin lot has an activated cost estimate.
    how to solve.
    Reg,
    chandu

    Hi  chandu,
    Can you take a look at the note 1507600 which pertains to resetting active production lot costing.
    Regards,
    Declan

  • What are the possible cost objects for raw material consumption postings

    what are the possible cost objects for raw material consumption postings. i want to know whether it can be work order(maintenance order).

    For example, you are confirming a process order and issuing raw materials to the process order, the system in the background creates the consumption posting and will by default use the process order as a cost object.
    Similarly, when you are issuing materials to a work order, you will use MB1A and with movement type 261 and the system prompts you to enter the order number.  If you are using movement type 201, then the system prompts you to enter the cost center and so on.
    Thanks,
    Madhav Nanduri

  • Cost estimate for material / plant  is incorrect

    Dear Gurus,
    While creating material cost estimate with quantity structure the above error occurs.
    Please let me know the solution for this?
    Regards,
    Ajit

    Dear,
    Please check with your Accounting,Costing datas in the material master .
    Please check with fields like material origin,With Quantity Structure,Variance
    Key,Planned price 1 & date against it.
    Valuation Class,Price control indicator,Origin group,Overhead group(if maintained
    any),Profit center.
    If not solved ,please send the screen shots.
    Regards
    Mangal